G & H Machinery Co. v. United States

32 Cont. Cas. Fed. 73,201, 7 Cl. Ct. 199, 1985 U.S. Claims LEXIS 1080
CourtUnited States Court of Claims
DecidedJanuary 9, 1985
DocketNo. 216-84C
StatusPublished
Cited by10 cases

This text of 32 Cont. Cas. Fed. 73,201 (G & H Machinery Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G & H Machinery Co. v. United States, 32 Cont. Cas. Fed. 73,201, 7 Cl. Ct. 199, 1985 U.S. Claims LEXIS 1080 (cc 1985).

Opinion

OPINION

ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

WHITE, Senior Judge.

This is an action by G & H Machinery Company, the plaintiff, to recover damages, and for other relief, in connection with an alleged breach of contract No. GS-05DP-(P)45869 (the contract), which the plaintiff entered into with the defendant (represented by a contracting officer of the General Services Administration (GSA)) in June 1974.

The case is now before the court on a motion filed by the defendant as a motion to dismiss but which will be treated as a motion for summary judgment, because various evidentiary materials have been submitted for the consideration of the court in acting on the motion. The plaintiff has responded to the motion; and the defendant has replied to the response.

The parties seem to agree on the basic facts of the case.

The Facts

According to the agreed facts, the contract called for the plaintiff to provide the labor and material necessary to repair certain government machinery. Pursuant to the contract, the GSA on March 18, 1975, issued orders for the modification and winterization of 40 warehouse tractors owned by the Government. Based on these orders, the plaintiff ordered the material that would be needed to perform the work on the 40 warehouse tractors. The material thus ordered by the plaintiff was specifically manufactured for use in modifying and winterizing the 40 tractors involved in the orders of March 18, 1975.

Later, the plaintiff received 29 of the warehouse tractors, and performed the required services on them.

On January 29, 1976, the plaintiff received an order which reduced to 29 the number of warehouse tractors that were to be modified and winterized.

The plaintiff was unable to dispose of the material which it had procured in order to perform the work on the 11 warehouse tractors eliminated from the contract by the order of January 29, 1976, as such material had been specifically manufactured for those warehouse tractors. The plaintiff attempted to turn the surplus material over to the GSA, but that agency refused to accept it.

On October 13, 1978, the plaintiff submitted its claim in this matter to the GSA contracting officer.

The contracting officer, however, did not render a decision on the plaintiff’s claim, despite repeated requests by the plaintiff that he do so. Finally, in a letter to the contracting officer under the date of July 15, 1982, the plaintiff stated in part as follows:

I am at a loss to understand why you have not rendered a decision in this mat[201]*201ter. I must remind you that Title 41, USCA, Section 605(c2) provides that you are to make a decision within sixty (60) days of receipt of a claim or notify me of the time within which a decision will be issued.
If I have not received a response from you within a fairly short time, I will either request that the Board of Contract Appeals directs you to issue a decision or file an appeal without a decision.

In a response dated July 29, 1982, the contracting officer promised the plaintiff that he would render a decision on or before August 31, 1982. This promise was not kept, however, and the contracting officer had not rendered a decision on the plaintiff’s claim as of the date, May 1,1984, when the plaintiff filed its complaint with this court.

Discussion

The defendant’s motion is based principally upon the contention that the plaintiff did not file its complaint within the time allowed by law for this purpose, inasmuch as the alleged breach of contract occurred in 1976 and the complaint was not filed until May 1, 1984, approximately 8 years later.

The plaintiff, on the other hand, relies upon the failure of the contracting officer to render a decision on its claim, and argues (inter alia) that the period of limitations was tolled by the contracting officer’s failure to act on the claim. In this connection, the plaintiff says in its brief that the disputes clause of the contract in question required the plaintiff to submit its claim to the contracting officer; and that “[a] claim against the United States does not accrue until any mandatory administrative proceedings are concluded,” citing Lins v. United States, 231 Ct.Cl. 579, 688 F.2d 784 (1982), cert. denied, 459 U.S. 1147, 103 S.Ct. 788, 74 L.Ed.2d 995 (1983), Friedman v. United States, 159 Ct.Cl. 1, 310 F.2d 381 (1962), cert. denied, 373 U.S. 932, 83 S.Ct. 1540, 10 L.Ed.2d 691 (1963).

The difficulty with the plaintiff’s position on this point is that, under the provisions of the so-called Wunderlich Act (41 U.S.C. §§ 321, 322 (1976)) in effect at the time when the alleged breach of contract occurred, the disputes clause of a government contract did not cover a claim based upon an alleged breach of contract, and such a claim was not redressable by the contracting officer or other agency personnel under the provisions of the contract. Cf. United States v. Utah Construction & Mining Co., 384 U.S. 394, 412, 86 S.Ct. 1545, 1555, 16 L.Ed.2d 642 (1966). Thus, the filing of a claim with the contracting officer was not a “mandatory” administrative procedure in 1976 if the claim was based on an alleged breach of contract.

It has been held in numerous cases that the running of the limitations period is not affected by an attempt to obtain administrative relief through a procedure not mandated by law (e.g., Camacho v. United States, 204 Ct.Cl. 248, 259, 494 F.2d 1363, 1369 (1974); Steel Improvement & Forge Co. v. United States, 174 Ct.Cl. 24, 29, 355 F.2d 627, 631 (1966)).

At the time of the alleged breach in this case, a contractor’s only means of obtaining redress on a breach of contract claim (if it exceeded $10,000, as is true in this case) was to file an action with this court’s predecessor, the United States Court of Claims, under 28 U.S.C. § 1491 (1976). Moreover, it was necessary, under the Court of Claims’ general limitations provision, that the contractor institute its action in that court “within six years after such claim first accrues” (28 U.S.C. § 2501 (1976)), which the plaintiff in this case failed to do.

Thus, under the law as it existed in 1976, the plaintiff began its action too late.

The plaintiff points out, quite correctly, that the law of government contracts was changed considerably by the Contract Disputes Act of 1978 (Pub.L. 95-563; 92 Stat. 2383), which was enacted on November 1, 1978, and, under section 16 of the act (92 Stat. at 2391), became effective 120 days later.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Maryland State Police v. Warwick Supply & Equipment Co.
624 A.2d 1238 (Court of Appeals of Maryland, 1993)
W & J Construction Corp. v. United States
34 Cont. Cas. Fed. 75,318 (Court of Claims, 1987)
Pathman Construction Company, Inc. v. The United States
817 F.2d 1573 (Federal Circuit, 1987)
Kunz Construction Co. v. United States
34 Cont. Cas. Fed. 75,243 (Court of Claims, 1987)
Malissa Co. v. United States
33 Cont. Cas. Fed. 74,927 (Court of Claims, 1986)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)
Turner Construction Co. v. United States
33 Cont. Cas. Fed. 74,117 (Court of Claims, 1985)
Vemo Co. v. United States
33 Cont. Cas. Fed. 74,095 (Court of Claims, 1985)
Timberland Paving & Construction Co. v. United States
33 Cont. Cas. Fed. 73,781 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,201, 7 Cl. Ct. 199, 1985 U.S. Claims LEXIS 1080, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-h-machinery-co-v-united-states-cc-1985.