Datronics Engineers, Inc. v. The United States

418 F.2d 1371, 190 Ct. Cl. 196, 1969 U.S. Ct. Cl. LEXIS 165
CourtUnited States Court of Claims
DecidedDecember 12, 1969
Docket157-66
StatusPublished
Cited by3 cases

This text of 418 F.2d 1371 (Datronics Engineers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Datronics Engineers, Inc. v. The United States, 418 F.2d 1371, 190 Ct. Cl. 196, 1969 U.S. Ct. Cl. LEXIS 165 (cc 1969).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner James F. Davis with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 99(c) [since September 1, 1969, Rule 166(c)]. The commissioner has done so in an opinion and report filed on May 2, 1969, wherein such facts as are necessary to the opinion are set forth. Exceptions (request for review by the court) were filed by plaintiff. Defendant accepted the commissioner’s opinion with an exception concerning his denial of defendant’s counterclaim. The case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion and recommended conclusion of the trial commissioner (with a minor change in the conclusion), it hereby adopts the same, as hereinafter set forth, as the basis for its decision in this case. Therefore, plaintiff’s motion for summary judgment is denied and defendant’s cross-motion is granted. Defendant is entitled to recover on its counterclaim only to the extent of $162.-50 (as found by the Armed Services Board of Contract Appeals) and judg *1373 ment is entered for defendant on its counterclaim in’ the sum of $162.50. Plaintiff’s petition is dismissed.

OPINION OF COMMISSIONER

DAVIS, Commissioner:

The issue here is whether defendant properly terminated plaintiff’s contract for default. Plaintiff says the termination should be treated as one for the convenience of the government. If defendant is right, then another issue is whether the government correctly assessed against plaintiff excess costs for completing the contract.

I.

Plaintiff’s contract was with the Air Force to rehabilitate radio antennas serving Andrews Air Force Base at Brandywine, Maryland and Davidson-ville, Maryland. At the transmitter site (Davidsonville), there were 20 antennas; at the receiver site (Brandy-wine), there were 22 antennas. The nature of the antennas is discussed below to the extent necessary to understand the issues. Rehabilitation work consisted of (1) dismantling, repairing, and rebuilding the antennas, and (2) laying new underground cable between antennas and communications buildings.

Plaintiff as low bidder was awarded the contract on February 18, 1963, for the price of $19,927. 1 The notice to proceed was issued on March 1, 1963; was received by plaintiff on March 4; and work was to be completed within 120 calendar days of receipt, making July 2, 1963, the original completion date. Plaintiff started to work in mid-March. Progress was slow, and the quality of much of plaintiff’s work was deemed unsatisfactory and unacceptable. On June 24, 1963, the administrative contracting officer (ACO) issued a show-cause notice stating that plaintiff had failed to make satisfactory progress to complete the contract on time, and that the government was considering terminating the contract for default. Plaintiff was invited to state reasons why its failure to perform satisfactorily arose out of causes beyond its control and without its fault or negligence. 2

Plaintiff replied, setting out several reasons for delay and requesting an extension of the completion date to August 2, 1963. The ACO, on June 27, 1963, asked plaintiff for a more detailed explanation. Plaintiff complied by letter of July 5, 1963, in which it elaborated on the previously stated reasons and set out several more reasons.

Meanwhile, plaintiff continued to work. On July 5, while digging trenches at Brandywine to lay new cable, plaintiff’s trencher machine inadvertently cut an underground cable servicing one of the antennas. On July 9, the contracting officer issued a stop-work order, pending investigation of the cable-cutting incident. The same day, the order was rescinded when it appeared that the problem had been cleared up. However, within several days, plaintiff cut more cables, rendering other antennas unserviceable; and on July 19, a second and final stop-work order was issued. On September 24, 1963, the termination contracting officer (TCO) issued a notice of default termination and findings of *1374 fact, stating, among other things, that plaintiff

* * * failed to complete performance of your contract within the prescribed performance period, and the work which you did perform was not accomplished in an acceptable and satisfactory manner. Furthermore, in the course of performance of your contract, you caused damages to, among other things, existing underground cables. You failed to correct deficiencies in your contract performance and failed to repair damages which you caused to existing equipment in an acceptable manner.

Plaintiff wrote letters to the TCO on October 4 and October 16, 1963, asking for reconsideration of the default termination. The TCO reviewed the letters, visited the worksite, and advised plaintiff his decision would stand. Plaintiff appealed to the Armed Services Board of Contract Appeals (Datronies Engineers Inc., ASBCA No. 9506, 65-2 BCA 5123).

Thereafter, defendant completed the contract using military personnel from Brookley Air Force Base, Alabama, who worked from October to December 1963 and from February to April 1964. On October 5, 1964, the government assessed plaintiff $42,604 excess costs (later reduced to $21,891.77) for completing the contract. Plaintiff appealed to the ASBCA (Datronies Engineers Inc., ASBCA No. 10355, 66-2 BCA fl 6069).

In No. 9506, the board held on September 30, 1965, that the default termination was proper. The board said (65-2 BCA, p. 24,127):

Summarizing the alleged causes of delay apparently relied upon by the appellant * * * we conclude that the appellant was entitled to time extensions of a total of 18 days, extending to approximately 20 July the date for completion of the contract work. We find in the record no reliable evidence upon which to estimate the percentage of contract work completed as of 19 July when the contractor was ordered to stop work, but it is obvious that the work remaining to be done was far in excess of what could be completed in just one day, i. e., by 20 July. The appellant has failed to show and in fact has not even contended that the work under the contract could have been completed by 20 July 1963 had the stop work order not been issued.

* * * We find, in conclusion, that at the time of the issuance of the stop work order on 19 July appellant was in default by virtue of having failed to prosecute the work with such diligence as to insure its completion by the specified completion date of 2 July plus an 18-day extension to which appellant was entitled for delays due to excusable causes. In addition the appellant was in default in damaging and failing to repair promptly the RG 85 cables, and in particular those cables cut 16 July. Since appellant was in default when the contract was terminated, there is no basis for converting the contract termination from a termination for default to one for the convenience of the Government. ******

In No. 10355, the board heard testimony and received documents relating to defendant’s costs to complete the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penner v. United States Postal Service
879 F. Supp. 553 (M.D. North Carolina, 1995)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
418 F.2d 1371, 190 Ct. Cl. 196, 1969 U.S. Ct. Cl. LEXIS 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/datronics-engineers-inc-v-the-united-states-cc-1969.