General Dynamics Corporation v. The United States

410 F.2d 404, 187 Ct. Cl. 597, 1969 U.S. Ct. Cl. LEXIS 175
CourtUnited States Court of Claims
DecidedMay 16, 1969
Docket161-66
StatusPublished
Cited by9 cases

This text of 410 F.2d 404 (General Dynamics Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Dynamics Corporation v. The United States, 410 F.2d 404, 187 Ct. Cl. 597, 1969 U.S. Ct. Cl. LEXIS 175 (cc 1969).

Opinion

OPINION *

SKELTON, Judge.

The plaintiff, a San Diego, California, based corporation, entered into a cost-plus-fixed-fee contract No. AF04(645)-4 with the United States, on or about January 14, 1955, for the research, development, manufacturing, and testing of the Atlas Intercontinental Ballistic Missile, which later became known as the ICBM’s. The project was engaged in as a crash program so that the first missile could be fired in the spring of 1957. The undertaking was of such magnitude that by 1961 over one billion dollars had been incurred in costs and a fee of nearly sixty-seven million dollars had been earned by the plaintiff contractor.

The plaintiff spent over twenty million dollars building a plant in San Diego, California, to manufacture the system. It became necessary for the plaintiff to build a missile flight facility at Cape Canaveral (later Cape Kennedy), Florida, from which the missiles could be launched and tested. This required it to move hundreds of its highly trained employees from California, to Cape Canaveral, Florida. It began its operations there in August 1955. However, most of the employees arrived at the Cape after January 1, 1956. The payroll records indicate that the number of employees at the Cape at different times were as follows:

January 1956................ 9

June 1956.................. 44

December 1956.............. 206

June 1957.................. 580

August 1957................ 695

January 1960............... 1,113

In the summer of 1955, there was an acute housing shortage at the Cape. Also, there was no potable water supply, no sewage system, few paved roads, and poor schools. There was no FHA financing for houses and the available houses were in bad condition and the rents were high. The plaintiff tried unsuccessfully to interest private financiers and the FHA to finance the building of houses in the area. The plaintiff, as well as the government, had made housing surveys of the Cape and both were fully aware of the existing housing situation.

The plaintiff had planned at first to move only about 300 men to the Cape, but this plan was changed when it decided to have a permanent force there of about 900 men, with at least 300 of them in residence by the middle of 1957. The plaintiff viewed the housing shortage as critical. In September 1955, its opera *406 tion manager at the Cape, a Mr. Byron McNabb, recommended to plaintiff that the only solution was for it to go into the real estate business by building houses it could rent to its employees.

On January 11, 1956, the plaintiff wrote the Air Force at the Cape requesting contract coverage for leasing of permanent type housing, but the Air Force contracting officer refused to agree to it. On April 3, 1956, the contracting officer advised the plaintiff that “the contract does not allow for contractor provided housing at AFMTC [Air Force Missile Test Center].”

In the meantime, the government was attempting to remedy the housing situation in several ways. On June 6, 1956, it sent the plaintiff a telegram outlining its efforts in this regard, stating:

(1) It had signed a contract with the City of Cocoa for a water supply.
(2) It was supporting the Sparkman Bill in Congress to provide FHA mortgage insurance for housing.
(3) It was making an effort to get Capehart Housing for military personnel which would release other housing occupied by them.
(4) It was endeavoring to interest private builders to construct houses in the area.

The telegram further stated:

In consideration of actions possibly in progress, the Air Force plans no third party indemnity guarantees for housing requirements of contractor employees performing at AFMTC.

The plaintiff answered this telegram by a wire message on June 25, 1956, in which it disagreed with the government’s telegram of June 6th.

On July 23, 1956, the government sent plaintiff the following telegram:

The Sparkman Bill became law on 13 June 1956 — PL 574. The Department of Defense has issued a certificate to FHA for mortgage guarantee on 1000 houses under Sparkman Bill. Local FHA, Tampa Office, believes that in view of interest already indicated by builders in Sparkman program, that considerable construction will be started immediately. In addition, AFMTC has approval for 1125 houses under the Capehart Bill. Current estimate is April 1957 for first units to be completed * * *. We are firmly convinced that no additional action which the Government might take would result in obtaining housing sooner than the above Sparkman and Capehart actions. Although the housing situation will remain critical for several months, we cannot accept that it is critical to the extent that your program schedules cannot be maintained.

In the meantime, plaintiff had been negotiating with Whitmor Homebuilders, Inc., to build houses for its employees, and on August 9, 1956, it issued a letter of intent to this company, which was followed up on September 14, 1956, with the execution of a formal contract for the building of 130 houses. The first house was to be completed by December 15, 1956, and all of them by June 15, 1957. The contract provided that the houses would be leased to the plaintiff for twelve years at a stated monthly rental, with plaintiff having the option to buy them at any time with credit for all prior rent payments. The plaintiff proposed to rent or sell the houses without profit to its employees. Construction was not started, however, until February 1957, with the first house being finished in May and the last one in August of that year.

By the time these houses were started in February 1957, water had become available and also the Sparkman Act provided FHA financing. This caused private builders to become interested in the area and they started building houses before the plaintiff’s houses were started, and began renting them cheaper than plaintiff could rent its houses. As a consequence, plaintiff could not rent or sell many of its houses.

On March 7, 1957. at the beginning of the construction of plaintiff’s 130 houses, the contracting officer asked plaintiff to concur in the contracting officer’s understanding that no costs in connection with *407 the housing project would be charged directly or indirectly to the government under the contract. The plaintiff replied by letter of April 17, 1957, refusing to agree to the contracting officer’s request.

It should be pointed out that on October 19, 1956, the Air Force wrote the plaintiff that it intended to discontinue making bonus payments to plaintiff’s employees at the Cape. The plaintiff’s president wrote a letter protesting this action in which he said:

Convair therefore recommended many months ago that it be permitted to have additional housing built under a lease arrangement whereby non-occupancy costs would be guaranteed by Convair and reimbursed by the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D-STAR Engineering Corp.
Armed Services Board of Contract Appeals, 2025
Fluor Intercontinental, Inc.
Armed Services Board of Contract Appeals, 2022
Kellogg Brown & Root Services, Inc. v. United States
742 F.3d 967 (Federal Circuit, 2014)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Iconco v. United States
32 Cont. Cas. Fed. 72,720 (Court of Claims, 1984)
Metric Construction Co. v. United States
30 Cont. Cas. Fed. 70,793 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
410 F.2d 404, 187 Ct. Cl. 597, 1969 U.S. Ct. Cl. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-dynamics-corporation-v-the-united-states-cc-1969.