Romala Corporation, a Delaware Corporation v. The United States

927 F.2d 1219, 37 Cont. Cas. Fed. 76,051, 19 Fed. R. Serv. 3d 1065, 1991 U.S. App. LEXIS 3927, 1991 WL 30796
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 12, 1991
Docket90-5134
StatusPublished
Cited by53 cases

This text of 927 F.2d 1219 (Romala Corporation, a Delaware Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Romala Corporation, a Delaware Corporation v. The United States, 927 F.2d 1219, 37 Cont. Cas. Fed. 76,051, 19 Fed. R. Serv. 3d 1065, 1991 U.S. App. LEXIS 3927, 1991 WL 30796 (Fed. Cir. 1991).

Opinion

MICHEL, Circuit Judge.

Romala Corporation appeals the May 18, 1990 judgment of the United States Claims Court dismissing its action under the Contract Disputes Act against the government, in which it contended that in terminating a contract for Romala’s non-performance, the government breached the contract. Romala Corp. v. United States, 20 Cl.Ct. 435 (1990). Because the Claims Court’s findings with respect to the facts at issue were not clearly erroneous, because its interpretation of the contract was correct as a matter of law, and because its application of the correct construction to the found facts involved no error, we affirm. And because Romala’s appeal is frivolous, we impose sanctions pursuant to Fed.R.App.P. 38 and hold Romala and its attorney jointly and severally liable to the government for double its costs.

BACKGROUND

In September, 1984 the United States Postal Service advertised that it was interested in leasing a building in Dragoon, Arizona, to be used as a post office. Romala requested and was sent a bid package, which included drawings and specifications of architectural, plumbing, electrical and other requirements for the proposed facility. On October 11, 1984, Romala responded by submitting an executed copy of the Postal Service's standard form contract, titled “Agreement to Lease,” offering to lease space for a ten-year term and subsequent five-year terms. Romala’s bid, however, deviated from the standard form lease agreement in two respects: First, Romala had struck through all or part of five paragraphs of the general conditions in the form lease. Second, Romala also included with its bid a series of drawings and photo *1221 graphs with a cover letter stating that they were plans of a prototype facility it had constructed for the Postal Service in the past at other locations. The form lease as submitted included a Paragraph 10, unaltered by Romala, which provided in relevant part:

Within 60 days after having received his copy of the “Agreement to Lease” the lessor shall submit four (4) sets of the preliminary plans and specifications as adapted to the specific site by the lessor’s A/E firm. This submittal shall be at the 30% design stage. A final plan review shall be made at the 100% design stage prior to the commencement of construction. (emphasis added.)

Romala’s president discussed the bid with representatives of the Postal Service from the October, 1984 submission date until March, 1985, when the Postal Service accepted Romala’s offer by mailing to Romala an executed copy of the Agreement to Lease. The Postal Service also sent Romala a letter, dated March 28, 1985, stating that the drawings submitted with the bid were being considered as the required 30 percent plans, noting the probable need for their revision, and calling attention to Romala’s obligation to submit plans at the "100 percent design stage” before construction could begin. Romala replied with a letter, dated April 10, 1985, to the effect that it considered what it had already submitted, on its prototype facility, to be 100 percent plans.

The parties began a year-long series of discussions and correspondence aimed at reaching agreement on a set of drawings that could be accepted as 100 percent design stage plans. These efforts failed, and Romala then submitted a claim to the Contracting Officer, who denied the claim and terminated the contract for default.

In September, 1987 Romala filed this suit in the United States Claims Court under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982), alleging that the government’s termination of the contract between the parties amounted to a breach. The Claims Court tried the case and on May 18, 1990 issued its decision holding that because the contract required Romala to submit plans at the 100 percent design stage, and because no plans had been submitted that were adequate to be deemed 100 percent design stage plans, the termination for default was not arbitrary or capricious and thus was not a breach of contract. Romala Corp. v. United States, 20 Cl.Ct. 435, 446-47 (1990). Romala being precluded as a matter of law from recovering, the court dismissed the complaint, and this appeal followed.

Our jurisdiction is based on 28 U.S.C. § 1295(a)(3) (1988).

DISCUSSION

I

The Claims Court interpreted the contract to require submission of plans at the 100 percent design stage. This interpretation reflects the explicit language in paragraph 10 as well as the facts as found by the court, and we hold that it is correct as a matter of law.

It is undisputed that while Romala crossed out some provisions in the standard form contract it submitted to the Postal Service, it did not cross out paragraph 10, quoted above, which contained language specifically providing for submission of one set of plans at the “30 percent design stage” and another set at the “100 percent design stage.” This language was not inconsistent, as Romala seems to argue, with its submission of its prototype plans in its bid: The Claims Court found, and there certainly can be no clear error here, that the cover letter submitted with the bid stated only that the prototype plans were being submitted, not that Romala would not supply more complete plans. Furthermore, Romala does not argue on appeal any clear error in the Claims Court’s finding, based on its weighing of testimony and its inferences from the content and timing of the correspondence between the Postal Service and Romala, that prior to accepting Romala’s bid the Postal Service pointed out to Romala’s president that additional (i.e., 100 percent) plans would still be required. Nor do we find clear error in the Claims *1222 Court’s finding that the prior course of dealing between the parties (which in any event was with other postal officials in other postal regions of the country) was not sufficient to constitute a mutual understanding that Romala’s preliminary plans must always and everywhere be accepted as 100 percent design stage plans.

In light of the factual findings by the Claims Court in this case, we hold that the court’s construction of the contract to require submission of plans beyond those submitted with the bid proposal is correct as a matter of law. The court found, and Romala has not disputed on appeal, that despite adequate opportunity to do so, Romala never submitted more detailed plans. The court thus correctly determined that the Postal Service’s termination of the contract was not arbitrary or capricious. Accordingly, the judgment of dismissal of this suit for breach of contract must be affirmed.

II

Having determined that Romala’s appeal is entirely without merit, we shall now consider whether it lacked an arguable basis, thus making it frivolous within the meaning of Fed.R.App.P. 38. As we noted in our recent decision in Finch v. Hughes Aircraft Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ps Products Inc. v. Panther Trading Co. Inc.
122 F.4th 893 (Federal Circuit, 2024)
Adams v. Hafen
D. Utah, 2024
Hage-Boutros v. Ethika, Inc.
Federal Circuit, 2022
Westech Aerosol Corporation v. 3m Company
927 F.3d 1378 (Federal Circuit, 2019)
Walker v. Health International Corp.
845 F.3d 1148 (Federal Circuit, 2017)
Brendalynne Duncan v. Citimortgage, Inc.
617 F. App'x 958 (Eleventh Circuit, 2015)
Martin v. Essrig
277 P.3d 857 (Colorado Court of Appeals, 2011)
Kendall v. Cudd
2011 Mass. App. Div. 20 (Mass. Dist. Ct., App. Div., 2011)
E-Pass Technologies, Inc. v. 3Com Corp.
559 F.3d 1374 (Federal Circuit, 2009)
Castillo v. Koppes-Conway
148 P.3d 289 (Colorado Court of Appeals, 2006)
State v. Perez
885 A.2d 178 (Supreme Court of Connecticut, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
927 F.2d 1219, 37 Cont. Cas. Fed. 76,051, 19 Fed. R. Serv. 3d 1065, 1991 U.S. App. LEXIS 3927, 1991 WL 30796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/romala-corporation-a-delaware-corporation-v-the-united-states-cafc-1991.