Timberland Paving & Construction Co. v. United States

33 Cont. Cas. Fed. 73,781, 8 Cl. Ct. 653, 1985 U.S. Claims LEXIS 929
CourtUnited States Court of Claims
DecidedAugust 20, 1985
DocketNo. 123-81C
StatusPublished
Cited by5 cases

This text of 33 Cont. Cas. Fed. 73,781 (Timberland Paving & Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timberland Paving & Construction Co. v. United States, 33 Cont. Cas. Fed. 73,781, 8 Cl. Ct. 653, 1985 U.S. Claims LEXIS 929 (cc 1985).

Opinion

OPINION

WOOD, Judge:

In this action, before the court for decision following trial on the merits, plaintiff, a Washington State corporation whose 1978 road construction contract with defendant was purportedly terminated for default April 23, 1980, sues to recover damages for an alleged breach of that contract, plus certain sums said to have been improperly withheld from plaintiff by defendant.

Defendant not only denies any liability to plaintiff but, by way of counterclaim, seeks to recover from plaintiff (in defendant’s words) both “damages for the lost benefit of its price bargain” and “contract liquidated damages” (or, as an alternative to the latter, “administrative costs incurred as a result of plaintiff’s breach.”)

With its answer and counterclaim, defendant filed a motion for notice to American Insurance Co. (American), plaintiff’s performance bond surety on the contract in suit. Defendant’s motion reflected that, as surety on plaintiff’s performance bond,

[655]*655American might “ultimately be held liable if the United States is successful on its counterclaim herein.” The motion was allowed in due course. American subsequently filed a response to defendant’s counterclaim, and has fully participated throughout pretrial and trial of this case.

For the reasons, and under the facts and circumstances, set forth hereinafter, the court concludes that the purported termination of plaintiff’s contract for default was invalid and of no legal force and effect, and that it is accordingly entitled to recover, but that, under the terms of the contract, the amount due plaintiff is to be determined, at least in the first instance, administratively. Accordingly, and pursuant to the provisions of 28 U.S.C. § 1491(a)(2) (1982), this case is hereby remanded to the Commissioner of Indian Affairs with instructions to proceed promptly to determine the amount due plaintiff “as if the notice of termination [for default] had been issued * * * ” to plaintiff pursuant to the contract “clause providing for termination for convenience of the Government * * *.”

Pursuant to RUSCC 60.1(a)(2), proceedings in this court are hereby stayed for a period not to exceed six months from the date of the filing of this opinion. The attorney of record for plaintiff shall report to the court the status of the matter on remand in conformity with the requirements of RUSCC 60.1(a)(5).

I

On September 29, 1978, defendant, acting through the Portland (Oregon) Area Office, Bureau of Indian Affairs (BIA), Department of the Interior,1 awarded to plaintiff Contract No. POOC14205709 (hereinafter “the contract”) to perform work on a project (“Project No. YIR 140(4),”) described as “Emulsified Asphalt Concrete Pavement, Grade and Drain on 9.195 miles of Signal Peak Road” on the Yakima Indian Reservation, Yakima County, Washington, at a firm fixed price of $1,282,842.2 Work was to be completed within 220 calendar days after receipt of notice to proceed. The contract contained Standard Form 23-A (Rev. 4-75), “General Provisions (Construction Contract),” which included standard Changes, Differing Site Conditions, Termination for Default, and Disputes Clauses. American furnished payment and performance bonds for plaintiff in connection with the contract.

On April 23, 1979, plaintiff received instructions to proceed with the contract work.3 The contracting officer then advised plaintiff that 170 days remained for contract performance. Plaintiff (through a subcontractor employed to clear, pioneer, drill and blast a rock bluff area between Station 296 and Station 323) began work at the project site on April 23, 1979.

By early June, 1979, subcontractor coordination difficulties had arisen. Moreover, plaintiff took the position that there was a serious safety problem in the rock bluff area, and asked that defendant inspect the work site and advise plaintiff how it could safely proceed with the contract work in that area. Defendant was of the view that no real safety problem existed, and that plaintiff should proceed to construct the rock cut as designed.

Work in the rock bluff area came to a halt about the middle of June, 1979, and neither plaintiff nor any of its subcontractors performed any work on the unclassified excavation work item in the contract during July and August 1979. Although plaintiff (through a new subcontractor) [656]*656subsequently did perform some work on the unclassified excavation item, progress on this work was slow. By October 13, 1979, four days after the time then allowed for completion of work under the contract had expired, plaintiff had completed approximately 27 percent of the work on Project No. YIR 140(4).

In the interim, during the period July 23 to August 1, 1979, and again from September 9 to 19, 1979, defendant had performed road maintenance in the project area, the asserted cost of which (some $5,295) was withheld from progress payments due plaintiff. Moreover, in mid-October 1979, the contracting officer advised plaintiff that liquidated damages would be assessed against plaintiff commencing October 10, 1979, and such damages were in fact assessed and also withheld from progress payments due plaintiff.4

Between June and November 1979, considerable discussion about, and some investigation into, the matter of safely performing work in the rock bluff area had taken place, and on November 21, 1979, a meeting, at which plaintiff proposed a design change in the project, was held. BIA then agreed that it would consider the proposed change. As will be seen, the proposal remained under consideration by the BIA for some three months thereafter, but was ultimately rejected.

On November 23, 1979, two days after the meeting described in the proceding paragraph, Mr. Powers, as contracting officer, suspended work on the project due to unfavorable weather as of the close of business that day. He then advised plaintiff that it had exceeded total contract time by 45 days. On November 27, 1979, Mr. Powers directed to plaintiff a notice to show cause why the contract should not be terminated for default. Plaintiff responded to that notice December 12,1979, asserting (in broad terms) that any action to terminate the contract for default at that time would be inappropriate.

By letter, dated December 13, 1979, to Mr. Powers, as contracting officer, plaintiff transmitted two claims. The first was for contract payments allegedly improperly withheld in consequence of government performance of road maintenance for which, according to the BIA, plaintiff was responsible. The second was for contract payments withheld in consequence of an allegedly “improper and erroneous assessment of liquidated damages.” In conjunction with the latter claim, plaintiff specifically asserted that it was entitled to a considerable extension of contract time, and that, in substance, it was not then in default. With respect to both claims, plaintiff gave notice that “the contractor elects to have your determination * * * made under the Contract Disputes Act of 1978 * *.”

In or prior to mid-January, 1980, Mr. Powers, to that point the BIA Area Property and Supply Officer in Portland, was transferred to Washington, D.C.,5 where he worked for a time as Special Assistant to the BIA Commissioner.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
Bearingpoint, Inc. v. United States
82 Fed. Cl. 181 (Federal Claims, 2008)
Timberland Paving & Construction Co. v. United States
35 Cont. Cas. Fed. 75,713 (Court of Claims, 1989)
City of El Centro v. United States
16 Cl. Ct. 500 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 73,781, 8 Cl. Ct. 653, 1985 U.S. Claims LEXIS 929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timberland-paving-construction-co-v-united-states-cc-1985.