W & J Construction Corp. v. United States

34 Cont. Cas. Fed. 75,318, 12 Cl. Ct. 507, 1987 U.S. Claims LEXIS 107
CourtUnited States Court of Claims
DecidedJune 19, 1987
DocketNo. 666-85C
StatusPublished

This text of 34 Cont. Cas. Fed. 75,318 (W & J Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W & J Construction Corp. v. United States, 34 Cont. Cas. Fed. 75,318, 12 Cl. Ct. 507, 1987 U.S. Claims LEXIS 107 (cc 1987).

Opinion

OPINION

SETO, Judge.

This government contract case comes before the court on defendant’s motion for an order to dismiss plaintiff’s claim for lack of jurisdiction, or in the alternative, for summary judgment. Defendant asserts that plaintiff’s “direct access” to the Claims Court under 41 U.S.C. § 609(a) (1982) is precluded by its alleged election to proceed before the National Aeronautics and Space Administration Board of Contract Appeals (NASA Board or Board). Plaintiff in response asserts that its proceedings before the Board were undertaken merely to request a final decision on the contract claim from the contracting officer as authorized by 41 U.S.C. § 605(c)(4) (1982), and cannot be construed as a binding election to bring the merits of its claim before the Board. For the reasons stated herein, we find that plaintiff’s claim is properly before the Claims Court and thus defendant’s motions are DENIED.

FACTS1

Plaintiff, W & J Construction Corporation, entered into a contract with the National Aeronautics and Space Administration (NASA) in May 1982 to build a solid rocket booster facility at Kennedy Space Center, Florida. As a result of alleged design deficiencies in the govemment-fur-[508]*508nished drawings, plaintiff contends it incurred impact and delay costs and submitted a certified claim to the contracting officer seeking recovery of those costs in April 1985. The contracting officer, however, failed to issue a final decision on plaintiff’s certified claim, or to notify plaintiff of the time within which a decision would be issued, as required by 41 U.S.C. § 605(c)(2). See Defendant’s Appendix at 9. Consequently, plaintiff sent two arguably vague letters to the Board in July 1985. Plaintiff’s first letter to the Board, captioned “Notice of Intent to Appeal2 Failure of Contracting Officer to Issue a Final Decision,” stated that:

The Contracting Officer has failed and refused to issue a final decision on [the structural steel delays] claim even though the time period has long since passed.
Therefore, ... this shall constitute our Notice of Intent to appeal the Contracting Officer’s failure to issue a Final Decision in connection with the above-referenced claim.

See Defendant’s Appendix at 7-8.

Plaintiff’s second letter, dated July 24, stated:

We refer you to our letter of July 23 wherein we filed the Notice of Intent to Appeal the Contracting Officer’s failure to issue a Final Decision.
Through an abundance of caution, we wish to advise that our client has elected to proceed under the Contract Disputes Act of 1978. We further advise that the Contracting Officer failed to comply with the mandates of either subparagraphs (A) or (B) of Section 6(c)(2) of the Act. We incorporate herein the text of our letter of July 23 so as to make it abundantly clear that your Board has jurisdiction over these proceedings.

See Defendant’s Appendix at 9.

The Board, in a letter dated July 30, 1985, responded to plaintiff that it had:

Received and docketed the appeal of [plaintiff] relating to the alleged failure of the Contracting Officer to issue a final decision with respect to its certified claim____
If the claim is not settled within 30 days from the date of this notice, the Contracting Officer shall issue a final decision pursuant to the Contract Disputes Act of 1978, and the implementing regulations. The Contracting Officer is requested to timely furnish a copy of the decision to this Board.
Upon receipt of the Contracting Officer’s decision Appellant may then appeal the decision or bring suit on it pursuant to Section 7 or 10 respectively of the Contract Disputes Act of 1978.
Failure to issue the decision within the period of the stay of the proceedings will be deemed a decision denying the claim and will authorize the commencement of the appeal or suit on the claim pursuant to Section 6(c)(5) of the Contract Disputes Act of 1978.

See Defendant’s Appendix at 15-16.

On July 29, the contracting officer issued a final decision on the contract dispute in favor of defendant, and informed plaintiff in its order that plaintiff had available two avenues in which to appeal the adverse decision, either to the NASA Board or directly to the U.S. Court of Claims. See Defendant’s Appendix at 12. The Board received the officer’s final decision on August 12, 1985 and thereafter dismissed plaintiff’s claim, reiterating the contracting officer’s statement that the adverse decision could be appealed to either the Board or to the Claims Court under the Contract Disputes Act. See Defendant’s Appendix at 17-18. Plaintiff filed this suit in the Claims Court on November 13, 1985, asserting jurisdiction under 28 U.S.C. § 1491 and 41 U.S.C. § 609(a)(1).

DISCUSSION

The pivotal issue in this case is whether plaintiff’s letters to the Board, set out above in pertinent part, should be construed as an appeal from a deemed denial, [509]*509as provided for in section 605(c)(5)3 or, as a request for for an actual decision from the contracting officer as authorized by section 605(c)(4).4

Defendant, characterizing the letters as the former, moves to dismiss plaintiffs claim on the ground that plaintiff is precluded from invoking section 609(a)(1),5 which provides a contractor direct access to the Claims Court in lieu of appealing the contracting officer’s adverse decision to an agency board. Since plaintiff elected to submit its claim to the Board, defendant avers, it can no longer elect to appeal directly to the Claims Court. See Diamond Manufacturing Co. v. United States, 3 Cl.Ct. 424, 427 (1983), citing Tuttle/White Constructors, Inc. v. United States, 228 Ct.Cl. 354, 656 F.2d 644 (1981) and Santa Fe Engineers v. United States, 230 Ct.Cl. 512, 677 F.2d 876 (1982), Defendant urges this court to find that plaintiff’s letters to the Board appealing from the contracting officer’s failure to issue a final decision, constituted plaintiff’s binding election of a forum and therefore, the instant appeal of the contracting officer’s final decision cannot be maintained in this court. See Beacon Oil Co. v. United States, 8 Cl.Ct. 695, 697, 699 (1985) (electing to appeal contracting officer’s final decision to agency board precludes jurisdiction in Claims Court).

Plaintiff countervails that defendant misconstrues the nature and the implications of the letters it submitted to the NASA Board.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Essex Electro Engineers, Inc. v. The United States
702 F.2d 998 (Federal Circuit, 1983)
Zinger Construction Company, Inc. v. The United States
753 F.2d 1053 (Federal Circuit, 1985)
S.E.R., Jobs for Progress, Inc. v. United States
759 F.2d 1 (Federal Circuit, 1985)
Pathman Construction Company, Inc. v. The United States
817 F.2d 1573 (Federal Circuit, 1987)
Diamond Manufacturing Co. v. United States
31 Cont. Cas. Fed. 71,579 (Court of Claims, 1983)
G & H Machinery Co. v. United States
32 Cont. Cas. Fed. 73,201 (Court of Claims, 1985)
Beacon Oil Co. v. United States
33 Cont. Cas. Fed. 74,025 (Court of Claims, 1985)
Turner Construction Co. v. United States
33 Cont. Cas. Fed. 74,117 (Court of Claims, 1985)
Vemo Co. v. United States
33 Cont. Cas. Fed. 74,095 (Court of Claims, 1985)
LaCoste v. United States
33 Cont. Cas. Fed. 74,201 (Court of Claims, 1986)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)
National Electric Coil v. United States
28 Cont. Cas. Fed. 81,219 (Court of Claims, 1981)
Tuttle/White Constructors, Inc. v. United States
656 F.2d 644 (Court of Claims, 1981)
S. J. Groves & Sons Co. v. United States
661 F.2d 170 (Court of Claims, 1981)
Santa Fe Engineers, Inc. v. United States
677 F.2d 876 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,318, 12 Cl. Ct. 507, 1987 U.S. Claims LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-j-construction-corp-v-united-states-cc-1987.