Fluor Intercontinental, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 29, 2022
DocketASBCA No. 62550, 62672
StatusPublished

This text of Fluor Intercontinental, Inc. (Fluor Intercontinental, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fluor Intercontinental, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Fluor Intercontinental, Inc. ) ASBCA Nos. 62550, 62672 ) Under Contract No. W912BU-11-D-0003 )

APPEARANCES FOR THE APPELLANT: James A. Hughes, Jr., Esq. Hughes Law PLC Arlington, VA

Andrea L. Reagan, Esq. Donald M. Yenovkian II, Esq. R. Austin Kusnir, Esq. Counsels

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Kyle A. Guess, Esq. John A. Skarbek, Esq. John R. Lockard, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Norfolk

OPINION BY ADMINISTRATIVE JUDGE HERZFELD ON THE GOVERNMENT’S MOTION TO DISMISS AND APPELLANT’S MOTION FOR SUMMARY JUDGMENT

Respondent, the United States Army Corps of Engineers, moves to dismiss part of appellant Fluor Intercontinental, Inc.’s (Fluor) complaint for failure to state a claim upon which relief may be granted. In particular, the agency seeks to dismiss Fluor’s attempt to recover subcontractor Blanchard Machinery Company’s (Blanchard) termination costs because Blanchard estimated some of its costs using an inapplicable cost principle. Fluor cross-moves for summary judgment, asserting that Fluor’s decision to settle with Blanchard was reasonable and, thus, should be awarded all its costs from settling with Blanchard. We find that Fluor has plausibly pleaded a claim for recovery of its subcontractor costs, but that there is a genuine dispute of material fact as to whether and what amount of its costs were reasonable. Thus, we deny both motions. . STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS

On December 3, 2010, the Corps of Engineers awarded an electrical support services multiple-award task order contract to Fluor (Contract) and to a competitor, Inglett and Stubbs Intercontinental (Inglett & Stubbs), for a base one-year period and four, one-year option periods (R4, tab 3 at 93, tab 2 at 8). On February 14, 2011, Fluor entered a subcontract with Blanchard Machinery Company (Blanchard) using a basic ordering agreement (Subcontract) following from a teaming agreement to pursue the Contract (first amended compl. ¶¶ 10-12; app. supp. R4, tab 13 at 307-59 (basic ordering agreement); app. supp. R4, tab 13 at 297-306 (teaming agreement)).

With a closing date of September 25, 2012, the Corps of Engineers issued a task order solicitation and Fluor submitted a proposal to quickly provide leased generators to operate and maintain a 30 megawatt power plant at the airfield in Bagram, Afghanistan (first amended compl. ¶ 24; R4, tab 10 at 232-33). On February 4, 2013, the Corps of Engineers awarded Fluor task order 10 (Task Order) under the Contract and issued a notice to proceed (first amended compl. ¶¶ 4, 29; R4, tab 2 at 42-46). On February 27, 2013, Fluor issued a purchase order to Blanchard to lease generators, switches, and control panels to meet the Task Order requirements (codifying a “verbal/facsimile” agreement on February 18, 2013) (first amended compl. ¶ 17; app. supp. R4, tab 13 at 406-69). Because Fluor would need to provide the government power generating capacity within 60-120 days of the notice to proceed, Fluor had previously authorized Blanchard to purchase, ready, and ship the equipment in September 2012, which Blanchard did (first amended compl. ¶¶ 26-27; app. supp. R4, tab 13 at 95 (indicating the generator acquisition dates); R4, tab 8 at 181 (acknowledging that Blanchard shipped the generators to Dubai)).

On February 27, 2013, the Corps of Engineers issued a stop-work order to Fluor (first amended compl. ¶ 5; R4, tab 4 at 109). On March 18, 2021, Inglett & Stubbs filed a protest with the Government Accountability Office (GAO) challenging the award of the Task Order to Fluor (R4, tab 11 at 248; first amended compl. at 9 n.3). On April 12, 2013, GAO dismissed the protest after the Corps of Engineers took corrective action (R4, tab 11 at 282-83). While taking corrective action, the Corps of Engineers realized that it failed to timely exercise the options under the Contract and, thus, could not use the Contract as a vehicle to issue task orders to obtain these services (R4, tab 6 at 141).

On May 24, 2013, the Corps of Engineers terminated Fluor’s Task Order for convenience (first amended compl. ¶ 5; R4, tab 6 at 143-46). As part of the convenience termination notice, the Corps of Engineers directed Fluor to cease all activities and discussed procedures for submitting a termination settlement proposal (R4, tab 6 at 143-46). Additionally, the Corps of Engineers specifically reminded Fluor of the contractor’s obligations to its subcontractors: “You remain liable to your subcontractors and suppliers for proposals arising because of the termination of their subcontracts or

2 orders. You are requested to settle these settlement proposals as promptly as possible. For purposes of reimbursement by the Government, settlements will be governed by the provisions of Part 49” (R4, tab 6 at 144).

The Contract incorporated by reference two Federal Acquisition Regulation (FAR) standard termination for convenience provisions: (1) FAR 52.249-1, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM) (APR 1984); and (2) FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (MAY 2004) (first amended compl. ¶ 72; R4, tab 2 at 31). Additionally, the Contract included two clauses requiring Fluor to flow down certain other FAR and Defense Federal Acquisition Regulation Supplement (DFARS) clauses to subcontractors providing commercial items: (1) FAR 52.244-6, SUBCONTRACTS FOR COMMERCIAL ITEMS (APR 2010); and (2) DFARS 252.244-7000, SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL COMPONENTS (DOD CONTRACTS) (AUG 2009) (first amended compl. ¶ 59; R4, tab 2 at 30-31). FAR 52.244-6 otherwise discourages flowing down more clauses in commercial items subcontracts, but states, “Contractor may flow down to subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.” FAR 52.244-6(c)(2).

Fluor flowed down the two commercial items subcontract clauses to Blanchard in the purchase order (first amended compl. ¶ 20; app. supp. R4, tab 13 at 423). 1 However, as permitted by these two clauses, Fluor also flowed down the short form Termination for Convenience clause to Blanchard as part of the Subcontract, including the entire FAR provision:

As prescribed in the FAR 49.502(a)(1), insert the following: “The Contracting Off[ic]er, by written notice, may terminate this contract, in whole or in part, when it is in the Government’s best interest. If this contract is terminated, the rights, duties, and obligations of the parties, including compensation to the Contractor, shall be in accordance with Part 49 of Federal [A]cquisition [Regulation] in effect on the date of the award of this contract.”

(First amended compl. ¶ 15 (quoting DFARS 52.249-1); app. supp. R4, tab 13 at 318 (same)) The Subcontract included several forms with terms and conditions, including an

1 The supplemental appellant’s Rule 4 file includes two tabs labeled as “13.” We have labeled the second as “13.2” for ease of reference. Also, we use the pdf page numbers for appellant’s supplemental Rule 4 file because appellant did not add page numbers as we generally require. ASBCA Rule 4(c) (“Any documents without internal page numbers shall have page numbers added.”). 3 additional termination for convenience clause that promised any termination payment “shall be promptly and mutually agreed to” by Fluor and Blanchard (first amended compl. ¶ 16; app. supp. R4, tab 13 at 330).

Fluor submitted a termination settlement proposal (dated December 19, 2013) to the Corps of Engineers seeking $5,179,655 in termination costs (first amended compl. ¶ 42; R4, tab 13; app. supp. R4, tab 13.2 at 4, tab 15 at 1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)
Secretary of the Army v. Tecom, Inc.
566 F.3d 1037 (Federal Circuit, 2009)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
General Dynamics Corporation v. The United States
410 F.2d 404 (Court of Claims, 1969)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
Indiana Michigan Power Company v. United States
422 F.3d 1369 (Federal Circuit, 2005)
Jacobs Engineering Group, Inc. v. United States
434 F.3d 1378 (Federal Circuit, 2006)
PARSONS GLOBAL EX REL. ODELL INTERN. v. McHugh
677 F.3d 1166 (Federal Circuit, 2012)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
H. J. Lyness Construction, Inc. v. United States
121 Fed. Cl. 287 (Federal Claims, 2015)
Federal Contracting, Inc. v. United States
128 Fed. Cl. 788 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Fluor Intercontinental, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fluor-intercontinental-inc-asbca-2022.