Best Foam Fabricators, Inc. v. United States

41 Cont. Cas. Fed. 77,143, 38 Fed. Cl. 627, 1997 U.S. Claims LEXIS 148, 1997 WL 409205
CourtUnited States Court of Federal Claims
DecidedJuly 18, 1997
DocketNo. 94-1036C
StatusPublished
Cited by28 cases

This text of 41 Cont. Cas. Fed. 77,143 (Best Foam Fabricators, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Best Foam Fabricators, Inc. v. United States, 41 Cont. Cas. Fed. 77,143, 38 Fed. Cl. 627, 1997 U.S. Claims LEXIS 148, 1997 WL 409205 (uscfc 1997).

Opinion

OPINION

MEROW, Judge.

Following a trial in this action, plaintiff Best Foam Fabricators, Inc. (“Best Foam”) seeks damages from defendant for breach of contract. Best Foam asserts that it entered into a valid and binding contract with the United States, Department of the Navy, Aviation Supply Office (“ASO”), for the production of foam fuel cells for use in Navy helicopters. Best Foam alleges further that the government breached the contract by withholding information Best Foam needed to complete performance and by refusing to recognize the existence of a valid contract. Best Foam seeks damages in the amount of the contract price plus the costs incurred pursuing this action.

Defendant contends that no contract was formed because Best Foam never accepted the government’s offer to contract. Instead, defendant asserts, Best Foam’s purported acceptance was really a counteroffer (which defendant eventually rejected) because it took exception to material terms of the proposed contract. Finally, defendant alleges that even if a valid contract was formed, Best Foam cannot recover because the foam fuel cells Best Foam manufactured pursuant to the contract do not conform to the contract specifications. For the reasons stated below, it is held that a valid and binding contract was formed and that defendant’s nonperformance and unjustified repudiation of the contract constitute a constructive termination of the contract for the government’s convenience. Pursuant to the termination for convenience clause contained in the contract, plaintiff is entitled to recover $395,680.22, plus interest in accordance with the Contract Disputes Act, 41 U.S.C. § 611 (1994).

FACTS

Best Foam is a small, minority-owned manufacturer of foam products located in Chicago, Illinois. Best Foam has manufactured foam products for the government since 1983 and has successfully completed several hundred government contracts. The company qualified as a “small and disadvantaged business” pursuant to section 8(a) of the Small Business Act, 15 U.S.C. § 637(a), from 1985 to September 1994, when it graduated from the 8(a) program.

In 1989, Best Foam began manufacturing “foam fuel cells” for the government. These products are inserted into the fuel tanks of military aircraft to stabilize and contain the fuel so as to prevent or minimize the effects of an explosion if the aircraft crashes or is subjected to gunfire. In 1992, the United States Naval Aviation Depot (“NADEP”) in Pensacola, Florida solicited bids for the production of a prototype set of foam fuel cells for the Navy’s UH-1N/HH-1N helicopter. After competitive bidding, Best Foam was awarded the contract. The contract stated that the prototype set was to be manufactured in accordance with drawings created by another company, American Electronics Laboratories, Inc. (“AEL”). Best Foam produced a set of foam fuel cells using these drawings and submitted it to NADEP for testing. NADEP’s engineers discovered that the cells contained certain dimensional and marking errors indicating that AEL’s drawings were inaccurate. As a result, Best Foam, in conjunction with NADEP’s engineers, developed its own set of drawings which corrected the errors in AEL’s and successfully manufactured the prototype set using its drawings. NADEP subsequently [630]*630awarded Best Foam, on a sole source basis, a follow-up contract for the production of validation and verification sets of foam fuel cells for the UH-1N/HH-1N helicopter. Best Foam also manufactured these two sets using its drawings and successfully completed the contract.

The Navy then decided to procure foam fuel cells for its entire UH-1N/HH-1N fleet. There was an urgent need for the product because many of the helicopters were flying either with older, lower quality foam inserts which were deteriorating or without any foam inserts at all. In fact, many helicopters were grounded because they were not equipped with adequate foam inserts. The procurement was to be conducted by ASO in Philadelphia, Pennsylvania. NADEP’s engineers recommended to ASO that the foam fuel cells be purchased from Best Foam in light of its successful completion of the prototype and validation/verification contracts. No other sources were recommended. Based on NADEP’s advice, by letter dated May 19, 1993, ASO offered the requirement for the foam fuel cells to the Small Business Administration (“SBA”) under the 8(a) program and identified Best Foam as the recommended source. By letter dated June 25, 1993, SBA accepted the offer and authorized ASO to negotiate a contract directly with Best Foam, subject to SBA’s approval.

On July 6, 1993, ASO sent Best Foam a solicitation for 158 sets of foam fuel cells for the Navy’s UH-1N/HH-1N helicopter fleet. The solicitation indicated that the contract would contain the standard inspection system requirements set forth in section 52.246-2 of the Federal Acquisition Regulation (“FAR”), “Inspection of Supplies-Fixed Price,” 48 C.F.R. § 52.246-2 (1993), as well as the higher level inspection requirements contained in provision MIL-1^5208, “Inspection System Requirements.”1 This provision is much more stringent than FAR 52.246-2 and basically requires the contractor to have a detailed and thorough inspection system in place which ensures and substantiates that all goods submitted to the government conform to the contract requirements. The clause makes the contractor responsible for performing all of the inspections and tests necessary to ensure compliance with the contract. However, the government retains the right to determine the adequacy of the contractor’s inspection procedures prior to and during performance pursuant to section 3.1, which states that the contractor’s inspection system “shall be documented and shall be available for review by the Government Representative prior to the initiation of production and throughout the life of the contract.”

Best Foam submitted its proposal in response to the solicitation on July 28, 1993. The proposal identified Best Foam’s part numbers, corresponding to its drawings, as the items to be manufactured. Best Foam proposed a total price of $718,890. Nowhere in its proposal did Best Foam take issue with the proposed inclusion of MIL-I — 45208 in the contract.

In August 1993, ASO and Best Foam engaged in price negotiations. The negotiations were conducted by ASO contracting officer William Ryan, Keith Hasty, president of Best Foam, and Darence Smith, Best Foam’s government sales representative. Although the parties anticipated during the negotiations that production would be spread out evenly over a six month period following contract award, Mr. Ryan repeatedly stated that the Navy urgently needed the foam fuel cells for the reasons stated above. On September 14, 1993, the parties agreed upon a price of $569,795.40 and concluded negotiations. Mr. Smith certified that, as of that date, the cost and pricing data Best Foam submitted were accurate, complete, and current.

On September 17, 1993, Mr. Ryan contacted Keith Hasty and asked if, in light of the government’s urgent need, Best Foam would agree to an accelerated delivery schedule whereby Best Foam would provide 75 sets of foam fuel cells within 60 days of contract award. Mr. Ryan also indicated that he would be forwarding a formal contract to Best Foam within the next few weeks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fluor Intercontinental, Inc.
Armed Services Board of Contract Appeals, 2022
Bowles v. United States
Federal Claims, 2019
Avant Assessment, LLC v. United States
134 Fed. Cl. 323 (Federal Claims, 2017)
Boarhog LLC v. United States
129 Fed. Cl. 130 (Federal Claims, 2016)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
TRG Construction Inc. v. District of Columbia Water & Sewer Authority
70 A.3d 1164 (District of Columbia Court of Appeals, 2013)
Tigerswan, Inc. v. United States
110 Fed. Cl. 336 (Federal Claims, 2013)
NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)
Bearingpoint, Inc. v. United States
82 Fed. Cl. 181 (Federal Claims, 2008)
Praecomm, Inc. v. United States
78 Fed. Cl. 5 (Federal Claims, 2007)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Sweetwater, A Wilderness Lodge LLC v. United States
72 Fed. Cl. 208 (Federal Claims, 2006)
Jacobs Engineering Group, Inc. v. United States
63 Fed. Cl. 451 (Federal Claims, 2005)
Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 77,143, 38 Fed. Cl. 627, 1997 U.S. Claims LEXIS 148, 1997 WL 409205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/best-foam-fabricators-inc-v-united-states-uscfc-1997.