Vemo Co. v. United States

33 Cont. Cas. Fed. 74,095, 9 Cl. Ct. 217, 1985 U.S. Claims LEXIS 877
CourtUnited States Court of Claims
DecidedNovember 27, 1985
DocketNo. 589-84C
StatusPublished
Cited by11 cases

This text of 33 Cont. Cas. Fed. 74,095 (Vemo Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vemo Co. v. United States, 33 Cont. Cas. Fed. 74,095, 9 Cl. Ct. 217, 1985 U.S. Claims LEXIS 877 (cc 1985).

Opinion

OPINION

YOCK, Judge.

This contract case comes before the Court on the defendant’s motion to dismiss the plaintiff’s complaint on the grounds that its claim is time-barred by the statute of limitations prescribed by 41 U.S.C. § 609(a) (1982). The defendant’s motion will be treated as a motion for summary judgment, since various evidentiary materials have been submitted for the consideration of the Court in acting on the motion. See RUSCC 12(b).

For the reasons discussed herein, the motion is denied. There is no dispute on the material facts.

Facts

On September 30, 1982, The Vemo Company (“Vemo”) was awarded Contract No. N62474-80-C-9011 for the construction of the Unaccompanied Enlisted Personnel Housing Complex at the Puget Sound Naval Shipyard, Bremerton, Washington. Commercial Electrical Contractors, Inc. (“CEC”) was the subcontractor performing the electrical work for the project under Vemo, the prime contractor. The contract called for the installation of approximately 3,200 feet of high voltage power feeder cable. A dispute arose between Vemo and the Department of the Navy over contract specifications regarding the type of cable to be used in the primary power feeder. Basically, the Navy contended that the contract called for Vemo to use single conductor copper cable, whereas the plaintiff contended that the contract specifications allowed for the use of three conductor aluminum cable. The Navy eventually ordered the plaintiff to use the single conductor copper cable. Vemo thereafter, on January 14, 1983, submitted a request for a change order regarding the cable on behalf of its subcontractor CEC. The Resident Officer in Charge of Construction denied [218]*218Vemo’s request in a response dated February 8, 1983. On March 16, 1983, Vemo submitted a properly certified claim for an equitable adjustment pertaining to the cable dispute and asked for a final decision by the Navy's contracting officer. On July 22, 1983, Vemo again wrote to the Navy contracting officer requesting a final decision, noting that it had received no response during the 127 days that had passed since its previous request. In late September 1983, the Navy represented that a decision would be reached within a month. That deadline passed, and the Navy subsequently declined to state when the claim would be processed. During February 1984, plaintiff’s counsel met with Mr. Emil Wynn, Head Contract Claims Branch, Western Division, Naval Facilities Engineering Command, San Bruno, California. At that meeting, the Navy indicated that a decision on Vemo’s cable claim would be forthcoming. When Vemo had not heard from the Navy by March 28, 1984, it again wrote to Mr. Wynn requesting that a final decision be reached.

Subsequently, in early August 1984, plaintiff’s counsel traveled to Washington, D.C., to meet with Mr. Paul Bonacoursi at the headquarters of the Naval Facilities Engineering Command (NFEC), Alexandria, Virginia. At this point, the claim had been transferred to NFEC from San Bruno for evaluation. Mr. Bonacoursi indicated that a decision on the claim would be issued in approximately two weeks. When two weeks had passed with no decision being made, plaintiff notified the Navy by letter dated August 29,1984, that a suit would be commenced in the Claims Court if the claim was not resolved by September 7, 1984. No resolution was forthcoming, and on November 13, 1984, plaintiff filed a direct access complaint in this Court. Subsequently, the contracting officer issued a written decision on December 4, 1984, denying Vemo’s claim, which was received by Vemo on December 12, 1984. In that final decision, the Navy informed the plaintiff that it could bring an action directly in this Court within twelve months of its receipt.

Discussion

The defendant has now moved to dismiss this action asserting that the plaintiff’s claim is time-barred by section 609(a)(3) of the Contract Disputes Act of 1978 (CDA). 41 U.S.C. § 601 et seq. (1982).

In support of its motion to dismiss the plaintiff’s complaint, the defendant argues that the 60-day period within which a contracting officer must issue a decision started running for plaintiff’s claim on March 16, 1983. This was the date that Vemo had submitted its properly certified claim to the Navy’s contracting officer. When the claim had not been decided within 60 days, i.e., on May 16, 1983, the claim was “deemed” denied under section 605(c)(5) of the CDA. The defendant contends that the twelve-month statute of limitations of section 609(a)(3) then began running from that date—i.e., May 16, 1983. Thus, the Government asserts that the plaintiff had until May 16,1984, twelve months from the date of the “deemed” decision, to file its claim within section 609(a) of the CDA or be forever barred. Since the plaintiff did not file its direct access complaint in this Court until November 13, 1984, its claim is time barred, and the complaint should be dismissed.

The plaintiff has responded with three basic points in opposition to the Government’s motion. First, the plaintiff contends that the Government has misinterpreted section 605(c)(5) of the CDA, in that this provision is, in fact, permissive and not mandatory, thereby giving the plaintiff the choice of filing suit if the contracting officer has not yet reached a final decision within the relevant 60-day time period. Second, the plaintiff asserts that the one-year statute of limitations, contained in section 609(a)(3) of the CDA, only relates to the time period that begins to run after the contracting officer has issued an actual final decision, and not a deemed final decision. Third and finally, the plaintiff argues that it is inequitable and unjust to place on the plaintiff the burden of filing what may be a premature and costly suit when it is the Government’s dereliction of [219]*219duty that is the heart of the problem. This is especially inequitable and unfair when the Government is promising at every step of the proceeding to render a final decision forthwith, as are the circumstances of this case.

As earlier indicated, this Court agrees with the plaintiff’s contentions in this regard and therefore denies the Government’s motion.

Title 41 U.S.C. § 609(a) (1982) provides in pertinent part:

(1) * * * [I]n lieu of appealing the decision of the contracting officer under section 605 of this title to an agency board, a contractor may bring an action directly on the claim in the United States Claims Court, notwithstanding any contract provision, regulation, or rule of law to the contrary.
* * * * * *
(3) Any action under paragraph (1) * * shall be filed, within twelve months from the date of the receipt by the contractor of the decision of the contracting officer concerning the claim, and shall proceed de novo in accordance with the rules of the appropriate court. [Emphasis supplied.]

In addition, 41 U.S.C. § 605(c) (1982) provides in pertinent part:

(2) A contracting officer shall, within sixty days of receipt of a submitted certified claim over $50,000—

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland State Police v. Warwick Supply & Equipment Co.
624 A.2d 1238 (Court of Appeals of Maryland, 1993)
Orbas & Associates v. United States
38 Cont. Cas. Fed. 76,373 (Court of Claims, 1992)
Durable Metal Products, Inc. v. United States
36 Cont. Cas. Fed. 75,897 (Court of Claims, 1990)
Rhen v. United States
35 Cont. Cas. Fed. 75,672 (Court of Claims, 1989)
W & J Construction Corp. v. United States
34 Cont. Cas. Fed. 75,318 (Court of Claims, 1987)
Pathman Construction Company, Inc. v. The United States
817 F.2d 1573 (Federal Circuit, 1987)
Kunz Construction Co. v. United States
34 Cont. Cas. Fed. 75,243 (Court of Claims, 1987)
Malissa Co. v. United States
33 Cont. Cas. Fed. 74,927 (Court of Claims, 1986)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)
LaCoste v. United States
33 Cont. Cas. Fed. 74,201 (Court of Claims, 1986)
Turner Construction Co. v. United States
33 Cont. Cas. Fed. 74,117 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,095, 9 Cl. Ct. 217, 1985 U.S. Claims LEXIS 877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vemo-co-v-united-states-cc-1985.