Keiland Construction L L C v. Weeks Marine Inc

CourtDistrict Court, W.D. Louisiana
DecidedNovember 16, 2022
Docket2:20-cv-00827
StatusUnknown

This text of Keiland Construction L L C v. Weeks Marine Inc (Keiland Construction L L C v. Weeks Marine Inc) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keiland Construction L L C v. Weeks Marine Inc, (W.D. La. 2022).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAKE CHARLES DIVISION KEILAND CONSTRUCTION L L C CASE NO. 2:20-CV-00827

VERSUS JUDGE JAMES D. CAIN, JR. WEEKS MARINE INC ET AL MAGISTRATE JUDGE KAY

MEMORANDUM RULING Before the court is a breach of contract suit filed by Keiland Construction, LLC (“Keiland”) against Weeks Marine, LLC (“Weeks”). A one-day bench trial was held in this matter before the undersigned on November 7, 2022. Having considered the evidence and applicable law, as well as the post-trial memoranda submitted by the parties, the court now

issues its ruling. I. BACKGROUND This suit arises from Weeks’s early termination of its subcontract with Keiland. Weeks, a New Jersey company, was acting as general contractor at the Venture Global LNG Site in Cameron Parish, Louisiana, and subcontracted work on a storm surge wall at the site to Keiland, a Louisiana company. Keiland began this work pursuant to a Short- Form Construction Subcontract executed with effective date of December 18, 2019. Weeks sent notice of its intent to terminate the work “effective immediately” to Keiland by email

on March 18, 2020, and by undated letter received shortly thereafter. Under the terms of the subcontract, it maintains, this action converted Keiland’s compensation from a lump sum basis to a cost-plus basis for all work performed. Keiland asserted, however, that the termination only converted compensation to a cost-plus basis for work performed between

the notice of termination and the termination and that Weeks failed to pay outstanding sums due under the subcontract. Accordingly, it filed suit in the 38th Judicial District Court, Cameron Parish, Louisiana, raising a claim of breach of contract.1 Doc. 1, att. 1. Weeks removed the matter to this court on the basis of diversity jurisdiction, 28 U.S.C. § 1332. The parties then filed cross-motions for summary judgment on the breach of contract claim, arguing their respective interpretations of the Compensation and

Termination for Convenience sections. Docs. 34, 36. The court found an ambiguity in the terms and denied both motions. Doc. 40. At the request of the parties, the matter was bifurcated for trial with damages deferred until after the contract interpretation issues had been settled. The matter then proceeded to a bench trial before the undersigned on November 7, 2022, at which additional parol evidence was adduced regarding the drafting

of the subcontract. II. FINDINGS OF FACT & CONCLUSIONS OF LAW

A. Evidence Adduced at Trial 1. Subcontract terms Section 5 of the subcontract provides the compensation terms and states: COMPENSATION: As full consideration for the satisfactory performance by SUBCONTRACTOR of this subcontract, CONTRACTOR shall pay to

1 Keiland initially raised claims against Weeks employee Jansson Wurster, but these were dismissed pursuant to a joint stipulation after Weeks raised allegations of improper joinder in its Notice of Removal. Docs. 1, 21. It also raised a claim under the Louisiana Unfair Trade Practices Act, but later dismissed same pursuant to Federal Rule of Civil Procedure 41(a)(2). Docs. 53, 54. SUBCONTRACTOR compensation in accordance with the price terms set forth below.

Description Unit Price Esentist NW Gate Concrete Work | 1 LS | $348,000.00 | $348,000.00 ee ener) 3 LS | $318,375.00 | $318,375.00 SE Emergency Gat 7 ae ne 3 Concrate Work ae $14,225.00 | $14,225.00 |4 _| Access Doors Concrete Work | 6 $2,900.00 __ _ Total: | $698,000.00

All pricing is firm for the duration of the Project. All unit priced quantities listed above are estimated quantities only. Payment will be made in accordance with actual quantities performed by SUBCONTRACTOR and approved by CONTRACTOR. Unit pricing shall remain the same irrespective of final quantities performed. SUBCONTRACTOR shall provide monthly invoices for work completed and payment shall be made within fourteen (14) days of CONTRACTOR’S receipt of payment from OWNER. CONTRACTOR shall be entitled to deduct and retain five percentage (5%) from every SUBCONTRACTOR invoice. Such retained percentage shall be the same as that required under the Prime Contract and shall be released to SUBCONTRACTOR in accordance with the terms of the Prime Contract. As a condition precedent to receiving its monthly payment, SUBCONTRACTOR shall execute a partial release, waiver of lien and affidavit of payment in the form indicated within Appendix E or in the form required under the Prime Contract if direct by CONTRACTOR. In addition, as a condition precedent to SUBCONTRACTOR receiving final payment, SUBCONTRACTOR shall execute a final release, waiver of lien and affidavit of payment in the form indicated within APPENDIX E or in the form required under the Prime Contract if directed by CONTRACTOR. Doc. 87, att. 2, pp. 3-4. Meanwhile, Section 9 provides the rights and duties of the parties upon the contractor’s unilateral termination of the subcontract: TERMINATION FOR CONVENIENCE: CONTRACTOR may, at its option, terminate for convenience any of the Work under this subcontract in whole or in part at any time by written notice to SUBCONTRACTOR. Such notice shall specify the extent to which the performance of the Work is

Page 3 of 10

terminated and the effective date of such termination. Upon receipt of such notice SUBCONTRACTOR shall: 1. Immediately discontinue the Work on the date and to the extent specified in the notice and place no further purchase orders or subcontracts for materials, services, or facilities, other than as may be required for completion of such portion of the Work that is not terminated; 2. Promptly obtain assignment or cancellation upon terms satisfactory to CONTRACTOR of all purchase orders, subcontracts, rentals, or any other agreements existing for the performance of the terminated work or assign those agreements as directed by CONTRACTOR. 3. Assist CONTRACTOR for the maintenance, protection, and disposition of work in progress, plant, tools, equipment, property, and materials acquired by SUBCONTRACTOR or furnished by CONTRACTOR under this subcontract; and 4. Complete performance of such portion of the Work which is not terminated. Upon any such termination initiated by CONTRACTOR, SUBCONTRACTOR shall be entitled to the actual and necessary expense of finishing its Work through the date of termination, the actual and necessary expenses of withdrawing from the Project site, and twenty-one percent (21%) for overhead and profit associated with its Work through the date of termination. Upon any such termination initiated by OWNER, SUBCONTRACTOR shall only be entitled to compensation as provided through the Prime Contract.

Id. at 5. This subcontract was signed by Weeks’ vice president David Hafner and Keiland president Keith DuRousseau. Doc. 87, att. 2. 2. Parol evidence The final paragraph of Section 9 in the Weeks/Keiland subcontract differs from the final paragraph of Section 9 in Weeks’s standard form subcontract, which provides: Upon any such termination, SUBCONTRACTOR shall waive any claim for damages including loss of anticipated profits; on account thereof, but as the sole right and remedy of SUBCONTRACTOR, an equitable adjustment will be agreed between the parties. Doc. 87, att. 1, p. 5. Instead, it more closely resembles the compensation terms under Section 10 (“Termination for Cause”):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omnitech International, Inc. v. Clorox Co.
11 F.3d 1316 (Fifth Circuit, 1994)
Condrey v. Suntrust Bank of GA
429 F.3d 556 (Fifth Circuit, 2005)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Cates v. Sears, Roebuck & Co.
928 F.2d 679 (Fifth Circuit, 1991)
Car Kits, Inc. v. Bolt-On Parts, Inc.
439 So. 2d 479 (Louisiana Court of Appeal, 1983)
Apache Corporation v. W & T Offshore, Incorporated
930 F.3d 647 (Fifth Circuit, 2019)
Whitney Bank v. SMI Companies Global, Inc.
949 F.3d 196 (Fifth Circuit, 2020)
Best Foam Fabricators, Inc. v. United States
41 Cont. Cas. Fed. 77,143 (Federal Claims, 1997)
White Buffalo Construction, Inc. v. United States
52 Fed. Cl. 1 (Federal Claims, 2002)
Praecomm, Inc. v. United States
78 Fed. Cl. 5 (Federal Claims, 2007)
NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)
NCLN20, Inc. v. United States
495 F. App'x 94 (Federal Circuit, 2012)
Praecomm, Inc. v. United States
296 F. App'x 929 (Federal Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Keiland Construction L L C v. Weeks Marine Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keiland-construction-l-l-c-v-weeks-marine-inc-lawd-2022.