Chalender v. United States

119 F. Supp. 186
CourtUnited States Court of Claims
DecidedMarch 2, 1954
Docket49091
StatusPublished
Cited by36 cases

This text of 119 F. Supp. 186 (Chalender v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chalender v. United States, 119 F. Supp. 186 (cc 1954).

Opinion

*188 LITTLETON; Judge.

Plaintiff 1 sues to recover an alleged loss sustained in the performance of a construction contract with the defendant, The petition is in two counts. Count I seeks recovery under the War Contracts Hardship Claims Act, 2 also known as the Lucas Act, and Count II is a claim for breach of contract.

Under this contract, which was a lump sum contract entered into with the U. S. Army Corps of Engineers in June 1943, plaintiff was to construct within a period of 61 days an addition or enlargement to the existing water treatment facilities at Camp Gruber, Oklahoma. Defendant was to furnish virtually all of the cast-iron pipe, specials, fittings and valves required in the work. Plaintiff claims that defendant’s delay in furnishing certain of these materials delayed and interfered with the orderly progress of the work upon which plaintiff's bid was based, thereby causing the work to be done in disorderly sequence and requiring 71 days’ additional time at an increased cost of $38,390.33.

Count I

Upon the close of plaintiff’s proof relative to Count I defendant moved pursuant to Rule 49 (b) 3 for a dismissal of that count on the grounds, inter alia, that plaintiff had never made a valid request for relief under the Lucas Act. The commissioner of this court made detailed findings of fact and filed a report recommending that defendant’s motion be granted. On the basis of those findings (findings 2 to 7) and our review of the record, we accept the recommendation of the commissioner and dismiss plaintiff’s claims under Count I of the petition on the ground that plaintiff had never filed with the appropriate dapartment a valid request for relief under the Lucas Act. Throughout all negotiations, plaintiff believed and asserted that the Government, as of right, owed her the amounts claimed. Recovery under the Lucas Act requires that the written reQuest for relief must be such as to apprise the Government that the claim be-made was one for extra legal relief outside of any contractual obligation. Fogarty v. United States, 340 U.S. 8, 71 S.Ct. 5, 95 L.Ed. 10; Lawrance Aeronautical Corp v. United States, Ct.Cl., 115 F.Supp. 903. Plaintiff has not met that requirement.

Count II

Under Count II of the petition, plaintiff seeks recovery for breach of contract.

The enlargement of the water treatment facilities at Camp Gruber was authorized by the Chief of Engineers on May 14, 1943. The specifications were dated June 2, 1943, and plaintiff was advised of the acceptance of its bid by letter of June 16, 1943, accepted by plaintiff on June 17, 1943. The specifications-required that work be commenced within one calendar day after receipt of notice of award and be completed on or before August 17, 1943. Since plaintiff accepted the award on June 17, it provided for 61 calendar days for completion of the work. The notice of award was the notice to proceed as well. The work as. far as plaintiff was concerned was completed on October 27, 1943, which was a delay in completion of 71 days.

Plaintiff was paid $38,765.58 which consisted of the contract price of $35,210,. changes amounting to $55.25 (finding 20), additional cement over that specified in the sum of $341.88 (finding 26) and $3,158.72 for additional work done in correcting leakage of existing structures. (Finding 30.) The total cost to plaintiff under the contract was $77,156.- *189 18 (finding 33) which resulted in a loss of $38,390.33, representing the excess cost of performance by reason of delays in the delivery of materials. In addition to asking recovery of this amount, plaintiff also claimed $1,394.83 as representing additional costs entailed in performing alleged extra work. The facts as found by the commissioner of this court do not support these latter claims, and plaintiff has taken no exception to those findings. (Findings 31 and 35.) Therefore, the only loss with which we are now concerned is that which plaintiff alleges was caused by delays of defendant in the delivery of materials.

This contract called for the construction of a settling basin and filter house which were to be added to the already operating water purification system at the camp. Of the two structures, the filter house was the more complex, requiring three floors with installations for the purification of water, a gallery of cast-iron piping running through the floors and connections with adjacent filter structures. It is not disputed that the sole cause of the 71-day delay was the late delivery of materials needed in the construction of the filter house. The settling basin was substantially completed within the contract period. Practically all the material for the filter house was to be furnished by the defendant.

Plaintiff contends, and there is some evidence, that the failure of the Government to effect timely delivery of these materials was responsible for the entire 71-day delay. This, plaintiff alleges amounted to a breach of contract on the part of the defendant, making it liable for the full amount of the loss sustained.

Defendant while admitting that plaintiff sustained a loss of $38,390.33 asserts that, since no negligence on its part has been shown, it cannot be held liable for any part of the loss. Defendant argues that in any event it was responsible for only 14 or 15 days of the delay resulting from' the late arrival of materials .that it was required to supply, and it further contends that, even assuming liability on its part for causing a particular number of days of delay, plaintiff is still not entitled to recover because of the impossibility of apportioning the amount of the resulting loss between delays chargeable to the Government and those not chargeable to it. We have uniformly held that where the defendant causes delay we will not undertake to apportion the delay unless the evidence is clear.

In setting up this work, plaintiff planned a method of opération which was proper and reasonable, wherein the construction of both settling basin and filter house would proceed simultaneously making use of the same work crews. This method saved expense and was reasonable and proper. Plaintiff intended to alternate the different trades from one building to the other as the need required. Thus, most of the workers could be kept on the job' continuously until their ultimate release. The construction of both structures simultaneously, with the workers being shifted from one to the other, was the only possible procedure which could be followed if all work was to be completed within the time required by the contract, and was obviously contemplated by the parties and by the contract. In order to follow this procedure it was necessary that the pipe and related items needed for the filter house, which were to be supplied by defendant, be on hand as the work progressed. In fact, no substantial work could be accomplished at all in connection with the filter house without having the pipe on hand. The installation of this piping was unlike that encountered in the building trade generally, where the plumbing and heating pipes could be provided by merely inserting sleeves through the concrete walls for the placing of the pipes at a later time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
California Federal Bank v. United States
54 Fed. Cl. 704 (Federal Claims, 2002)
Precision Pine & Timber, Inc. v. United States
50 Fed. Cl. 35 (Federal Claims, 2001)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
John C. Grimberg Company, Inc. v. The United States
869 F.2d 1475 (Federal Circuit, 1989)
Penberthy Electromelt International Inc. v. United States
33 Cont. Cas. Fed. 74,887 (Court of Claims, 1986)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
G. C. S., Inc. v. Foster Wheeler Corp.
437 F. Supp. 764 (W.D. Pennsylvania, 1977)
Burgess Construction Co. v. M. Morrin & Son Co.
526 F.2d 108 (Tenth Circuit, 1975)
Koppers/Clough v. United States
201 Ct. Cl. 344 (Court of Claims, 1973)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Luria Brothers & Company, Inc. v. The United States
369 F.2d 701 (Court of Claims, 1966)
L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Luria Bros. & Co. v. United States
369 F.2d 701 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
119 F. Supp. 186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chalender-v-united-states-cc-1954.