Penberthy Electromelt International Inc. v. United States

33 Cont. Cas. Fed. 74,887, 11 Cl. Ct. 307, 1986 U.S. Claims LEXIS 758
CourtUnited States Court of Claims
DecidedDecember 5, 1986
DocketNo. 437-82C
StatusPublished
Cited by4 cases

This text of 33 Cont. Cas. Fed. 74,887 (Penberthy Electromelt International Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penberthy Electromelt International Inc. v. United States, 33 Cont. Cas. Fed. 74,887, 11 Cl. Ct. 307, 1986 U.S. Claims LEXIS 758 (cc 1986).

Opinion

OPINION

BRUGGINK, Judge.

This is an action brought pursuant to the Contract Disputes Act, 41 U.S.C. §§ 601-13 (1982). Plaintiff seeks additional sums under its contract with the Department of Energy (“DOE”). The DOE in turn has counterclaimed. After trial of the action and consideration of post trial briefing, the court finds that each party is entitled to relief on part of its claim.

I. Factual Background

Penberthy Electromelt International, Inc. (“PEI”) is a Seattle, Washington, corporation engaged primarily in the manufacture of glass smelting furnaces. The president of PEI is H. Larry Penberthy (“Penberthy”). Penberthy’s professional background in chemistry, optics, and glass technology have made him a recognized expert in the area of glass furnaces. In addition, he has had experience making lead oxide glass blocks for use as radiation shielding. In 1952, Penberthy formed PEI, in part to market furnaces employing innovative molybdenum electrodes. It was the possible application of this technology to glassification of nuclear wastes which gave rise to the contract at issue here.

In the mid 1960’s, a nuclear processing facility was privately developed in West Valley, New York (“West Valley”). A large quantity of liquid high level nuclear waste was generated and stored at the facility. In the late 1970’s Congress directed DOE to stabilize those wastes.

Penberthy heard about the need to stabilize the West Valley wastes, and had conversations with DOE officials concerning the possible use of glass blocks to contain them. In 1978 PEI conducted small scale test melts. In March 1979, PEI submitted an unsolicited proposal to DOE suggesting a detailed plan for glassifying the West Valley wastes in large quantity.

In response to further conversations with DOE officials, in November 1979, PEI submitted a modification of its March proposal, suggesting that it be limited to a demonstration project. The modification divided the project into seven tasks and estimated that completion of all seven would cost $800,000.00.

Penberthy testified that he received a telephone call approximately February 14, 1980, from either Goetz Oertel or James Turi, both DOE officials, informing him that PEI’s proposal had been accepted. This was confirmed by a letter of the same date. Penberthy further testified that once he received that call, he had no doubt that a formal contract would soon be signed. Similar testimony was given by Dennis Hotaling, Technical Manager of PEL

In the period between receipt of the phone call and letter in February, and the signing in June of a letter contract, PEI ordered certain materials which it anticipated using in performance of the contract. Penberthy and Hotaling both testified that it was necessary to order the proper refractories and electrodes as early as possible because they were “long lead” items—i.e., that it would take a substantial amount of time for PEI’s source to make them for the project. Penberthy further testified that he had earlier discussed the need to order these items with Turi and Sandra Smith, DOE’s assigned Contract Specialist, and had received no objection from them.

The determination of which electrodes and refractory materials to order was based upon test melts done in a very small furnace during the early months of 1980. These melts were done on the assumption [310]*310that the nuclear wastes at West Valley would be glassified in a matrix made up of sands from that site. Although a decision was later made not to use those sands, the electrodes and refractories ordered based on those early tests were subsequently used in performing the contract.

Between February and June 1980, negotiations were conducted between Penberthy and Hotáling on behalf of PEI, and Sandra Smith and the contracting officer, Donald Gier, for DOE. Smith testified without contradiction that she informed Penberthy and Hotaling that she was a “Contract Specialist” and not a Contract Officer.

On April 3, 1980, PEI submitted a Contract Pricing Proposal for Task I, setting forth the cost elements for the initial phase of the work. The total amount proposed for Task I was $54,500.00. The following day, PEI sent DOE invoices to cover the refractories and electrodes previously ordered. The cover letter to the invoices asked, “Can you arrange to accept these three invoices in advance of completing the contract? This would help us much.”

On June 9, 1980, a letter contract became effective between PEI and DOE. It obligated $112,305.00 to the contract—$50,-000.00 for completion of Task I and $62,-305.00 for the materials previously invoiced. “Understanding” number 5 of the contract stated that the funds obligated to the contract would be the limitation of funds authorized to be expended in performance of the contract. That same understanding required eventual transfer to the defendant of “all materials (including specifications and drawings), and work in progress.”

The letter contract contemplated that it would be superseded by a “definitive contract.” In the interim, PEI was required, within 30 days, to submit a detailed cost estimate program plan and milestone schedule for the remaining tasks.

On August 6, 1980, PEI submitted a revised Contract Pricing Proposal for Tasks 1 through 7, as well as a Cost Plan and a Milestone Schedule. The total estimated cost plus fixed fee for doing Tasks 1 and 2 was $636,569.00. In calculating this amount, in addition to direct labor and material costs, PEI utilized the following percentages:

fixed fee—17.65%
labor overhead—186%
general and administrative (“G & A”) overhead—345%

In none of the documents did PEI indicate that contract work had been done prior to the effective date of the letter contract.

During August and September 1980, an audit was performed on PEI’s pricing proposal at the request of DOE by the Defense Contracting Audit Agency (“DCAA”). The audit was prepared by Keith Lanier, who worked with James Mitchell, PEI’s controller.

On September 5, 1980, DCAA issued its pre-award audit report on PEI’s pricing proposal. Among other things, it concluded that the overhead rates for labor and G & A should be reduced. Specifically, it recommended that G & A overhead be calculated on a base consisting of all direct costs and overhead other than general and administrative expenses, rather than on a base of only direct labor. By using the company’s experience during the first seven months of 1980, the rates for labor and G & A overhead were calculated at 154% and 56% respectively.

The pre-award audit contained the following statement:

[W]e consider that period [January—July 1980] to be representative of the indirect costs that should be incurred during CY’s 1980 and 1981. However, due to the significant fluctuations in PEI’s workload and the attendant fluctuation of its indirect expense rates, we recommend that the contracting officer consider the use of ceiling rates.

Lanier testified that during conversations with Mitchell, they agreed upon the change in PEI’s method of calculating G & A overhead, and upon the use of 154% and 56% as the estimated overhead rates.

On September 6, 1980, an amendment to the letter contract was executed to increase

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OK's Cascade Co. v. United States
97 Fed. Cl. 635 (Federal Claims, 2011)
Best Foam Fabricators, Inc. v. United States
41 Cont. Cas. Fed. 77,143 (Federal Claims, 1997)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,887, 11 Cl. Ct. 307, 1986 U.S. Claims LEXIS 758, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penberthy-electromelt-international-inc-v-united-states-cc-1986.