Western Contracting Corp. v. United States

144 Ct. Cl. 318, 1958 U.S. Ct. Cl. LEXIS 121, 1958 WL 7348
CourtUnited States Court of Claims
DecidedDecember 3, 1958
DocketNo. 344-55
StatusPublished
Cited by30 cases

This text of 144 Ct. Cl. 318 (Western Contracting Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Contracting Corp. v. United States, 144 Ct. Cl. 318, 1958 U.S. Ct. Cl. LEXIS 121, 1958 WL 7348 (cc 1958).

Opinion

Opinion

per curiam:

This is an action brought by plaintiff contractor for damages alleged to have resulted from defendant’s breach of a construction contract. The case was referred pursuant to rule 45 (a) to W. Ney Evans, a trial commissioner of the court, with directions to make findings of fact and recommendations for conclusions of law to which this court should arrive.

Accordingly, Commissioner Evans has submitted his findings of fact and a recommendation that the court adopt the [320]*320conclusion as a matter of law that the defendant did in fact breach the subject contract and that as a result thereof plaintiff suffered damage in the amount of $225,000 and is entitled to recover said sum from the United States. The court, after having considered the evidence, the briefs and argument of counsel, agrees that the defendant breached the contract for which it must stand liable.

In his determination as to the amount of damage suffered by the plaintiff, Commissioner Evans based his conclusions upon, “an inference drawn from the evidence as a whole, being in the nature of a jury verdict.” We are of the opinion that the Commissioner was correct in determining damages based upon his judgment arrived at by a studied consideration of the record before him. This court has many times held that the measure of damages is not an exact science calling for a hard and fast rule, but is a determination based upon the facts and circumstances of each case. As we said in Needles v. United States, 101 C. Cls. 535, 618:

* * * The breach is the standard by which the compensation is to be measured, and all that the law requires is that such damages be allowed as, in the judgment of fair men, directly and naturally resulted from the breach of the contract for which the suit is brought.

See also, First-Citizens Bank & Trust Co. v. United States, 110 C. Cls. 280, 326; Chalender v. United States, 127 C. Cls. 557, 566; Houston Ready-Cut House Co. v. United States, 119 C. Cls. 120, 193. On the authority of the principle announced in the above-cited cases we approve the Commissioner’s conclusion that plaintiff was damaged to the extent of $225,000.

The findings of fact and conclusions of law of the Commissioner are hereby adopted and made the basis of the court’s judgment in this case. It follows that plaintiff is entitled to recover of and from the United States the sum of $225,000, and judgment will be entered to that effect.

It is so ordered.

OPINION OE THE COMMISSIONER

The contract in suit covered Earthwork, Stage III, in the construction of Fort Randall Dam, an earth-filled mul[321]*321tiple purpose dam across the Missouri Kiver in South Dakota, built (under contracts) by the Corps of Engineers of the Army. As initially planned the estimated cost of the project was $200 million, and the anticipated construction period was nine years.

The earthwork was divided into four stages, with a separate contract for each stage. Plaintiff was the successful bidder for each of the four earthwork contracts. Other contractors were responsible for the construction of the concrete portion of the dam, which included the control works.1

Plaintiff satisfactorily completed the work on each of its contracts, and on the schedule required by defendant. The present controversy arose out of the scheduling which defendant required for the performance of the Stage III contract.

During the working season of 1949 plaintiff was engaged in the performance of the Stage II contract. This work was completed before the end of the year.

Meanwhile, the Corps of Engineers was preparing the specifications for the Earthwork Stage III contract, which was to include the crucial operations of diverting and closing the river.

Diversion of the river required the completion of the approach and discharge channels, already partially excavated, the removal of four “plugs” (narrow, unexcavated areas, two upstream and two downstream from the control works, retained to keep water away from the control works and to provide access roads and ramps), and the construction of a dike across the normal channel of the river to force the water into the approach channel.

Closure of the river required the construction of a permanent embankment of substantial size (as part of the earth-filled dam) across the old or normal channel of the river.

The flow of the river (its rise and fall) was such that diversion and closure had to be made after the “June rise” and before the ensuing winter months. Once these operations were begun, they had to be completed during the work[322]*322ing season to secure the dam from the dangers of over-topping by flood waters.

The preparation of the specifications for the Earthwork Stage III contract was begun early in 1949. At that time the Corps of Engineers intended to issue the invitation for bids shortly after July 1, 1949 (representing the beginning of the Government’s fiscal year 1950), to award the contract as soon thereafter as reasonably might be, to require the Stage III work to be begun on or before March 1, 1950, and to require the diversion and closure of the river to be made in 1951.

In this connection the responsible officers of the Corps of Engineers were fully aware of the advantage in bid-position for the Stage III contract accruing to plaintiff by reason of its mobilization of men and equipment on the job-site in the performance of the Stage II contract. Plaintiff was known to them to be a highly competent construction company. There was never any intention of trying to prevent or preclude plaintiff from bidding on the Stage III contract. The concern of the Engineers was to provide conditions that would assure competitive bidding for the work.

The conclusion they reached was that if the invitation for bids was issued and the contract awarded in 1949 at a date early enough to allow the fall and winter months for mobilization, the situation would be as conducive to competitive bids as could reasonably be expected, considering the fact that plaintiff was on the job-site and partially mobilized for the Stage III work.

As the year 1949 wore on, action was delayed in Congress on appropriations for fiscal 1950. By the end of fiscal 1949, the outlook for appropriations sufficient to maintain the planned schedule of Port Eandall construction was unfavorable. The invitation for bids for Stage III was not issued.

Work proceeded, nevertheless, in the drafting of the Stage III specifications, incorporating the original schedule for completion of the contract work in 1951. In August 1949 the draft specifications were assembled in stencil form and distributed to engineers in the field for review and comment.

By this time it had become apparent to the Corps of Engi[323]*323neers that tibe funds for Fort Eandall construction during fiscal 1950 would probably be less than had been hoped for, and that, in any event, it would no longer be possible to advertise for bids and award a contract early enough in 1949 to assure potential bidders of the fall as well as the winter months for mobilization. Plaintiff’s bid-position advantage would therefore be accentuated unless some further adjustment was made in the scheduling of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Record Steel & Construction, Inc. v. United States
62 Fed. Cl. 508 (Federal Claims, 2004)
L.W. Matteson, Inc. v. United States
61 Fed. Cl. 296 (Federal Claims, 2004)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
California Canners & Growers Ass'n v. United States
9 Cl. Ct. 774 (Court of Claims, 1986)
Balboa Insurance v. United States
31 Cont. Cas. Fed. 71,682 (Court of Claims, 1983)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
J. W. Bateson Co. v. United States
450 F.2d 896 (Court of Claims, 1971)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Maxwell Dynamometer Company v. United States
386 F.2d 855 (Court of Claims, 1967)
Maxwell Dynamometer Co. v. United States
386 F.2d 855 (Court of Claims, 1967)
Johnson v. United States
173 Ct. Cl. 561 (Court of Claims, 1965)
Wallace Process Piping Co. v. Martin-Marietta Corp.
251 F. Supp. 411 (E.D. Virginia, 1965)
Tulelake Irrigation District v. The United States
342 F.2d 447 (Court of Claims, 1965)
Kings Electronics Co., Inc. v. The United States
341 F.2d 632 (Court of Claims, 1965)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
144 Ct. Cl. 318, 1958 U.S. Ct. Cl. LEXIS 121, 1958 WL 7348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-contracting-corp-v-united-states-cc-1958.