Allen Engineering Contractor Inc. v. United States

611 F. App'x 701, 123 Fed. Cl. 701
CourtCourt of Appeals for the Federal Circuit
DecidedMay 7, 2015
Docket2014-5094, 2014-5095, 2014-5096
StatusUnpublished
Cited by9 cases

This text of 611 F. App'x 701 (Allen Engineering Contractor Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen Engineering Contractor Inc. v. United States, 611 F. App'x 701, 123 Fed. Cl. 701 (Fed. Cir. 2015).

Opinion

CLEVENGER, Circuit Judge.

Allen Engineering Contractor Inc. appeals the decisions of the Court of Federal Claims, granting motions to dismiss, in their entirety, complaints for improper termination of a contract. Allen Eng’g Contractor Inc. v. United States, 115 Fed.Cl. 457 (2014); Allen Eng’g Contractor Inc. v. United States, No. 13-720 C, 2014 WL 1862269 (Fed.Cl. May 8, 2014); Allen Eng’g Contractor Inc. v. United States, No. 13-695 C, 2014 WL 1860074 (Fed.Cl. May 8, 2014). This court has jurisdiction under 28 U.S.C. § 1295(a)(3) (2012). Because Allen Engineering Contractor Inc. breached its agreement with the Navy, and has failed to establish any grounds for excusing this breach or shifting liability to the Navy, we affirm,

I

This case concerns the same set of operative facts, pertaining to three distinct construction contracts between Allen Engineering Contractor Inc. (“AECI”) and the United States Navy. Between June and July 2012, AECI entered into three construction contracts with the Navy individually valued at $2,855,419, $11,553,083, and $ 12,301,127.05. 1 In May 2013, the Navy terminated all three of the contracts because AECI had failed to maintain valid performance and payment bonds covering each of them. This was a material breach of AECI’s agreement with the Navy, and the Navy appropriately terminated the contracts under 48 C.F.R. § 52.249-10(a).

A contractor on a construction project worth more than $150,000 is required to *704 post and maintain performance and payment bonds covering 100 percent of the contract price. 40 U.S.C.. § 3131; 48 C.F.R. § 52.228-15(b). 2 The regulations require that the “bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the. list contained in Treasury Department Circular 570 ...” 48 C.F.R. § 52.228-15(d).

“Under a' performance bond, a surety guarantees that the project will be completed if a contractor defaults.' It is designed to ensure ‘that [the government] is not left with a partially completed project because of an insolvent contractor.’ ” Dependable Ins. Co. v. United States, 846 F.2d 65, 66 (Fed.Cir.1988) (citing Aetna Casualty & Sur. Co. v. United States, 845 F.2d 971, 973 (Fed.Cir.1988); Morrison Assurance Co. v. United States, 3 Cl.Ct. 626, 632 (1983)). And payment bonds are designed to protect people who have contractual relationships with the prime contractor or a subcontractor. J.W. Bateson Co., Inc. v. United States ex rel. Bd. of Trustees of Nat. Automatic Sprinkler Industry Pension Fund, 434 U.S. 586, 587, 98 S.Ct. 873, 55 L.Ed.2d 50 (1978). “Because ‘a lien cannot attach to Government property,’ persons supplying labor or materials on a federal construction project [are] protected by a payment bond.” Id. at 589, 98 S.Ct. 873 (quoting F.D. Rich Co. v. United States ex rel. Industrial Dumber Co., 417 U.S. 116, 121-22, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974)).

Shortly after the Navy awarded the contracts in question, AECI provided performance and payment bonds from Liberty Mutual Insurance Company (“Liberty”). The Navy accepted each of the Liberty bonds, and work commenced on all three projects.

Between February and March 2013, AECI sought to replace those Liberty bonds with bonds from the Pacific Indemnity Company (“PIC”). After investigating the validity and authenticity of the PIC bonds, and per AECI’s request, the Navy replaced the Liberty bonds with PIC bonds. Also per AECI’s request, the Navy returned the Liberty bonds. Then, in May 2013, PIC called AECI and the Navy to inform them that the bonds supposedly issued by PIC were fraudulent. The supposed-PIC bonds were not issued by PIC and were therefore invalid.

In light of that fact; the Navy suspended work on each of the three contracts in question. The Navy asked AECI to provide valid replacement bonds, but AECI was unable to secure them. Because AECI failed to secure valid bonds, on July 5, 2013, the Navy terminated one contract for default and on July 10, 2013, terminated the other two for default.

In the present action, AECI is seeking to have the default terminations converted to convenience terminations. It would be appropriate to convert these to terminations for the convenience of the government if “it is determined that the Contractor was not in default, or that the delay was excusable.” 48 C.F.R. § 52.249-10(c).

AECI relies on multiple theories to allege that the Navy improperly terminated these contracts, and that it therefore did not default on the contracts. The Court of Federal Claims (“CFC”) held AECI had failed to state a claim on which relief could be granted, and therefore granted the government’s motion to dismiss. This court reviews de novo a CFC decision to dismiss *705 for failure to state a claim. Hearts Bluff Game Ranch, Inc. v. United States, 669 F.3d 1326, 1328 (Fed.Cir.2012).

II

AECI’s arguments on appeal are the same as those it raised to the CFC. “[0]nly a complaint that states a plausible claim for relief survives a motion to dismiss.” Ashcroft v. Iqbal, 556 U.S. 662, 679, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (citing Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 556, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007)). And a “claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Id. We agree that the CFC correctly rejected each of AECI’s arguments, and address each argument in turn.

A

The Navy terminated the AECI contracts for default under 48 C.F.R. § 52.249-10(a). “If [a] Contractor refuses or fails to prosecute [ ] work ..., with the diligence that will insure its completion within the time specified in [a] contract ..., the Government may ... terminate the right to proceed with the work....” 48 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
611 F. App'x 701, 123 Fed. Cl. 701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-engineering-contractor-inc-v-united-states-cafc-2015.