Moorefield Construction v. Cooley Construction CA4/3

CourtCalifornia Court of Appeal
DecidedJanuary 5, 2024
DocketG062153
StatusUnpublished

This text of Moorefield Construction v. Cooley Construction CA4/3 (Moorefield Construction v. Cooley Construction CA4/3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moorefield Construction v. Cooley Construction CA4/3, (Cal. Ct. App. 2024).

Opinion

Filed 1/5/24 Moorefield Construction v. Cooley Construction CA4/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

MOOREFIELD CONSTRUCTION, INC.,

Plaintiff and Appellant, G062153

v. (Super. Ct. No. 30-2020-01130607)

COOLEY CONSTRUCTION, INC., OPINION

Defendant and Respondent.

Appeal from a judgment of the Superior Court of Orange County, Nathan R. Scott, Judge. Affirmed. Mahoney & Soll and Richard A. Soll for Plaintiff and Appellant. Law Offices of Gregory J. Hout, Gregory J. Hout; Arias & Lockwood and Christopher D. Lockwood for Defendant and Respondent. * * * General contractor Moorefield Construction Inc. (Moorefield) hired subcontractor Cooley Construction Inc. (Cooley) to perform all the grading work on a construction project. Unforeseen issues arose, and the parties agreed Moorefield would hire a nonparty subcontractor to perform grading on the project in Cooley’s place. According to Moorefield, the nonparty subcontractor was only a temporary replacement. Cooley, however, believed the parties had agreed to terminate the grading subcontract and fully replace Cooley on the project with the new subcontractor. Moorefield later asked Cooley to return to the project and complete grading, but Cooley refused. Moorefield then sued Cooley for breach of contract for failing to complete the grading work. Cooley cross-complained based on Moorefield’s failure to make a retention payment owed under the grading subcontract. The trial court entered judgment in favor of Cooley on both the complaint and cross-complaint. We find substantial evidence supports the judgment and affirm.

I FACTS AND PROCEDURAL HISTORY A. The Construction Project Moorefield was the general contractor on a shopping center project in Perris (the project) owned by Nuevo Perris, LLC (the owner). It agreed to build the project on a cost-plus basis not to exceed $19,128,631.1 Moorefield subcontracted with Cooley to perform all the grading and demolition work on the project (the subcontract). Under the subcontract, it could terminate Cooley’s work on the project at any time and for any reason by written notice.

Generally, “[i]n a ‘cost-plus’ contract, the contractor is paid the cost of its materials, 1

labor, and overhead ‘plus’ either a fixed fee or a percentage of the cost of materials, labor, and overhead as ‘profit.’ It allows the contractor to pass-through to the owner the actual cost of construction while guaranteeing the contractor its profit margin.” (6 Miller & Starr, Cal. Real Estate Forms (2d ed. 2023) § 4:1.)

2 Moorefield agreed to pay Cooley $585,000 for its work. The subcontract also specified that a percentage of this amount would be held as retention during construction. Moorefield would make the final retention payment to Cooley (the retention payment) upon the project’s completion and after Cooley had submitted “all Release of Liens covering [its] work.” Several other paragraphs in the subcontract reiterate that Moorefield was not required to make the retention payment until Cooley gave the required releases. As initially planned, Cooley’s work on the project was to occur in three separate mobilizations. Cooley would demobilize and pull off the job between each one. The initial schedule called for Cooley to be completely finished with the three mobilizations by May 30, 2019. Unforeseen events altered the parties’ initial schedule. As a result, Cooley had to perform work on the project in smaller sections. It had already completed five mobilizations by early May 2019, with about 20 percent of the grading work left to complete. Due to these delays, Moorefield’s project manager, Ted Johnson, spoke by phone with Cooley’s project manager, Michael Patten, on May 9, 2019. On the call, they discussed the impact of the delays and agreed it would be better for Moorefield to bring in another grading subcontractor, Novi Environmental (Novi), to continue the grading work on a time and materials basis. Cooley agreed to send over a credit proposal for the work it had not completed. On May 10, 2019, Patten e-mailed Johnson a summary of their phone call from the prior day. The e-mail explained how various unforeseen circumstances had altered the original grading plan and cost schedule. It explained, “To minimize these time and cost impacts, Moorefield Construction has requested that Cooley Construction provide a cost proposal to credit back the uncompleted work associated with their subcontract. This is so Moorefield Construction can address the remaining grading with

3 their own team [(i.e., Novi]), which will work better with the current construction schedule. This decision is being made solely for the betterment of the project and does not reflect negatively towards Cooley Construction, for lack of performance or quality.” Patten’s e-mail continued, “We are compiling our records for all remaining billable items for the work completed. We are also generating a list of incomplete items that will be included in the proposal for reduction in scope. . . . [¶] Once all items are deemed acceptable by both parties, we will issue one final billing to reflect all outstanding payments to include retention, which is payable upon receipt. [¶] We hope the project finishes well for your team and we look forward to work with Moorefield Construction on another project in the near future.” Johnson replied the same day, writing, “Well stated and I agree with the status of the project. I will add there is no lack of effort on Cooley Construction but rather several unforeseen schedule changes due to delays in approvals from [local utility providers]. Please provide a comprehensive breakdown for the remaining work scope and cost.”2 Novi commenced grading work on the project on May 10, 2019. The parties’ stories diverge from here. Moorefield claims Cooley was still under contract. Novi was only a temporary fill-in while Cooley was unavailable, and it expected Cooley to return to the project to complete grading. In contrast, Cooley maintains the parties agreed to terminate the subcontract and completely replace Cooley on the project with Novi. In June 2019, Moorefield asked Cooley to return to the project to complete grading. Cooley replied that the subcontract had been cancelled on May 10, 2019, and all

2 Johnson and Patten subsequently e-mailed back and forth regarding the amount of the credit Cooley would give Moorefield for the reduced scope of work. While their conversations were fruitful, it does not appear the parties ever agreed on the final credit amount.

4 its grading crews were committed to other jobs and could not return. On June 18, 2019, Moorefield sent Cooley a notice demanding it return to the project to complete grading within 48 hours. Cooley refused, and Moorefield used Novi to finish the grading work. Evidence in the record shows Moorefield paid Cooley $449,408 and Novi $560,000 for their work on the project. Moorefield completed the entire project in November 2019. It billed the owner a total of $18,228,457, which was $900,174 less than the agreed-upon maximum price. However, Moorefield’s grading and demolitions costs were $362,241 overbudget. The budget to complete grading and demolition was $680,000, but the actual cost was $1,042,241. In December 2019, Cooley billed Moorefield for the retention payment in the amount of $51,049.68. Moorefield did not pay.

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry v. Sharma
154 Cal. App. 3d 665 (California Court of Appeal, 1984)
Baypoint Mortgage Corp. v. Crest Premium Real Estate Investment Retirement
168 Cal. App. 3d 818 (California Court of Appeal, 1985)
Jameson v. Five Feet Restaurant, Inc.
131 Cal. Rptr. 2d 771 (California Court of Appeal, 2003)
Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp.
4 Cal. Rptr. 3d 655 (California Court of Appeal, 2003)
Wagner Construction Co. v. Pacific Mechanical Corp.
157 P.3d 1029 (California Supreme Court, 2007)
Marriage of Brandes CA4/1
239 Cal. App. 4th 1461 (California Court of Appeal, 2015)
Vita Planning & Landscape Architecture, Inc. v. HKS Architects, Inc.
240 Cal. App. 4th 763 (California Court of Appeal, 2015)
McDermott Will & Emery LLP v. Superior Court of Orange County
10 Cal. App. 5th 1083 (California Court of Appeal, 2017)
DeLeon v. Verizon Wireless, LLC
207 Cal. App. 4th 800 (California Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Moorefield Construction v. Cooley Construction CA4/3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moorefield-construction-v-cooley-construction-ca43-calctapp-2024.