Air-A-Plane Corporation v. The United States

408 F.2d 1030, 187 Ct. Cl. 269
CourtUnited States Court of Claims
DecidedJune 13, 1969
Docket61-62
StatusPublished
Cited by63 cases

This text of 408 F.2d 1030 (Air-A-Plane Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Air-A-Plane Corporation v. The United States, 408 F.2d 1030, 187 Ct. Cl. 269 (cc 1969).

Opinion

OPINION

DAVIS, Judge *

After formal advertising, plaintiff Air-A-Plane Corporation entered into a fixed-price contract with the Army Chemical Corps to make over 1100 smoke generators (designated as M3A1). The total price at the outset was $607,101.04. The current dispute is the outcome of a large number of changes made by the Government after the award. In its decision the Armed Forces Board of Contract Appeals said that “[wjhile aware of the ‘Changes’ provision in the contract and of the Government’s right to order changes, [plaintiff] in bidding on the contract, had not anticipated that any substantial number of changes would be ordered. This belief was based principally on the fact that the contract, by way of detailed and comprehensive specifications and drawings, described the contract items minutely. This belief was apparently also based in part upon the fact that the contract was a fixed price contract.”

Nevertheless, the Board found, “[a]fter the contract was awarded a large number of changes were made. The first change changed the designation *1032 of the item from the M3A1 to the M3A2. The Board here emphasizes that it was a large number of changes that were made. Since the parties count the changes differently they do not agree on the precise number ([plaintiff] uses a figure of approximately 1000) but using either party’s version the number is large. So numerous were the changes that the contract took on the aspects of a design or development contract. Certain components of the generator were the subject of more than one change; and other components, although not themselves changed, would be affected (as to time of assembly for example) by changes made on other components. The frequency and nature of the changes were disruptive of [plaintiff’s] production. By way of illustration as to the number of changes the first change deleted some 41 drawings in their entirety, making substitutions for most of them; and directed [plaintiff] to hold in abeyance the procurement of the materials and components covered by some 126 other drawings.”

As compensation for these modifications, the contractor sought equitable adjustments under the Changes article. Certain supplemental agreements were made, one of which (No. 17) added some $25,000 to the total price. The parties could not agree on the recovery for other changes, and the contracting officer unilaterally allowed an additional $60,000, which was much less than plaintiff had asked. It appealed to the Board of Contract Appeals, arguing that Supplemental Agreement No. 17 should be set aside as induced by economic duress, and that the total equitable adjustment should be considerably enlarged over the $85,000 (or so) extra which had been granted.

The Board agreed that “There is no dispute as to the fact that changes were ordered. There is no dispute as to the fact that the over-all effect of these changes was to increase the cost of performing the contract. „ There is no dispute as to the fact that [plaintiff] is entitled to an upward adjustment of the contract price.” The Board decided, however, that Supplemental Agreement No. 17 was not vitiated by duress and that Air-A-Plane had failed to prove that it was entitled to anything more, by way of equitable adjustments under the Changes article, than it had already been allowed by the contracting officer. Air-A-Plane Corp., ASBCA No. 3842, 60-1 BCA ¶ 2547, at 12,203.

The original petition in this court (filed in 1962) contented itself with attacking the Board’s decision, on the amount of recovery, as vulnerable under the standards of the Wunderlich Act, 41 U.S.C. § 321 (1964). After United States v. Carlo Bianchi & Company, 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963), plaintiff was allowed to amend the petition to assert, in addition, (a) that defendant breached the contract because the changes imposed amounted in toto to a cardinal change, beyond the scope of the Changes article, and (b) a plea for reformation of the contract because the parties intended, but never executed, a novation of the original contract, transforming it into a research, development, and production agreement. 1 Plaintiff continues to press these additional claims, and we consider them first because their disposition may make it unnecessary to review the Board’s decision at all.

Cardinal change: The normal Changes article (which was the clause in this agreement) permits the Government to make changes “within the general scope of this contract.” Because of this phrase in particular, and the structure of the article in general, the court has con *1033 sistently ruled that such a “changes” provision does not authorize a “cardinal” change — a drastic modification beyond the scope of the contract. 2 Rather, a fundamental alteration of this type is a contract breach, entitling the contractor to breach damages.

The basic standard, as the court has put it, is whether the modified job “was essentially the same work as the parties bargained for when the contract was awarded. Plaintiff has no right to complain if the project it ultimately constructed was essentially the same as the one it contracted to construct.” Conversely, there is a cardinal change if the ordered deviations “altered the nature of the thing to be constructed”. Aragona Constr. Co. v. United States, supra, note 2, 165 Ct.Cl. at 391 ; Keco Indus., Inc. v. United States, supra, note 2, 364 F.2d at 847-848, 176 Ct.Cl. at 998 ; see Wunderlich Contracting Co. v. United States, supra note 2, 351 F.2d at 966, 173 Ct.Cl. at 194. Our opinions have cautioned that the problem “is a matter of degree varying from one contract to another” and can be resolved only “by considering the totality of the change and this requires recourse to its magnitude as well as its quality”. Saddler v. United States, supra note 2, 287 F.2d at 413, 152 Ct.Cl. at 561, see J. D. Hedin Constr. Co. v. United States, supra note 2, 347 F.2d at 257, 171 Ct.Cl. at 105, 106. “There is no exact formula * * *. Each case must be analyzed on its own facts and in light of its own circumstances, giving just consideration to the magnitude and quality of the changes ordered and their cumulative effect upon the project as a whole.” Wunderlich Contracting Co. v. United States, supra, 351 F.2d at 966, 173 Ct.Cl. at 194. In emphasizing that there is no mechanical or arithmetical answer, we have repeated that “[t]he number of changes is not, in and of itself, the test * * Saddler v. United States, supra, 287 F.2d at 413, 152 Ct.Cl. at 561 ; see Aragona Constr. Co. v. United States, supra, 165 Ct.Cl. at 390 ; J. D. Hedin Constr. Co. v. United States, supra, 347 F.2d at 257-258, 171 Ct.Cl. at 106.

Under these general standards, there is surely adequate warrant for inquiring whether the modifications made by the defendant in the M3A1 generator resulted in a cardinal change.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Semac Electric Co. v. Skanska USA Building, Inc.
195 Conn. App. 695 (Connecticut Appellate Court, 2020)
Aircraft Charter Solutions, Inc. v. United States
109 Fed. Cl. 398 (Federal Claims, 2013)
American Apparel, Inc. v. United States
108 Fed. Cl. 11 (Federal Claims, 2012)
Golden Manufacturing Co. v. United States
107 Fed. Cl. 264 (Federal Claims, 2012)
International Data Products Corp. v. United States
70 Fed. Cl. 387 (Federal Claims, 2006)
Micalizzi v. Rumsfeld
247 F. Supp. 2d 556 (D. Vermont, 2003)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Northrop Grumman Corp. v. United States
50 Fed. Cl. 443 (Federal Claims, 2001)
Pellerin Construction, Inc. v. Witco Corp.
169 F. Supp. 2d 568 (E.D. Louisiana, 2001)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)
Northern States Power Co. v. United States
43 Cont. Cas. Fed. 77,450 (Federal Claims, 1999)
Amertex Enterprises, Ltd. v. United States
108 F.3d 1392 (Federal Circuit, 1997)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
408 F.2d 1030, 187 Ct. Cl. 269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/air-a-plane-corporation-v-the-united-states-cc-1969.