Board of County Commissioners v. CAM Construction Co.

480 A.2d 795, 300 Md. 643, 1984 Md. LEXIS 331
CourtCourt of Appeals of Maryland
DecidedAugust 24, 1984
Docket95, September Term, 1983
StatusPublished
Cited by6 cases

This text of 480 A.2d 795 (Board of County Commissioners v. CAM Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of County Commissioners v. CAM Construction Co., 480 A.2d 795, 300 Md. 643, 1984 Md. LEXIS 331 (Md. 1984).

Opinion

RODOWSKY, Judge.

Arbitrability is the issue on this appeal. The prime contractor on a building construction project demanded arbitration with the owner. Part of the recovery sought by the prime consists of losses allegedly suffered by subcontractors. Because there is no privity of contract between the owner and subcontractors, the owner denies that the arbitration agreement in the prime construction contract is one to arbitrate “subcontractors’ claims.” We shall reject this contention and hold that the standing of the prime to claim the losses is, at a minimum, sufficient to carry the matter to arbitration.

The project is the new Frederick County Courthouse and Multi-Service Center. By written contract dated November 13, 1978 the Board of County Commissioners of Frederick County (the County), as owner, engaged Cam Construction Company, Inc. (Cam), as contractor, to build the project.’ Part of the integrated contract is the General Conditions of *645 the Contract for Construction as set forth in American Institute of Architects Document A 201-1976. Paragraph 7.9.1 of these general conditions contains an arbitration provision which in relevant part reads:

All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof, ... shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise____ No arbitration shall include by consolidation, joinder or in any other manner, parties other than the Owner, the Contractor and any other persons substantially involved in a common question of fact or law, whose presence is required if complete relief is to be accorded in the arbitration.

By ¶ 17.1.A.2 of special supplementary conditions to the contract, the parties added a provision that

[t]he General Contractor only shall be recognized as a part [sic ] of this Contract and it shall be his responsibility to turn over to the Owner a project complete in all respects and in accordance with the Contract Documents.

On August 11, 1982 Cam demanded arbitration with the County and took the position that the contract had been substantially completed. Attached to the formal demand was a general description of the claims. Cam sought retainage of $491,000 and also an unspecified sum as damages resulting from the owner’s alleged refusal to allow Cam access to the work site. Paragraphs 4 and 5 included the following allegations:

4. During the course of the project, CAM and its subcontractors were continuously delayed and disrupted by actions or inactions which were caused [by] or attributable to the Owner and/or the Architect. The causes of said delays and disruptions are more fully enumerated in Exhibit D.
*646 5. The delays and disruptions enumerated in Exhibit D resulted in additional costs to CAM and its subcontractors in the total amount of $1,660,871.30 for which CAM and its subcontractors are entitled to be renumerated [s¿c]. Said additional costs are more fully itemized in Exhibit D.

Exhibit D to the demand for arbitration is not part of the record on appeal in this case.

The County responded to the demand for arbitration by filing with the American Arbitration Association an answer which denied the material allegations, and filing a counterclaim which asserted breach by Cam. Then, when the County did not furnish certain discovery which Cam sought, Cam brought an equity action against the County in the Circuit Court for Baltimore County. There Cam invoked the Public Information Act, Md.Code (1980 Repl. Vol., 1982 Cum.Supp.), Art. 76A, §§ 1-5A. That issue is not before us on this appeal. The County counterclaimed for an injunction to restrain Cam from proceeding with the arbitration. Injunctive relief was denied and the County appealed. We granted the County’s petition for certiorari and a cross-petition by Cam prior to consideration of the appeal by the Court of Special Appeals. 1

In its argument the County frequently refers to claims made against it by subcontractors as if subcontractors were parties to the arbitration it opposes. With its feet firmly planted on this unsupported premise, the County easily slays a number of strawmen. It says it has no obligation to arbitrate with parties with whom it has not agreed to arbitrate. It says that joinder of subcontractors as additional parties to the arbitration violates If 7.9.1 of the construction contract. All of this is contrary to the record. Only Cam has invoked the particular arbitration proceeding *647 which the County seeks to enjoin. Cam and the County are the only parties to that arbitration. All of the claims made against the County are asserted in the name of Cam.

The County’s argument necessarily rests on the fact that some portion of the recovery claimed by Cam will admittedly be for the account of one or more subcontractors. Beyond this, the record leaves us uninformed. We do not know the identity of the subcontractors or the provisions of their construction subcontracts. The record is silent concerning the facts allegedly giving rise to the losses claimed to have been suffered by subcontractors and concerning the legal theory under which Cam says the County is responsible for those alleged losses. While counsel for Cam advised at oral argument that there are “liquidating agreements” between Cam and subcontractors, respectively, which deal with the relationship of the Cam-invoked arbitration to those claims in which the respective subcontractors are interested, those agreements are not before us. Against the backdrop of this record, the issue narrows to whether Cam has standing to present in its name in arbitration against the County claims for the benefit of subcontractors.

It is clear that the concept of privity is not an absolute bar to a suit brought by a prime contractor against the owner for damages as to which a subcontractor is the real party in interest. In point is United States v. Blair, 321 U.S. 730, 64 S.Ct. 820, 88 L.Ed. 1039, reh’g denied, 322 U.S. 768, 64 S.Ct. 1052, 88 L.Ed. 1594 (1944), which arose out of the construction of a building for the Veterans’ Administration. The prime contractor claimed for the use of a subcontractor who had performed extra work, a characterization with which the contracting officer agreed. The subcontract did not expressly indicate whether the contractor was liable to the subcontractor for the acts of the Government which were the basis for the claim. The contractor had not paid the subcontractor for the latter’s additional costs. On the appeal by the Government from *648 judgment by the Court of Claims in favor of the prime contractor, the Supreme Court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Alamo Community College District v. Browning Construction Co.
131 S.W.3d 146 (Court of Appeals of Texas, 2004)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
480 A.2d 795, 300 Md. 643, 1984 Md. LEXIS 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-county-commissioners-v-cam-construction-co-md-1984.