Dick v. United States

82 F. Supp. 326, 113 Ct. Cl. 94
CourtUnited States Court of Claims
DecidedFebruary 7, 1949
Docket48879
StatusPublished
Cited by15 cases

This text of 82 F. Supp. 326 (Dick v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dick v. United States, 82 F. Supp. 326, 113 Ct. Cl. 94 (cc 1949).

Opinions

JONES, Chief Judge.

Plaintiff sues for the value of two propellers, spare parts and patterns furnished the United States Coast Guard, the value of which he alleges to have been $59,275.

[327]*327Briefly the petition alleges that during the period involved the Coast Guard was under the jurisdiction of the Navy; that prior to 1944 the Navy and the Coast Guard jointly designed a new type of propeller for use on icebreaking vessels; that on June 30, 1944, the plaintiff agreed to manufacture and furnish to the Navy one shipset of the new propeller equipment including two propellers, spare blades and hubs, the price being $55,096.70, the equipment to be manufactured in accordance with a designated Coast Guard plan. Then on July 21, 1944, by contract, the plaintiff agreed, for the sum of $19,556, to manufacture the bow components of the new propeller equipment. This contract also specified that the equipment should be manufactured in accordance with the specified Coast Guard plan with the exception of certain modifications. These two contracts resulted in a price of $74,753.80 for one complete shipset of the new propeller equipment. About these contracts there is apparently no dispute.

On December 26, 1944, the United States Coast Guard headquarters in Washington, D. C., requested a bid on similar new propeller equipment. The following appeared on the first page of the negotiations:

“Telegraphic bid requested, to be confirmed by mail using this bid form.”

The requirements, listed on the third page of the negotiation, were described as follows:

“Item No. Description Quantity Unit Price Total

“1. Propellers, each set consisting of (1) left hand propeller, (1) right hand propeller, (3) spare blades for right hand propeller, (1) spare propeller hub for right hand propeller, (3) spare blades for left hand propeller, and spare propeller hub for left hand propeller.

2 sets

All as indicated on Coast Guard Plan No. 96-CR-4400-4 Alteration O. The above propellers and blades to be complete .with additional items as covered by list of materials (quantities for one ship) as indicated on the above mentioned plan. Finish, dimensions and materials shall be in accordance with all requirements of the Coast Guard Plan, 96-CR-4400-4.

2. Propellers, two (2) left hand, complete with (3) spare blades for each of two propellers and all additional items as indicated in list of material on Coast Guard Plan No. 96-CR-4400-5. The dimensions, finish, and materials shall all be as required on Coast Guard Plan 96-CR-4400-5.

2 sets”

This negotiation or request for bid was submitted by the Coast Guard to the plaintiff only. It was not submitted to other contractors. There followed considerable telegraphic correspondence. Each of the ■telegrams sent by plaintiff contained some reference to the Navy contract. In his first telegram plaintiff stated “We now have a Navy contract * * * for identical propeller blades * * *.” The telegrams also discussed a conference to be held with one of the Navy officials. On January 10, 1945, the plaintiff, in the belief that the negotiation called for one ship-set of the new propeller equipment, telegraphed the Coast Guard quotations on Item No. 1 for 2 sets for $51,032; item No. 2 $16,911.10. The telegram also stated “This same as Bureau of Ships order less the male and female gauges and patterns.”

In submitting this bid plaintiff made a mistake. He thought he was submitting a bid for one set of 2 propellers and a bow propeller, rather than two sets of 2 propellers and a bow propeller each. There followed several telegraphic communications. Then on February 19, 1945, the Coast Guard headquarters in Washington issued a second negotiation, bearing the same identifying symbols. The plaintiff received the revised negotiation on February 21, 1945. The next day, February 22, 1945, the plaintiff, still under the impression that the negotiation called for one shipset of the new propeller 'equipment, telegraphed the Coast Guard a quoted price of $68,275, which included, in addition to the items in the previous negotiation, a new set of patterns at $4,500. On February 24, 1945, the Coast Guard telegraphed plaintiff that—

“Subject execution formal contract your telegraphic offer of 22 February accepted * * * in amount of 47555 dollars item [328]*328one and 16220 dollars item 2 also set of patterns 4500 dollars * * * Proceed with work * * * acknowledge.”

On February 27, 1945, the plaintiff acknowledged receipt of the order. On March 8, 1945, the Coast Guard sent plaintiff its purchase order in which plaintiff was named as supplier. On March 15, 1945, plaintiff’s assistant manager deposited in the mail for the Coast Guard an acceptance of the purchase order. The following day, March 16, 1945, plaintiff telegraphed the Coast Guard that he had made the mistake of quoting one set instead of two sets, and that the price should be doubled. On March 17, 1945, the Coast Guard sent plaintiff a telegram stating

“Your wire quotation for propellers was confirmed by your formal quotation dated 22 February” and then added

“request letter explanation of prices described as mistake * * * also detailed cost break-down.”

The mailed acceptance apparently did not reach defendant’s officials until about March 21, 1945.

The plaintiff then submitted an explanation of his mistake to Lt. Comdr. Robbins, United States Coast Guard, then contracting officer, who was in charge of the negotiations. At a conference it was stated that it was obvious a mistake had been made and Commander Robbins agreed to a purchase price of $127,550 and stated that the Coast Guard would prepare a formal contract covering the requirements of the negotiation in which the purchase price would be set forth in the amount of the revised quotation, $127,550. Plaintiff’s representative was informed that it would take some time for the formal contract to be prepared and that in view of the urgency of its need for the propellers, defendant desired plaintiff to proceed with the work on the propellers pending.the preparation and issuance of the formal contract Plaintiff, relying on the agreement with the contracting officer, went ahead with the manufacture of the propellers.

On March 31, 1945, the Coast Guard returned to the plaintiff the purchase order referred to above which bore the acceptance of plaintiff as of March 15, 1945.

The Coast Guard prepared a formal contract in which the purchase price was clearly stated to be $127,550. On April 5, 1945, the Coast Guard, after the contract had been approved by its legal division, sent the original and two copies of the formal contract to plaintiff for execution. Plaintiff received them on April 9, 1945, and on the same day executed and returned them to the Coast Guard. In May 1945 the plaintiff learned that the Procurement Legal Division of the Coast Guard had determined that the Coast Guard could not execute the formal contract unless the Comptroller General of the United States ruled that the alleged contract growing out of the telegraphic communications was subject to reformation. Plaintiff prepared and on July 25, 1945, submitted a petition to the Comptroller General for reformation of the alleged contract. The Comptroller General stated that the case had not been previously presented to that office for consideration and plaintiff’s letter afforded no proper basis for action at that time, but that a report was being requested from the Navy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Best Foam Fabricators, Inc. v. United States
41 Cont. Cas. Fed. 77,143 (Federal Claims, 1997)
John Soldau v. Organon Inc., a Delaware Corp.
860 F.2d 355 (Ninth Circuit, 1988)
Worms v. Burgess
620 P.2d 455 (Court of Civil Appeals of Oklahoma, 1980)
Emeco Industries, Inc. v. United States
485 F.2d 652 (Court of Claims, 1973)
G. C. Casebolt Co. v. United States
421 F.2d 710 (Court of Claims, 1970)
G. C. Casebolt Co. v. The United States
421 F.2d 710 (Court of Claims, 1970)
Reserve Insurance v. Duckett
238 A.2d 536 (Court of Appeals of Maryland, 1968)
Morrison v. Thoelke
155 So. 2d 889 (District Court of Appeal of Florida, 1963)
Pacific Alaska Contractors, Inc. v. United States
157 F. Supp. 844 (Court of Claims, 1958)
Slobojan v. United States
136 Ct. Cl. 620 (Court of Claims, 1956)
Rhode Island Tool Company v. United States
128 F. Supp. 417 (Court of Claims, 1955)
Dick v. United States
82 F. Supp. 326 (Court of Claims, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
82 F. Supp. 326, 113 Ct. Cl. 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dick-v-united-states-cc-1949.