Aragona Construction Co. v. United States

165 Ct. Cl. 382, 1964 U.S. Ct. Cl. LEXIS 81, 1964 WL 8634
CourtUnited States Court of Claims
DecidedApril 17, 1964
DocketNo. 345-59
StatusPublished
Cited by23 cases

This text of 165 Ct. Cl. 382 (Aragona Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aragona Construction Co. v. United States, 165 Ct. Cl. 382, 1964 U.S. Ct. Cl. LEXIS 81, 1964 WL 8634 (cc 1964).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiff, a construction contractor, brings this suit to recover $68,028.03, a sum it says it lost in constructing a hospital for the Veterans’ Administration. In 1941, it was awarded a, contract to build a reinforced concrete hospital building at Fort Howard, Maryland, for a price of $871,700. It began work on August 22 of that year. The building was to have been completed within 400 calendar days after receipt of notice to proceed on August 12,1941, i.e., by September 16, 1942. In actuality, however, completion was delayed for 429 additional days, and the hospital was not accepted until November 19,1943.

The intervention of a World War was the primary cause of most of the delay. Beginning in the early part of 1942, the Office of Production Management, in order to facilitate [385]*385production under armaments contracts,1 issued a number of priority orders that diverted certain scarce building materials from this project and either forbade or limited their use. These orders prevented plaintiff from using building materials such as steel, copper, brass, and aluminum as it had planned to do. Acting under the Changes article of the contract,2 defendant required plaintiff to procure substitute materials, such as wood, cast iron, fabric and plastic, and to use them in place of those affected by priority orders.

Plaintiff’s case rests upon the argument that the cumulative effect of the various priority orders was to make performance of its obligations under the contract impossible. Plaintiff further contends that, in complying with the various change orders, it was compelled to construct a wholly different project from that called for under the original specifications. For this work, plaintiff says it is entitled to receive a fair price, equal to its costs in doing the worn.

The trial commissioner to whom this case was referred concluded that the onset of the war created chaotic conditions in the construction field generally and thoroughly disrupted the program for the completion of this particular [386]*386project. He also found that most of the delay stemmed from these chaotic conditions and was not the fault of either the plaintiff or the defendant, both of whom coped with the situation as best they could. Although each party complains of deficiencies on the part of the other, the evidence supports the commissioner’s findings in this respect. Defendant ultimately granted plaintiff extensions of time sufficient to cover the extra time necessary to finish the building and thereby waived any claim for liquidated damages.

When the work first got underway, plaintiff encountered delays in driving foundation piles and in pouring concrete, which exceeded two months in duration. These delays, which were unrelated to the issuance of priority orders, and for which defendant was not responsible, had a disruptive effect on the balance of the project; for, as time went along, the effects of military conscription coupled with the establishment of many defense plants in the area created a severe shortage of skilled labor and an increase in labor costs. The passage of time also brought an increasing number of priority orders, as more and more materials were allocated exclusively to war production.

Plaintiff had let the bulk of the subcontracts and had ordered most of the materials required by the specifications by the fall of 1941. As it was prohibited from using one or another type of building material, plaintiff had to ascertain from its various subcontractors and suppliers what substitutes were available and the extent to which the substitutions would increase or decrease its costs. Having obtained this information, plaintiff would then pass it along to the contracting officer, and he would — after determining that the substitute was acceptable and not barred by priority orders — approve the substitution and issue a change order authorizing the use of the new material in lieu of the one that was not available.

The contract price was then adjusted to reflect any cost changes resulting from the substitution. Plaintiff was generally allowed a 10 percent overhead fee and a 10 percent profit on the cost of materials. When the price was in[387]*387creased, the profit and overhead charges were recomputed to reflect the increased cost. When the cost of the substitute materials was less than the cost of those originally specified, however, no change was made in the original profit and overhead fees. The net effect of the various changes was to decrease the contract price by $9,372.28.

Plaintiff accepted all the change orders, including those increasing or decreasing the contract price, without protest.

However, on one occasion, in November 1941, plaintiff complained to the Veterans’ Administration’s Director of Construction about the increase in its overhead costs arising from the need to obtain the information necessary to substitute materials (often through many tiers of subcontractors and suppliers) and the haphazard fashion in which approval for the changes was given. But plaintiff never exercised its right under the contract to contest the amount of the price adjustments through administrative channels.3

Our jurisdiction over this case is founded upon a private law, the text of which is fully set out in finding number 2. That Act extends the statute of limitations on the commencement of this suit, but we construe it in all other respects as authorizing us to determine this case by the same procedure and by the application of the same substantive rules of law as apply generally to any contract action brought under 28 U.S.C. § 1491. The parties have not confined their arguments to the issue of plaintiff’s entitlement to a judgment under those substantive rules. They have also j oined issue on plaintiff’s contention that it may obtain recovery by way of a gratuity arising by virtue of some moral claim it may have on the conscience of the nation. Even if we assume, ar-guendo, that we might be given jurisdiction over such a claim, we do not think that the statute which conferred jurisdiction over this litigation grants us the power to adju-[388]*388dicat© such, a claim.4 With the exception of the extension of the limitations period in plaintiff’s favor, we interpret it as placing plaintiff in no better position than any other litigant before the 'bar. Accordingly, we do not think that defendant can be held to any liability except such as flows from its acts and defaults as a party to a contract with the plaintiff.

As a consequence, any liability that attaches to the defendant must result from its acts or omissions in its purely contractual capacity and cannot be culled from its general and public acts as a sovereign. See Horowitz v. United States, 267 U.S. 458 (1925). Therefore, defendant does not incur any liability by reason of the issuance of priority orders that forbade the use of certain materials called for in the specifications. It issued those orders for the purpose of mobilizing the economy for war. In Gothwaite v. United States, 102 Ct. Cl. 400, 401 (1944), a case dealing with the same construction project that is here involved, we held that the issuance of priority orders was

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
Mabus v. General Dynamics C4 Systems, Inc.
633 F.3d 1356 (Federal Circuit, 2011)
Klamath Irrigation District v. United States
75 Fed. Cl. 677 (Federal Claims, 2007)
Capital Development Co. v. United States
49 Fed. Cl. 178 (Federal Claims, 2001)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Green Management Corp. v. United States
42 Cont. Cas. Fed. 77,412 (Federal Claims, 1998)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,379 (Federal Claims, 1998)
Airprep Technology, Inc. v. United States
39 Cont. Cas. Fed. 76,634 (Federal Claims, 1994)
LK Comstock & Co., Inc. v. Becon Const. Co., Inc.
932 F. Supp. 906 (E.D. Kentucky, 1993)
Atlantic Dry Dock Corp. v. United States
773 F. Supp. 335 (M.D. Florida, 1991)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
Universal Contracting & Brick Pointing Co. v. United States
36 Cont. Cas. Fed. 75,832 (Court of Claims, 1990)
Allied Materials & Equipment Co. v. United States
569 F.2d 562 (Court of Claims, 1978)
Broome Construction, Inc. v. United States
492 F.2d 829 (Court of Claims, 1974)
Seger v. United States
469 F.2d 292 (Court of Claims, 1972)
Edward R. Marden Corporation v. The United States
442 F.2d 364 (Court of Claims, 1971)
Air-A-Plane Corporation v. The United States
408 F.2d 1030 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
165 Ct. Cl. 382, 1964 U.S. Ct. Cl. LEXIS 81, 1964 WL 8634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aragona-construction-co-v-united-states-cc-1964.