Blount Brothers Construction Company v. The United States

346 F.2d 962, 171 Ct. Cl. 478, 1965 U.S. Ct. Cl. LEXIS 128
CourtUnited States Court of Claims
DecidedJune 11, 1965
Docket443-60
StatusPublished
Cited by90 cases

This text of 346 F.2d 962 (Blount Brothers Construction Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount Brothers Construction Company v. The United States, 346 F.2d 962, 171 Ct. Cl. 478, 1965 U.S. Ct. Cl. LEXIS 128 (cc 1965).

Opinion

PER CURIAM.

This is a contract case presented to this court on the record made before the Armed Services Board of Contract Appeals. The case was initially referred to Trial Commissioner C. Murray Bernhardt, who recommended that the plaintiff recover. The parties have submitted further briefs and oral argument has been had before the court. The court agrees with the commissioner that the contractor is correct in its interpretation of the contract. The court also rejects certain defenses, not going to the merits, which the Government has raised. We hold, therefore, that plaintiff is entitled to recover and that the amount of recovery should be determined under Rule 47(c).

I.

The issue is whether specifications and drawings incorporated in the plaintiff’s 1956 Navy contract for building the David Taylor Model Basin at Carderock, Maryland, required the bottom concrete slab of the 322' x 202' maneuvering basin to rest completely on concrete fill and/or natural rock; or whether portions of the slab were reasonably inferred to rest on soil. The rock line actually encountered was found to lie substantially lower than the levels interpolated by the Government from its core borings. We are not concerned with the concrete fill poured by plaintiff’s subcontractor under a change order to bring the actual rock line up to the levels erroneously plotted by the Government from its core borings, for this was performed and paid for as an extra. We are concerned with the concrete fill installed by the plaintiff at the Government’s direction to replace some 3,146 cubic yards of excavated muck and sand separating the hypothetical subsurface rock line erroneously diagrammed in the Government drawings, and the concrete slab prescribed by the drawings.

In the course of performance, disputes arose as to whether the contract plans and specifications required the plaintiff to (a) encase a number of concrete buttress footings in rock and/or concrete fill, and (b) replace with concrete fill all soil excavated between the theoretical rock line and the bottom of the maneuvering basin slab. In March 1957 the contracting officer ruled against the plaintiff on both disputes. His ruling on the latter dispute was as follows:

After a full review of the facts presented, the Contracting Officer determines that no conflict is apparent between the contract drawings and specification and further that *964 the drawings clearly indicate that the Basin slab must rest directly on rock, or on lean concrete where the elevation of the rock is lower than the bottom of the slab. Therefore, the position taken by you, that you are not required to provide concrete fill, other than in areas where over excavation of rock has occurred, is considered untenable.
Accordingly, and for the foregoing reason, your claim in the amount of $99,099.00 is hereby denied. This is a final decision of the Contracting Officer.

The plaintiff appealed both adverse decisions to the Armed Services Board of Contract Appeals, which held a hearing. On June 11, 1959, the Board sustained plaintiff’s appeal relating to the buttress footings, 1 and denied the other claim for concrete fill under the maneuvering basin slab, whereupon the plaintiff filed its present petition.

The issue before us is one of law — whether the specifications and drawings required concrete fill in those areas in which the Board denied the plaintiff’s claim. The Board dealt with this question as one of law, and in the main rested its decision on its view of the terms of the contract and the requirements of the drawings, not on disputed issues of fact. Since the question of contract interpretation is one of law, we are not bound by the Board’s understanding of the contractual obligations, but may decide the matter for ourselves. 41 U.S.C. § 322; C. J. Langenfelder & Son, Inc. v. United States, Ct.Cl., 341 F.2d 600, 609, decided Feb. 19, 1965; Kaiser Industries Corp. v. United States, Ct.Cl., 340 F.2d 322, 333-334, decided Jan. 22, 1965. 2 As will appear from Part III of this opinion, infra, only one aspect of the Board’s opinion which is significant to the resolution of the legal question can be characterized as a determination of a disputed factual issue, i. e. a symbol for concrete on the drawings. To the extent the Board relied on its finding on that point, its decision is unsupported by substantial evidence and must be rejected. The other factual findings of the Board are accepted; the court is not substituting its own view of the facts. See Morrison-Knudsen Co. v. United States, Ct.Cl., 345 F.2d 833, decided May 14, 1965. We decide the legal issue on the basis of the Board’s factual findings — except for the one finding, already mentioned, which we hold not to be adequately supported — and on the basis of those facts conclusively shown by the Board record. 3 These facts are found in the commissioner’s opinion, as approved by the court. Accordingly, there is no occasion to remand the case to the trial commissioner as defendant asks. The court can decide the legal issue and thus dispose of the case, at the present stage. 4

II.

Defendant urges that the plaintiff, the prime contractor, is barred by the doctrine of Severin v. United States, 99 Ct.Cl. 435, 442-444 (1943), cert. denied, 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1944), from recovering on behalf of its subcontractor (Whittington & Brown Co., Inc.) which actually did the work. The argument is that the subcontract exculpated the plaintiff from all *965 liability on this score. We hold, however, that the Government has failed to show that there was any pertinent exculpatory clause in the subcontract. That agreement provided that the “Contractor shall not be liable to the Sub-Contractor for delay to Sub-Contractor’s work by the act, neglect or default of the Owner [i. e., the Government], * * *” (Article III (d)). 5 But plaintiff does not seek in this action to recover delay damages; this suit is solely for an equitable adjustment for the additional expense incurred as a result of an alleged change ordered by the contracting officer. The subcontract does not embody any exculpatory clause relating to such adjustments for additional work ordered by the contracting officer but not compensated for by the defendant because believed to be within the original terms of the contract. Article IV deals with compensation for admitted changes ordered by the defendant and accepted by the prime, but the article contains no express exculpatory clause at all, 6 and certainly there is nothing in it absolving the prime from liability for extra work (performed by the subcontractor) on which the Government insists but for which it refuses any compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IMC Construction Group
Armed Services Board of Contract Appeals, 2023
Command Languages, Inc. d/b/a CLI Solutions
Armed Services Board of Contract Appeals, 2020
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
T.W. Laquay Marine, LLC v. United States
127 Fed. Cl. 748 (Federal Claims, 2016)
BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
Per Aarsleff A/S v. United States
121 Fed. Cl. 603 (Federal Claims, 2015)
Visual Connections, LLC v. United States
120 Fed. Cl. 684 (Federal Claims, 2015)
Otis Elevator Company v. WG Yates & Sons Construction Company
589 F. App'x 953 (Eleventh Circuit, 2014)
Guzar Mirbachakot Transportation v. United States
104 Fed. Cl. 53 (Federal Claims, 2012)
Chapman Law Firm, LPA v. United States
103 Fed. Cl. 28 (Federal Claims, 2012)
Northrop Grumman Computing Systems, Inc. v. United States
99 Fed. Cl. 651 (Federal Claims, 2011)
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Valley Realty Co. v. United States
96 Fed. Cl. 16 (Federal Claims, 2010)
States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
346 F.2d 962, 171 Ct. Cl. 478, 1965 U.S. Ct. Cl. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-brothers-construction-company-v-the-united-states-cc-1965.