Chalender v. United States

119 F. Supp. 186, 127 Ct. Cl. 557, 1954 U.S. Ct. Cl. LEXIS 62
United States Court of Claims·Decided March 2, 1954·No. No. 49091·Published·Cited by 45 cases

Opinion

LittletoN, Judge,

delivered the opinion of the court:

Plaintiff1 sues to recover an alleged loss sustained in the performance of a construction contract with the defendant. The petition is in two counts. Count I seeks recovery under the War Contract Hardship Claims Act,2 also known as the Lucas Act, and Count II is a claim for breach of contract.

Under this contract, which was a lump sum contract entered into with the U. S. Army Corps of Engineers in June 1943, plaintiff was to construct within a period of 61 days an addition or enlargement to the existing water treatment facilities at Camp Gruber, Oklahoma. Defendant was to furnish virtually all of the cast-iron pipe, specials, fittings and valves required in the work. Plaintiff claims that defendant’s delay in furnishing certain of these materials delayed and interfered with the orderly progress of the work upon which plaintiff’s bid was based, thereby causing the work to be done in disorderly sequence and requiring 71 days’ additional time at an increased cost of $88,390.33.

[560] COUNT I

Upon the close of plaintiff’s proof relative to Count I, defendant moved pursuant to Rule 49 (b)3 for a dismissal of that count on the grounds, inter alia, that plaintiff had never made a valid request for relief under the Lucas Act. The commissioner of this court made detailed findings of fact and filed a report recommending that defendant’s motion be granted. On the basis of those findings (findings 2 to 7) and our review of the record, we accept the recommendation of the commissioner and dismiss plaintiff’s claims under Count I of the petition on the ground that plaintiff had never filed with the appropriate department a valid request for relief under the Lucas Act. Throughout all negotiations, plaintiff believed and asserted that the Government, as of right, owed her the amounts claimed. Recovery under the Lucas Act requires that the written request for relief must be such as to apprise the Government that the claim being made was one for extra legal relief outside of any contractual obligation. Fogarty v. United States, 340 U. S. 8; Lawrance Aeronautical Corp. v. United States, No. 48942, decided November 3, 1953. Plaintiff has not met that requirement.

count n

Under Count II of the petition, plaintiff seeks recovery for breach of contract.

The enlargement of the water treatment facilities at Camp Gruber was authorized by the Chief of Enginers on May 14, 1943. The specifications were dated June 2,1943, and plaintiff was advised of the acceptance of its bid by letter of June 16,1943, accepted by plaintiff on June 17,1943. The specifications required that work be commenced within one calender day after receipt of notice of award and be completed on or before August 17, 1943. Since plaintiff accepted the award on June 17, it provided for 61 calendar days for completion of the work. The notice of award was the notice to proceed as well. The work as far as plaintiff was concerned [561] was completed on October 27, 1943, which was a delay in completion of 71 days.

Plaintiff was paid $38,765.58 which consisted of the contract price of $35,210, changes amounting to $55.25 (finding 20), additional cement over that specified in the sum of $341.88 (finding 26) and $3,158.72 for additional work done in correcting leakage of existing structures. (Finding 30.) The total cost to plaintiff under the contract was $77,156.18 (finding 33) which resulted in a loss of $38,390.33, representing the excess cost of performance by reason of delays in the delivery of materials. In addition to asking recovery of this amount, plaintiff also claimed $1,394.83 as representing additional costs entailed in performing alleged extra work. The facts as found by the commissioner of this court do not support these latter claims, and plaintiff has taken no exception to those findings. (Findings 31 and 35.) Therefore, the only loss with which we are now concerned is that which plaintiff alleges was caused by delays of defendant in the delivery of materials.

This contract called for the construction of a settling basin and filter house which were to be added to the already operating water purification system at the camp. Of the two structures, the filter house was the more complex, requiring three floors with installations for the purification of water, a gallery of cast-iron piping running through the floors and connections with adjacent filter structures. It is not disputed that the sole cause of the 71-day delay was the late delivery of materials needed in the construction of the filter house. The settling basin was substantially completed within the contract period. Practically all the material for the filter house was to be furnished by the defendant.

Plaintiff contends, and there is some evidence, that the failure of the Government to effect timely delivery of these materials was responsible for the entire 71-day delay. This, plaintiff alleges amounted to a breach of contract on the part of the defendant, making it liable for the full amount of the loss sustained.

Defendant while admitting that plaintiff sustained a loss of $38,390.33 asserts that, since no negligence on its part has been shown, it cannot be held liable for any part of the loss. [562] Defendant argues that in any event it was responsible for only 14 or 15 days of the delay resulting from the late arrival of materials that it was required to supply, and it further contends that, even assuming liability on its part for causing a particular number of days of delay, plaintiff is still not entitled to recover because of the impossibility of apportioning the amount of the resulting loss between delays chargeable to the Government and those not chargeable to it. We have uniformly held that where the defendant causes delay we will not undertake to apportion the delay unless the evidence is clear.

Free access — add to your briefcase to read the full text and ask questions with AI

Chalender v. United States, 119 F. Supp. 186, 127 Ct. Cl. 557, 1954 U.S. Ct. Cl. LEXIS 62 (cc 1954).

119 F. Supp. 186 (Chalender v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Trinity River Lumber Co. v. United States
66 Fed. Cl. 98 (Federal Claims, 2005)
California Federal Bank v. United States
54 Fed. Cl. 704 (Federal Claims, 2002)
Precision Pine & Timber, Inc. v. United States
50 Fed. Cl. 35 (Federal Claims, 2001)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
John C. Grimberg Company, Inc. v. The United States
869 F.2d 1475 (Federal Circuit, 1989)
Penberthy Electromelt International Inc. v. United States
33 Cont. Cas. Fed. 74,887 (Court of Claims, 1986)
Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
G. C. S., Inc. v. Foster Wheeler Corp.
437 F. Supp. 764 (W.D. Pennsylvania, 1977)
Burgess Construction Co. v. M. Morrin & Son Co.
526 F.2d 108 (Tenth Circuit, 1975)
Koppers/Clough v. United States
201 Ct. Cl. 344 (Court of Claims, 1973)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Luria Brothers & Company, Inc. v. The United States
369 F.2d 701 (Court of Claims, 1966)
L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Luria Bros. & Co. v. United States
369 F.2d 701 (Court of Claims, 1966)