Harry Pepper and Associates, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 13, 2021
DocketASBCA No. 62038, 62039, 62040, 62041, 62042
StatusPublished

This text of Harry Pepper and Associates, Inc. (Harry Pepper and Associates, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harry Pepper and Associates, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Harry Pepper and Associates, Inc. ) ASBCA Nos. 62038, 62039, 62040 ) 62041, 62042 Under Contract No. NNS14AA30T )

APPEARANCES FOR THE APPELLANT: David W. Mockbee, Esq. D. Wesley Mockbee, Esq. Mockbee Hall & Drake, P.A. Jackson, MS

APPEARANCES FOR THE GOVERNMENT: Scott W. Barber, Esq. NASA Chief Trial Attorney Jeffrey A. Renshaw, Esq. Shannon A. Sharkey, Esq. Trial Attorneys Stennis Space Center, MS

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE GOVERNMENT’S MOTION FOR PARTIAL SUMMARY JUDGMENT AND MOTION TO DISMISS FOR LACK OF JURISDICTION

The National Aeronautics and Space Administration (NASA or government) filed a motion for summary judgment on Harry Pepper & Associates’ (HPA’s or appellant’s) sixth claim for relief, which is based on the theory of a cardinal change. Though NASA styles its motion as one for summary judgment, it is aimed at one of the several theories behind each of the appeals, and would not result in disposal of any of the appeals at issue even if successful. Thus, the Board considers it to be a motion for partial summary judgment. We find NASA has shown that appellant has not alleged facts sufficient to constitute a cardinal change, and appellant fails to either show material facts in dispute or meaningfully rebut NASA’s argument.

In the alternative, NASA argues that we lack jurisdiction because this claim was not submitted to the contracting officer (CO) with a sum certain. But the Board’s review of HPA’s claims demonstrates otherwise.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

We previously issued a decision resolving the parties’ cross motions for summary judgment related to Counts I-V of appellant’s complaint. Familiarity with that decision and the facts discussed therein is presumed. However, we will reiterate several relevant facts here for clarity.

1. NASA awarded Contract No. NNS12AA84B, a multiple award construction contract to HPA on August 3, 2012. This contract included the following relevant clauses: FEDERAL ACQUISTION ACT (FAR) 52.233-1, DISPUTES (JUL 2002); FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007). (R4, tab 1 at 16, 38-39) On January 9, 2014, NASA awarded HPA Task Order NNS14AA30T (TO) for restoration of the B2 Test Stand at the John C. Stennis Space Center, MS, valued at $36,577,459. This involved relocation of the Main Propulsion Test Article (MPTA) Superstructure, reinforcement of Battleship Point 1, and other tasks (R4, tab 2 at 94-95). On February 7, 2014, NASA issued HPA a Notice to Proceed, which HPA acknowledged the same day. This document indicated all work was to be completed by March 14, 2015 (R4, tab 3 at 132).

2. As part of its bid, HPA says it assumed “a maximum of 1/8" of movement” of the structure due to thermal variations during the restoration work (R4, tab 46 at 2325). HPA also provided a Quality Assurance Plan, which mandated that one HPA representative would be solely responsible for a three-phase inspection approach: “preparatory, initial, and follow-up inspection[s].” At the initial phase, “[i]f the quality of the work is found to be nonconforming the work will be removed and replaced” and during the follow-up phase, “[n]on-confirming work found during these inspections will be removed and replaced.” (R4, tab 55f at 3425)

3. As part of the reinforcing of Battleship Point Loads “during the MPTA move and afterwards,” work which was designated by Engineering Modification Instructions (EMI) 12NCBZ-20 (EMI 20), the TO required installation of 28 wide flange steel shapes cut into two “T” shapes, referred to as “WTs.” Section 01 11 00 of Specification 200HF-G013, paragraph 1.1.3 stated “some of [these] will be installed by lowering them through temporary holes in the battleship top plate.” (R4, tab 18 at 1694)

4. HPA submitted welding procedures specifications to NASA, dated April 29, 2014, which River City Erectors (RCE), a subcontractor, had proposed as part of its work on EMI 20. These procedures proposed minimum preheat and interpass temperatures for welding various joints based on the thickness of the steel, and are listed as follows: 1/8” – 3/4” is 32º; 3/4” – 1 1/2” is 50º; 1 1/2” – 2 1/2” is 150º; and over 2 1/2” is 225º. No post weld heat treatment was anticipated. (R4, tab 56g at 3513, 3518-20)

1 The “Battleship” was not an actual battleship, but was a frame used to support a rocket booster to be tested on the B2 Test Stand. 2 5. EMI 18, 19, and 20 all contain drawings titled Drawing G-001 which, while different drawings, contain similar General Notes. General Note 2, the same in all three drawings, states “[t]he contractor shall field verify existing conditions, dimensions, and elevations before proceeding with the work. Any discrepancies between the contract documents and the actual field conditions must be reported immediately.” General Note 8 states “[t]his design is based on the original drawings, calculations and specifications prepared for the original construction in the 1960s and subsequent field observations by the current design team. . . . Notify the NASA COR [Contracting Officer Representative] if actual conditions differ from the original documents as modified to an ‘As-Built’ condition in 2011.” (R4, tab 4 at 165, tab 5 at 189, tab 6 at 257)

6. HPA submitted Request for Equitable Adjustment (REA) 1 on June 29, 2015, requesting compensation for relocation of the WTs and additional welding and trimming of WTs in the Battleship (app. supp. R4, tab 18 at 477-79). HPA submitted REA 4 on January 11, 2016, requesting compensation for the changes from Request for Information (RFI) 62’s revision and 62A’s clarification changing Partial Joint Penetration welds to Complete Joint Penetration welds, then to use of a diamond plate. This work was detailed in Field Change Request 37, which HPA stated had been denied. (App. supp. R4, tab 20) HPA supplemented both REAs on July 5, 2017, and a fourth compensation request was added for the cost of bringing the WTs into the Battleship via the north entrance rather than lowering them through a temporary hole in the top plate (app. supp. R4, tab 23c at 634-36).

7. Appellant later resubmitted REAs 1 and 4 as certified claims on December 19, 2018, requesting $2,687,848.40 and a 90-day extension, which NASA subsequently denied (R4, tabs 48, 53). This denial was timely appealed and docketed as ASBCA No. 62038.

8. HPA submitted REA 9, dated July 5, 2017, for changing

welding procedures on all of the MPTA baseplate reinforcement doubler plates . . . to meet the revised welding requirements specified by NASA for the first time in response to HPA RFI #146A. This extra work was necessary due to the excessive size of the fillet weld gaps between the existing columns and the new MPTA baseplate reinforcement doubler plates.

(App. supp. R4, tab 29b at 1379) This REA requested $852,884.98 (id. at 1376).

3 9. HPA submitted REA 10, also dated July 5, 2017, for the

extensive weld repair work required because of NASA’s defective design directive on how to bevel and back bevel the plates which created voids that had to be reworked because of NASA’s defective design, and because of NASA’s failure to detect the two (2) bolts put in the welds by a disgruntled [HPA] employee to slug the welds. Per NASA’s Quality Control responsibility, NASA was obligated to have an inspector inspect each weld during the entire welding process of each weld.

(App. supp. R4, tab 34c at 1815) This REA requested $3,234,428.58 (id. at 1816).

10. HPA submitted a certified claim dated December 19, 2018, reiterating the basis for and incorporating REA 9, and requesting $1,127,909.37 and a 29-day time extension (R4, tab 49 at 3039-40).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
P. L. Saddler v. United States
287 F.2d 411 (Court of Claims, 1961)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
PCL Construction Services, Inc. v. United States
96 F. App'x 672 (Federal Circuit, 2004)
Aragona Construction Co. v. United States
165 Ct. Cl. 382 (Court of Claims, 1964)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)
Edward R. Marden Corp. v. United States
200 Ct. Cl. 759 (Court of Claims, 1971)
Allied Materials & Equipment Co. v. United States
569 F.2d 562 (Court of Claims, 1978)
S. J. Groves & Sons Co. v. United States
661 F.2d 170 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Harry Pepper and Associates, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/harry-pepper-and-associates-inc-asbca-2021.