S. J. Groves & Sons Co. v. United States

661 F.2d 170, 29 Cont. Cas. Fed. 81,880, 228 Ct. Cl. 598, 1981 U.S. Ct. Cl. LEXIS 480
CourtUnited States Court of Claims
DecidedSeptember 23, 1981
DocketNo. 480-80C
StatusPublished
Cited by6 cases

This text of 661 F.2d 170 (S. J. Groves & Sons Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. J. Groves & Sons Co. v. United States, 661 F.2d 170, 29 Cont. Cas. Fed. 81,880, 228 Ct. Cl. 598, 1981 U.S. Ct. Cl. LEXIS 480 (cc 1981).

Opinion

SMITH, Judge,

delivered the opinion of the court:

[599]*599On May 22, 1981, we issued an order in this contract dispute, dismissing the petition without prejudice to plaintiffs rights under the Wunderlich Act,1 and in which order we stated that this opinion would follow.

I.

Pursuant to a contract dated July 15, 1974, between plaintiff, S. J. Groves & Sons Company (Groves), and the Bureau of Reclamation (bureau), United States Department of the Interior (Interior), Groves constructed a large pipeline as part of the Currant Creek Dam project. The purpose of the pipeline was to carry water from the impoundment at the Currant Creek Dam to the inlet portal of the Currant Creek Tunnel. Beginning in 1974, the pipeline was constructed of precast reinforced concrete pressure pipe sections, and was completed in the fall of 1976. During the period of construction the bureau supervised, inspected, tested, and approved the supplier’s pipe fabrications and Groves’ installation work.

Plaintiff began test-filling the pipeline in March 1977. Leaks were observed and, upon inspection, numerous cracks and leaky joints were found in the pipeline.

A series of meetings was held between the parties during which Groves took the position that the failures resulted from faulty specifications which had been called to the contracting officer’s attention during construction. Also, on two occasions Groves requested a decision on responsibility for the failures. After an independent evaluation by the bureau, Groves sent a letter to the bureau on December 5, 1978, requesting for a third time a decision on responsibility. On January 5, 1979, the bureau responded by letter stating that no part of the pipeline was acceptable and that Groves was responsible for replacement or repair. The letter stated further:

Acceptable corrective measures include any one of the following: (1) removal and replacement of the entire pipeline to specifications lines, grades, and requirements, [600]*600(2) installation of a mortar lined steel pipe inside the existing pipe * * * or (3) * * *.2
You are directed to proceed immediately with one of the three alternates * *****

Plaintiff sought injunctive and declaratory relief from the January 5, 1979, directive by filing suit in the United States District Court for the District of Colorado on February 7, 1979. On February 23, 1979, the contracting officer issued his findings of fact and decision, specifying the alleged failures on the part of plaintiff and repeating the directive and statements contained in the bureau’s January 5, 1979, letter. On March 23, 1979, the decision of the contracting officer was appealed by plaintiff to the Interior Board of Contract Appeals (board).

Various extensions of time for plaintiff to file a complaint were allowed by the board.

On May 13, 1980, the bureau sent plaintiff a cure notice stating that if no response were received within 10 days, the Government might consider termination of the contract for default. On June 5, 1980, plaintiff responded to the bureau that it was prepared to commence appropriate action under alternatives (1) or (2) of the February 23, 1979, directive, at the bureau’s election. On June 11,1980, the bureau directed plaintiff to proceed under alternative (2), i.e., by installation of the steel liner.3 Plaintiff is currently engaged in carrying out that directive.

Following the several extensions of time allowed by the board, inter alia, to permit plaintiff to seek judicial resolution of the case, that body ultimately dismissed the appeal before it on July 31, 1980, without prejudice to reinstatement by either party at any time prior to July 31, 1981.

On August 8, 1980, the district court issued an order holding that it had no jurisdiction over plaintiffs claim, which order, upon plaintiffs motion, the district court modified to transfer the case to us.4

[601]*601Plaintiffs first amended petition here alleges five claims for relief: estoppel, breach of contract, cardinal change, rescission and restitution, and return of retainages. Defendant contends that plaintiff has failed to exhaust its administrative remedies. We now set forth our reasons for granting, in our order dated May 22, 1981, defendant’s motion to dismiss, without prejudice to plaintiffs rights under the Wunderlich Act.

II.

Plaintiff contends defendant has breached its contract, asserting that it undertook to construct for defendant, not just any pipeline, but a pipeline according to plans and specifications warranted by defendant. Plaintiff argues that defendant’s directives, after the first filling of the pipeline, without providing change orders or reimbursement, constituted a major breach of contract of implied warranty and other implied and express covenants and promises. Defendant points out that plaintiff did not raise these arguments until the filing herein of plaintiffs opposition to the motion to dismiss, and asserts that plaintiff is attempting to circumvent the exhaustion of remedies doctrine. Plaintiff admits that these allegations are in addition to the claims set forth in the first amended petition, but asserts that facts previously alleged and undisputed "overwhelmingly support Grove’s claims.” Plaintiff recognizes that it has a considerable burden to establish that a breach has occurred. This, plaintiff claims, it has achieved.

Basically, plaintiffs argument is threefold: (1) the directive to install the steel liner constituted a cardinal change; (2) the full-time inspection, supervision, and interim approvals by defendant during construction estops the latter from rejecting the entire pipeline; and (3) the timing of the steel liner directive, creating a "new kind of pipeline,” after completion of the one contracted for, raises the remedies of rescission and restitution.

We agree with plaintiff that, if it established a cardinal change, we would have jurisdiction to take the case notwithstanding any failure to pursue to conclusion its [602]*602administrative remedies. The standard is set forth in Air-A-Plane Corp.,5 where we said:

The basic standard * * * is whether the modified job "was essentially the same work as the parties bargained for when the contract was awarded. * * *” * * *

Plaintiff argues that it meets this standard, that the disproportionate cost of installing the steel liner, as compared to the contract price for constructing the concrete pipe, cries out "cardinal change!” Plaintiff cites Luria Bros. & Co.,6 where we held that changes requiring significant increases in the cost of footings deeper than those originally specified for an aircraft hangar "were of such magnitude that they were not within the scope of the original contract but rather constituted a breach thereof.”7 Also cited is Edward R. Marden8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
American Apparel, Inc. v. United States
108 Fed. Cl. 11 (Federal Claims, 2012)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Pacific Northern Timber Co. v. United States
38 Cont. Cas. Fed. 76,455 (Federal Claims, 1992)
W & J Construction Corp. v. United States
34 Cont. Cas. Fed. 75,318 (Court of Claims, 1987)
S.J. Groves & Sons Co. v. United States
28 Cont. Cas. Fed. 81,411 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
661 F.2d 170, 29 Cont. Cas. Fed. 81,880, 228 Ct. Cl. 598, 1981 U.S. Ct. Cl. LEXIS 480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-j-groves-sons-co-v-united-states-cc-1981.