Iconco v. United States

32 Cont. Cas. Fed. 72,720, 6 Cl. Ct. 149, 1984 U.S. Claims LEXIS 1351
CourtUnited States Court of Claims
DecidedAugust 1, 1984
DocketNo. 617-83C
StatusPublished
Cited by10 cases

This text of 32 Cont. Cas. Fed. 72,720 (Iconco v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iconco v. United States, 32 Cont. Cas. Fed. 72,720, 6 Cl. Ct. 149, 1984 U.S. Claims LEXIS 1351 (cc 1984).

Opinion

OPINION

LYDON, Judge:

This government contract case involves review, under standards of the Wunderlich Act 41 U.S.C. §§ 321-322 (1976), of a decision by the Postal Service Board of Contract Appeals (Board) denying plaintiff’s claims for (1) additional compensation for removal of 231 cubic yards of excavation, and (2) additional compensation because of the Postal Service’s refusal to permit plaintiff to use certain excavated soil for back-filling and its refusal to pay plaintiff for its replacement with structural fill. On review, it is concluded that the Board’s decision is correct in fact and in law.

On November 23, 1977, plaintiff was awarded a contract to perform certain demolition work relative to preparation of a site for the construction of a United States Postal Service facility, known as the East Carrier Annex, in Seattle, Washington. The contract price was $149,290.- The work involved demolition and removal of buildings which was followed by clearing, filling, compaction and grading of the work site to conform to contours and elevations stated in the contract documents,

The scope of this court’s review in a Wunderlich Act case is narrow and limited. It is limited generally to determining whether there is substantial evidence, i.e., such evidence as might convince a reasonable person, to support the conclusion reached by the Board or agency. Koppers Co. v. United States, 186 Ct.Cl. 142, 148, 405 F.2d 554, 557 (1968).

In its first claim, plaintiff sought recovery for the removal of 251 cubic yards of unsuitable material, or $3,639.50. Plaintiff [152]*152claimed it had removed, at the direction of the Soils Engineer1, 586 cubic yards of unsuitable material whereas the Postal Service contended plaintiff only removed 355 cubic yards of said material. Plaintiff’s 251 cubic yard claim figure is premised on the view that the Postal Service only credited plaintiff with removing 335 cubic yards of unsuitable material. However, the Board found, and correctly so, that the Postal Service credited plaintiff with removing 355 cubic yards. Thus, the correct cubic yardage figure in dispute is 231 cubic yards (586-355 = 231).

The contract provided that removal by plaintiff of unsuitable “in-place” soils and structural fill replacement on the prior approval of the contracting officer would entitle it to payment on the basis of $14.50 per cubic yard “in-place” measurement. The contract specifications provided in pertinent part:

Only that material determined to be unsuitable in the opinion of the Soils Engineer shall be removed below the specified stripped surface. For the ‘in place’ yardage of unsuitable material so removed the Contractor will receive compensation at the unit price [$14.50 per cubic yard] set forth by the contractor’s bid * * *. The ‘in place’ volume measurement shall be made by the contractor, at no expense to the owner, using surveying methods determined suitable by the Soils Engineer. * * *

As to the first claim, the dispute is clearly factual. The majority of the Board found that plaintiff failed to show by a preponderance of the evidence that the material claimed to have been excavated, and for which payment was sought, was unsuitable, or that the Soils Engineer directed that it be removed on February 24,1978, or any other date. The Board’s use of the preponderance test is a proper one. See Davis v. United States, 180 Ct.Cl. 20, 32 (1967). See also Wm. A. Smith Contracting Co. v. United States, 188 Ct.Cl. 1062, 1085-1086, 412 F.2d 1325, 1337-1338 (1969).

The evidence bearing on plaintiff’s first claim was conflicting. In reaching its decision the Board majority clearly accepted the testimony of the Postal Service witness, the Soils Engineer, and other supportive exhibits, over the testimony and supportive exhibits of the plaintiff’s witnesses. Without more, the Board’s findings must be accepted. See Wm. A. Smith Contracting Co. v. United States, supra, 188 Ct.Cl. at 1076-1077, 412 F.2d at 1333. Where two versions of the facts are equally probable, this court is constrained to favor the version accepted by the Board. Williamsburg Drapery Co. v. United States, 177 Ct.Cl. 776, 783, 369 F.2d 729, 733 (1966). The testimony of the Soils Engineer was that the cubic yardage for which plaintiff sought compensation was located in an area that was not excavated at his direction. It is the function of the Board, not the court, to resolve conflicts in evidence. See Dean Constr. Co. v. United States, 188 Ct.Cl. 62, 67-68, 411 F.2d 1238, 1241, 1242 (1969); General Dynamics Corp. v. United States, 187 Ct.Cl. 597, 606, 410 F.2d 404, 409 (1969). Further, credibility of witnesses is clearly a Board function and this function is not to be disregarded merely because the testimony was heard by only one member of the three-member Board panel whose decision is under review. See Sternberger v. United States, 185 Ct.Cl. 528, 536-537, 401 F.2d 1012, 1017 (1968); see also Eggers & Higgins v. United States, 185 Ct.Cl. 765, 782, 403 F.2d 225, 234 (1968).

A review of the entire record in this case establishes that the Board findings and determination on plaintiff’s first claim are supported by substantial evidence. See Koppers Co. v. United States, supra, 186 Ct.Cl. at 148-151, 405 F.2d at 556, 559.2 The Board’s determinations on [153]*153said claim most certainly lie within the zone of reasonableness provided by the record before it. See Williamsburg Drapery Co. v. United States, 187 Ct.Cl. 298, 303, 407 F.2d 1342, 1344 (1969). Plaintiff has failed to meet its heavy burden of establishing that, on the record compiled before the Board, the Board’s findings are not supported by substantial evidence. See Arun-del Corp. v. United States, 207 Ct.Cl. 84, 98, 515 F.2d 1116, 1124 (1975).

In its second claim, plaintiff sought recovery, in the amount of $123,171.41, for the quantity of structural fill it furnished to replace material removed by plaintiff in excavating subsurface structures.

Under the contract, plaintiff was required to remove buried concrete walls, foundations and footings which were located on the work site. Some of these footings extended as far as 10 feet below the surface. Since the contract did not state the method or equipment to be employed in removing subsurface structures, the plaintiff was free to select whatever method and equipment it felt was necessary to do the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yee v. United States
Federal Claims, 2017
Maitland Bros. v. United States
36 Cont. Cas. Fed. 75,835 (Court of Claims, 1990)
Stegall v. United States
19 Cl. Ct. 765 (Court of Claims, 1990)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Blue Cross & Blue Shield Ass'n v. United States
34 Cont. Cas. Fed. 75,408 (Court of Claims, 1987)
Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States
33 Cont. Cas. Fed. 74,502 (Court of Claims, 1986)
Sperry Corp. v. United States
33 Cont. Cas. Fed. 74,234 (Court of Claims, 1986)
Cherry Hill Sand & Gravel Co. v. United States
33 Cont. Cas. Fed. 74,030 (Court of Claims, 1985)
Straga v. United States
32 Cont. Cas. Fed. 73,470 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,720, 6 Cl. Ct. 149, 1984 U.S. Claims LEXIS 1351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iconco-v-united-states-cc-1984.