Williamsburg Drapery Company, Inc. v. The United States

407 F.2d 1342, 187 Ct. Cl. 298, 1969 U.S. Ct. Cl. LEXIS 136
CourtUnited States Court of Claims
DecidedMarch 14, 1969
Docket67-63
StatusPublished
Cited by6 cases

This text of 407 F.2d 1342 (Williamsburg Drapery Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williamsburg Drapery Company, Inc. v. The United States, 407 F.2d 1342, 187 Ct. Cl. 298, 1969 U.S. Ct. Cl. LEXIS 136 (cc 1969).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM : *

This is the residuum from the court’s earlier opinion (Williamsburg Drapery Co. v. United States, 177 Ct.Cl. 776, 369 F.2d 729 (1966)), dismissing all of the plaintiff’s claims save the Bottom Hems dispute, which was remanded to the Armed Services Board of Contract Appeals for redetermination on the basis of underlying facts, and thence resubmitted to the court for review on the parties’ summary judgment motions and briefs addressed to the Board’s fresh findings (ASBCA Nos. 5484, 5561, 68-1 BCA ¶ 7002, at 32,389), which denied recovery. We hold that plaintiff is not entitled to recover, and grant the defendant’s motion for summary judgment as to the remnant in issue.

Recapitulating the highlights of the court’s earlier opinion, partial termination of the contract (to supply 8,353 curtains for the Air Force Academy) on December 30, 1958, for incipient default, and termination on February 3, 1959, of virtually all of the remainder for default, 1 precipitated an appeal to the Board, followed by a review proceeding in this court, to test the plaintiff’s demand that the termination for cause be converted into a termination for convenience of the Government, because of seven specific delays alleged to justify time extensions sufficient if granted to invalidate the termination. The Board rejected all of the plaintiff’s specific claims except that as to Handstitching of Pleats, which was ruled to warrant a four-day or five-day time extension for delivery of the first installment of curtains due January 15, 1959, depending on whether one considered the full contract installment or that installment as reduced by the partial termination. 2 *1343 The court agreed with the Board on all claims except the Bottom Hems claim, which as stated was remanded to the Board for ascertainment of basic facts. On the basis of its remand hearing on this isolated issue, the Board on April 22, 1968, rejected the Bottom Hems claim in 19 separate findings of fact. The plaintiff asserts as to each and every one of the Board’s findings that in whole or in specified part it was not supported by substantial evidence and was arbitrary and capricious.

The Board’s findings numbered 1 through 5 provide the chapter and verse support for finding 6 that “The hem change of [Supplemental Agreement] No. 2 was, therefore, not forced upon, but on the contrary originated with, appellant.” This conclusion, reached by the Board’s prerogative of discounting the credibility of plaintiff’s main witness, was clearly supported by the record.

The original specifications for the curtain procurement in suit contemplated that a three-inch bottom hem would be formed by folding over the bottom selvage of the drape twice, then sewing it through three thicknesses at the uppermost edge of the hem thus formed. The hem would first be “sized”, that is to say, the cloth would be folded over twice to the proper dimension, and pinned at both ends and in the center to hold the hem shape ready for sewing. It would then be fed into a sewing machine through a “folder” attachment, which automated the sewing operation to the extent of relieving the operator of the task of manually guiding a straight line of stitches.

It is customary to insert weights in the lower edge of curtains to enhance their hung appearance. When the hems in issue were sized and sewn, it was originally planned that a prefabricated removable tape containing regularly spaced flat lead weights would be threaded inside the completed hem and secured thereto at each end by a snap fastener.

In response to a suggestion by plaintiff which was adopted by Government representatives after some consultation, it was decided to use a lighter lead weight than specified in order to retard the deterioration of the hem fabric which the heavier prescribed weights would be apt to cause. Paragraph 2 of Supplemental Agreement No. 2, issued in October 1958, amended the specifications so as to substitute a lighter weight consisting of a bead chain of small lead shot interspersed through a knitted cloth sleeve. Because this lighter type of weighted tape could not be threaded satisfactorily through a completed bottom hem as the superseded lead weight tape could have been, it was necessary to alter the manufacturing method by folding the new type weighted tape into the material of the hem during the sizing operation, then fastening it into place in the hem fabric with numerous pins to prevent slippage during the sewing of the hem. The added thickness of the hem with the weighted tape inside, and the large number of securing pins, precluded the newly sized hem from being fed into the sewing machines through the folder attachment, and required instead that it be guided by the operator’s hand through the machine stitching procedure, removing pins as the sewing progressed and making time-consuming measurements to keep on course. The Board found, on challenged evidence, that each hem took 13 minutes longer to complete than it otherwise would have under the superseded hem specification— ten minutes extra for the sizing and three minutes more for the sewing.

Adverting once more to the Board’s opinion, its findings 7 through 12 relate to the contractor’s failure to make a timely demand for additional compensation or a time extension because of the Bottom Hems change, and provide the basis for the Board’s finding number 13 that “ * * * appellant did not claim an extension of delivery time on the basis of the bottom hem change until the very end of December 1958.” The record amply supports the finding in-so far as it is challenged. Although at the time that Supplemental Agreement No. 2 was discussed the plaintiff knew *1344 —and the Government did not- — that section 2 of the Agreement changing the bottom hem weights would take more time, at no time from then up to and including the filing of companion appeal petitions to the Board in March and April 1959 did the plaintiff make any written request for an extension of time ascribing as specific reason the Bottom Hems problem. This despite a series of letters through January 1959 demanding time extensions for various other performance headaches, including those arising from Supplemental Agreement No. 2 referring, however, only to the First Article aspect of the Supplemental Agreement and never directly or by reasonable inference to the Bottom Hems aspect. Oral mention of such a claim by plaintiff at the time of the first partial termination on December 30, 1958, was found by the Board.

The Board has, in findings 14 through 19, projected a 13-minutes per curtain determination of extra time due to the Bottom Hems change to conclude that plaintiff would on that account have been entitled to a 12-day time extension on the basis of the first installment of curtains due under the contract on January 15, 1959, or 8 days on the basis of the total due in the first installment as reduced by the partial termination of December 30, 1958.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iconco v. United States
32 Cont. Cas. Fed. 72,720 (Court of Claims, 1984)
Marley v. United States
423 F.2d 324 (First Circuit, 1970)
Marley v. United States
423 F.2d 324 (Court of Claims, 1970)
Datronics Engineers, Inc. v. The United States
418 F.2d 1371 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
407 F.2d 1342, 187 Ct. Cl. 298, 1969 U.S. Ct. Cl. LEXIS 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williamsburg-drapery-company-inc-v-the-united-states-cc-1969.