J. W. Bateson Co. v. United States

163 F. Supp. 871, 143 Ct. Cl. 228, 1958 U.S. Ct. Cl. LEXIS 171
CourtUnited States Court of Claims
DecidedJuly 16, 1958
DocketNo. 161-55
StatusPublished
Cited by12 cases

This text of 163 F. Supp. 871 (J. W. Bateson Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. W. Bateson Co. v. United States, 163 F. Supp. 871, 143 Ct. Cl. 228, 1958 U.S. Ct. Cl. LEXIS 171 (cc 1958).

Opinion

LaRamoke, Judge,

delivered the opinion of the court:

This suit is brought by the J. W. Bateson Co., Inc., on its behalf and that of its subcontractor, the Texas Housing Company, for the increased costs sustained by Texas Housing when the defendant terminated the prime contract for the convenience of the Government. Under this court’s decision in Donovan Construction Co. v. United States, 138 C. Cls. 97, cert. denied 355 U. S. 826, a prime contractor may bring suit on behalf of the subcontractor where the contract between those parties does not negate liability for increased costs occasioned by the acts of the Government. The evidence in this case does not show that the contract between Bateson and Texas Housing contained any exculpatory provisions and therefore this action may be maintained.

On February 19, 1953, plaintiff entered into a contract with the defendant, acting through the Public Housing Administration, hereafter referred to as the PHA, to furnish the labor, equipment, materials and services necessary for the construction of 430 individual prefabricated 3-bedroom dwelling units, nine laundry buildings, and one community building at Camp Breckenridge, Kentucky, complete with all utility connections and site improvements. Following the award of the contract, plaintiff issued a purchase order to Texas Housing to furnish and deliver to the site the structures called for under the prime contract. The shipping schedule called for the completion of deliveries by July 17, 1953.

On Friday, May 8, 1953, the defendant, pursuant to a provision of the contract, terminated all work in connection [230]*230with the project and so notified the plaintiff. Plaintiff in turn notified Texas Housing to cease production with respect to the prefabricated buildings for the Camp Breckenridge project. At this time there were 81 dwelling units erected at Camp Breckenridge and. 44 additional units had been ¡shipped by Texas Housing to the job site. Immediately thereafter, negotiations were entered into between plaintiff and the Government contracting officer for the reinstatement and continued fabrication of the terminated buildings. On Monday, May 11,1958, the defendant ordered the 44 units not yet erected at Camp Breckenridge to be shipped to Camp Pickett, Virginia, where plaintiff had a general contract calling for the erection of 250 units. Plaintiff was also instructed to obtain the remaining 206 units from Texas Housing for shipment to Camp Pickett which left a balance of 99 units to be cancelled. Later, the 99 units were reinstated and shipped to Piketon, Ohio, for installation at another PHA. project there.

Texas Housing completed delivery of the units for the Camp Pickett project on July 29,1953, and made final shipment of the 99 units to Piketon on October 10,1953.

It is plaintiff’s contention that Texas Plousing suffered increased costs in the production of the prefabricated units which increases were caused by the defendant’s termination and partial reinstatement of the contract. It is claimed that the extension of the delivery period from July to October 1953, prevented Texas Housing from maintaining continuous manufacturing operations which resulted in standby expenses and make ready and starting costs. A claim for these costs was presented to the PHA and was denied by the director of the Atlanta field office. The determination of the director was appealed under the disputes clause of the contract to the head of the agency which again resulted in a denial of the claim for work stoppages. Plaintiff was, however, allowed $8,506 on account of storage expense incurred by Texas Housing with respect to the 99 units bound for Piketon. Plaintiff has not received the $8,506 award and there is also due and owing it the sum of $6,296.30 pursuant to change order G-8.

[231]*231The commissioner of this court who heard, received, and carefully evaluated the evidence in this case, found that plaintiff has failed to substantiate its claim that Texas Housing suffered additional costs due to work stoppages, or otherwise, as a result of any action on the part of the defendant. The details showing a failure of proof by plaintiff on this issue are to be found in the trial commissioner’s findings which we adopt. The action of the head of the agency in denying plaintiff’s claim is final under the circumstances. Volentine and Littleton v. United States, 136 C. Cls. 638; Fehlhaber Corp. v. United States, 138 C. Cls. 571, cert. denied 355 U. S. 877.

Plaintiff is entitled to recover $6,296.30 under change order G-8, and $8,506 on account of the claim of Texas Housing for storage expense. Judgment will be entered for the plaintiff in the amount of $14,802.30.

It is so ordered.

Madden, Judge; Whitaker, Judge; Littleton, Judge; and Jones, Chief Judge, concur.

EINDINGS OP PACT

The court, having considered the evidence, the report of Commissioner Marion T. Bennett, and the briefs and argument of counsel, makes findings of fact as follows:

1. Plaintiff, J. W. Bateson Company, Inc., is a corporation organized and existing under the laws of the State of Texas with its principal place of business in Dallas and is engaged in business as a general contractor.

Plaintiff brought this suit on its behalf and on that of its subcontractor, the Texas Housing Company, a division of the New Mexico Housing Company, which is engaged in the manufacture of prefabricated houses with its principal plant in Dallas, Texas.

2. On February 19, 1953, plaintiff entered into a contract, No. R(G)DH-DEV-28, with the defendant, acting through the Public Housing Administration, to furnish the labor, equipment, materials and services necessary for the construction of 430 individual, prefabricated, three-bedroom dwelling units, nine laundry buildings and one community building [232]*232at Camp Breckinridge, Kentucky, complete with all utility connections and site improvements, for a consideration of $2,398,000.

3. Special conditions of the contract specifications provided that work should commence on the date stipulated in the notice to proceed and that groups of dwelling units should be progressively completed, suitable and ready for occupancy, including utilities, sidewalks and driveways, within 130 calendar days for the first 150 units, 180 days for 300 units, and 200 days for the total of 430 dwellings, with an additional 60 calendar days allowed for completing the landscaping. Liquidated damages for each calendar day of delay in completing the work were specified as one dollar a day for each dwelling, $15 a day for other construction and installations, and $10 a day for landscaping. The contract was terminated, as hereinafter reported, and no liquidated damages were assessed.

4. The general conditions of the specifications provided in part:

9. CHANGES IN THE WORK:
(a) Government representatives shall have no authority to alter the terms or conditions of the Contract Documents without written authority from the Contracting Officer.
(b) In determining the value of any change, either additive or subtractive, the Contracting parties are restricted to the use of the three following methods, singly or in combination. Method (1) shall be used to establish the equitable value of the change in every case where it can be fixed prior to performance of the changed work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kentucky Bridge & Dam, Inc. v. United States
42 Cont. Cas. Fed. 77,404 (Federal Claims, 1998)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
Board of County Commissioners v. CAM Construction Co.
480 A.2d 795 (Court of Appeals of Maryland, 1984)
Gardner Displays Co. v. United States
171 Ct. Cl. 497 (Court of Claims, 1965)
Gardner Displays Company v. The United States
346 F.2d 585 (Court of Claims, 1965)
Garod Radio Corporation v. The United States
307 F.2d 945 (Court of Claims, 1962)
Garod Radio Corp. v. United States
158 Ct. Cl. 596 (Court of Claims, 1962)
Union Painting Co. v. United States
194 F. Supp. 803 (D. Alaska, 1961)
St. Paul Dredging Co. v. State
107 N.W.2d 717 (Supreme Court of Minnesota, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
163 F. Supp. 871, 143 Ct. Cl. 228, 1958 U.S. Ct. Cl. LEXIS 171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-w-bateson-co-v-united-states-cc-1958.