Morrison Assurance Co. v. United States

31 Cont. Cas. Fed. 71,711, 3 Cl. Ct. 626, 52 A.F.T.R.2d (RIA) 6223, 1983 U.S. Claims LEXIS 1585
CourtUnited States Court of Claims
DecidedOctober 27, 1983
DocketNo. 195-81T
StatusPublished
Cited by21 cases

This text of 31 Cont. Cas. Fed. 71,711 (Morrison Assurance Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison Assurance Co. v. United States, 31 Cont. Cas. Fed. 71,711, 3 Cl. Ct. 626, 52 A.F.T.R.2d (RIA) 6223, 1983 U.S. Claims LEXIS 1585 (cc 1983).

Opinion

OPINION

LYDON, Judge:

Plaintiff, a surety company, had underwritten Miller Act bonds on a National Park Service (Park Service) construction contract with Consolidated Building Corporation (CBC) pursuant to 40 U.S.C. § 270a (1976). In this action plaintiff seeks to recover $30,119.15, representing the final contract payment, which the Park Service withheld from it and paid over to the Internal Revenue Service (IRS) pursuant to a tax levy issued by the IRS. The IRS had levied on the unpaid contract proceeds, which were otherwise due plaintiff, because CBC had a Federal tax deficiency of $30,-119.15.

Plaintiff claims that, under the circumstances of this case, the Park Service was not entitled to setoff CBC’s tax liability from contract proceeds otherwise due and owing plaintiff since completion of the contract in question was due solely to plaintiff’s actions as a completing surety under its performance bond. Defendant disputes plaintiff’s contention that it was a completing surety, and further argues that even assuming plaintiff to be a d'e facto completing surety, plaintiff was not a de jure completing surety since there was no formal default of the contractor which would serve to give rise to a formal takeover of contract performance by the surety in accordance with Federal Procurement Regulations (FPR), 41 C.F.R. §§ 1-18.803-1 to 1-18.-803-5, l-18.803-6(c) (1979).

Following trial, and after consideration of the submissions of the parties, it is concluded on the basis of the particular facts in this case, that plaintiff should be deemed to have completed the project as a completing surety and that the expenses incurred after it took over the contract were incurred under its performance bond. Consequently, plaintiff is entitled to the full amount of the contract proceeds free from any setoff for the contractor’s tax liabilities.

I.

On September 28, 1978, CBC contracted with the Park Service to perform renovation and construction work at the Cumberland Island National Seashore in Georgia for the contract price of $172,907. Under the terms of the contract between CBC and the Park Service, the Park Service agreed to pay CBC with a series of earned progress payments. The Park Service retained 10 percent of the progress payments due until satisfactory completion of the project.1

On October 20, 1978, plaintiff issued to CBC a payment bond and a performance bond for the Cumberland Island project. Plaintiff’s liability limit on the payment bond was $86,453.50, and its liability limit on the performance bond was $172,907. These bonds named plaintiff as surety, CBC [629]*629as principal, and the Park Service as obli-gee.

Prior to this time, on April 30, 1978, plaintiff and CBC had entered into a General Agreement of Indemnity. This agreement applied to all present and future CBC construction projects bonded by plaintiff, and therefore it included the Cumberland Island project. The agreement defined plaintiff’s indemnity rights with respect to construction bonds underwritten by plaintiff for CBC’s bonded projects. This agreement listed certain conditions which would serve to put CBC in default on the construction bonds. Two separate conditions of default listed in the agreement were: (1) “[if] Principal fails to pay for any labor or materials when due,” and (2) “[if] any obligee declares Principal to be in default.” The agreement further provided that in the event of CBC’s default, plaintiff could take over any of CBC’s bonded contracts and arrange for that project’s completion.

In February 1979, CBC began work on the Cumberland Island project. The project involved construction and historical renovation work on two structures at the Cumberland Island National Seashore, namely, the Captain’s House and the Carpenter’s Shop. CBC’s performance on the project thereafter proceeded in a fashion satisfactory to the Park Service.

About May 1979, plaintiff received several notices that CBC had failed to pay some suppliers and subcontractors on certain jobs bonded by plaintiff. None of these subcontractors or suppliers were on the Cumberland Island project. Plaintiff then began an initial investigation into CBC’s financial status. This initial investigation was conducted by plaintiff’s managing general agent.

As a result of CBC’s poor financial status, which this initial investigation disclosed, plaintiff hired a certified public accountant to conduct a more thorough investigation into CBC’s financial state. The accountant’s investigation disclosed that CBC had serious financial problems. Among CBC’s liabilities was an amount of $51,406.72 which CBC owed in delinquent state and Federal taxes, and another $10,089 which CBC owed in penalties for nonpayment of said taxes. Included in this tax delinquent amount was $24,216.23 which CBC owed the IRS for delinquent payroll taxes. The Federal payroll taxes were delinquent because CBC had deducted the amounts from the paychecks of its employees and then failed to deposit the amount with the IRS as required by law.

Essentially, plaintiff’s investigation into CBC’s financial status disclosed that CBC was currently operating only by nonpayment and/or delay in payment of its financial obligations. As a result, on the surface CBC’s contract performance gave no indication to the Park Service of CBC’s precarious financial situation. Because of CBC’s failure to pay some of its suppliers and subcontractors and its tax obligations, as of May 1979, plaintiff was in default on its April 30, 1978, indemnity agreement with plaintiff. On May 31, 1979, plaintiff sent a letter to the Park Service instructing it to stop all payments to CBC on the Cumberland Island contract. The Park Service at that time stopped all payments to CBC for work done in the Cumberland Island project. As of that date, the Park Service had paid some $52,900 to CBC on its contract.

In June 1979, CBC stopped work on the Cumberland Island project. Ostensibly, this work stoppage was a result of CBC’s inability to procure the proper grade of shingle for the Cumberland Island project. However, there was work which CBC could have performed without the shingles, and, moreover, CBC stopped work on all its government projects bonded by plaintiff after plaintiff froze the contract payments on each of them.

On or about July 17, 1979, plaintiff sent the Park Service a notice stating that all the proceeds of the Cumberland Island project were assigned to itself. The notice also stated that no monies were to be paid to CBC without the notification and consent of plaintiff. The Park Service accepted the assignment without determining whether CBC accepted it.

[630]*630CBC, in fact, contested the assignment and sent a letter to the Park Service on July 27, 1979, which disputed the assignment and claimed it to be invalid. The letter also stated that CBC would hold the Park Service liable for any amounts paid to plaintiff under the assignment. On August 3,1979, CBC took the further step of bringing suit in a federal district court against plaintiff and the Park Service. The suit alleged that the assignment of proceeds asserted by plaintiff was unlawful and invalid.

Meanwhile, during June and July 1979, plaintiff took action to curtail its liability on the government construction projects which it bonded for CBC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen Engineering Contractor Inc. v. United States
611 F. App'x 701 (Federal Circuit, 2015)
United States Fire Insurance v. United States
78 Fed. Cl. 308 (Federal Claims, 2007)
Dunn & Black, P.S. v. United States
366 F. Supp. 2d 1008 (E.D. Washington, 2005)
Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)
Miller-Stauch Construction Co. v. Williams-Bungart Electric, Inc.
959 S.W.2d 490 (Missouri Court of Appeals, 1998)
International Fidelity Insurance v. United States
27 Fed. Cl. 107 (Federal Claims, 1992)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)
Reliance Insurance v. United States
15 Cl. Ct. 62 (Court of Claims, 1988)
Indemnity Insurance Co. of North America v. United States
34 Cont. Cas. Fed. 75,436 (Court of Claims, 1988)
Egyptian American Bank, S.A.E. v. United States
34 Cont. Cas. Fed. 75,374 (Court of Claims, 1987)
Dependable Insurance v. United States
34 Cont. Cas. Fed. 75,347 (Court of Claims, 1987)
Aetna Casualty & Surety Co. v. United States
34 Cont. Cas. Fed. 75,263 (Court of Claims, 1987)
Universal Surety Co. v. United States
33 Cont. Cas. Fed. 74,603 (Court of Claims, 1986)
Timberland Paving & Construction Co. v. United States
33 Cont. Cas. Fed. 73,781 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,711, 3 Cl. Ct. 626, 52 A.F.T.R.2d (RIA) 6223, 1983 U.S. Claims LEXIS 1585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-assurance-co-v-united-states-cc-1983.