Taino Construction Group, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedJuly 31, 2025
Docket24-2030
StatusPublished

This text of Taino Construction Group, LLC v. United States (Taino Construction Group, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taino Construction Group, LLC v. United States, (uscfc 2025).

Opinion

In the United States Court of Federal Claims TAINO CONSTRUCTION GROUP, LLC,

Plaintiff, No. 24-cv-2030 v. Filed: July 31, 2025 THE UNITED STATES,

Defendant,

Gary Green of Sidkoff, Pincus & Green, P.C., Philadelphia, PA appeared for Plaintiff. With him on the briefs was Larry M. Keller of Sidkoff, Pincus & Green, P.C., Philadelphia, PA.

Rafael Shapiro of the United States Department of Justice, Civil Division, Washington, D.C. appeared for Defendant. With him on the briefs were Patricia M. McCarthy, Eric P. Bruskin, and Yaakov Roth, of the United States Department of Justice, Civil Division, Washington, D.C., and Matney E. Rolfe of the United States Department of the Air Force.

MEMORANDUM AND ORDER

Soon after the Department of the Air Force (Air Force) contracted with Taino Construction

Group, LLC (Taino) to demolish nine buildings at Fort Eustis in Virginia, the Air Force began

having issues with Taino’s performance. After providing Taino with multiples notices and

opportunities to cure, the Air Force terminated Taino’s contract in 2021. After submitting its

Certified Claim to the contracting officer seeking payment for allegedly completed work that the

Air Force did not accept prior to termination, Taino now lodges claims here for breach of contract

and breach of the implied duty of good faith and fair dealing.

Taino’s claims face two dispositive hurdles. First, Taino’s Certified Claim lacked any

details related to its breach of the implied duty of good faith and fair dealing claim, which falls far

short of the “clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim” required to satisfy the Contract Disputes Act’s (CDA’s)

jurisdictional presentment requirement. Scott Timber Co. v. United States, 333 F.3d 1358, 1365

(Fed. Cir. 2003) (quoting Contract Cleaning Maint., Inc. v. United States, 811 F.2d 586, 592 (Fed.

Cir. 1987)). Thus, this Court lacks jurisdiction over this claim as Taino did not properly present

this claim to the contracting officer. Second, Taino’s contract with the Air Force expressly

provides that, in the event of a termination for cause, “the Government shall not be liable to the

Contractor for any amount for supplies or services not accepted.” Ex. A (ECF No. 1-2) (the

Contract) at 15 (quoting FAR 52.212-4(m)). All parties agree that the Air Force did not accept the

work for which Taino now seeks payment. Thus, Taino fails to state a breach of contract claim

because it is not entitled to a legal remedy on the facts it alleges. Accordingly, the Court Grants

the Air Force’s Motion to Dismiss pursuant to Rules 12(b)(1) and 12(b)(6).

FACTUAL HISTORY

On January 30, 2020, the Air Force awarded Taino a contract to demolish nine buildings

at Fort Eustis in Virginia for a firm-fixed price of $968,750. ECF No. 1 (Compl.) ¶¶ 24–26, 39;

Contract at 2–3, 5. 1 The Contract expressly incorporates the CDA and multiple provisions of the

1 The exhibits to Taino’s Complaint are cited as “Ex.” followed by a corresponding letter. See ECF Nos. 1-2–1-16 (Exhibits A–O). Where appropriate, the exhibits are defined as, and referred to by, a shorthand for clarity and ease of reference. When considering Defendant’s Motion under both Rules 12(b)(1) and 12(b)(6), the Court may rely upon exhibits attached to Taino’s Complaint. Sharifi v. United States, 987 F.3d 1063, 1067 (Fed. Cir. 2021) (explaining that exhibits to the Complaint may be considered at 12(b)(6) stage as the exhibits “are not ‘matters outside the pleadings.’” (quoting Rule 12(d))); Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed. Cir. 1988) (citing Land v. Dollar, 330 U.S. 731, 735 (1947)) (noting that where a Rule 12(b)(1) motion “challenges the truth of the jurisdictional facts alleged in the complaint, the district court may consider relevant evidence in order to resolve the factual dispute”); see also AlexSam, Inc. v. Aetna, Inc., 119 F.4th 27, 34 (Fed. Cir. 2024) (“Review of a motion to dismiss under Rule 12(b)(6) is generally limited ‘to the facts as asserted within the four corners of the complaint, the documents attached to the complaint as exhibits, and any documents incorporated in the complaint by reference.’” (quoting McCarthy v. Dun & Bradstreet Corp., 482 F.3d 184, 191 (2d Cir. 2007))); where the Complaint’s exhibits contradict Taino’s contentions, the Court must follow the exhibits. Allen Eng’g Contractor, Inc. v. United States, 115 Fed. Cl. 457, 464 (2014) (“In the event of

2 Federal Acquisition Regulation (FAR) in full and by reference. 2 Contract at 14 (“This Contract is

subject to 41 U.S.C. chapter 71, Contract Disputes. . . . [Disputes] arising under or relating to this

contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes,

which is incorporated herein by reference.” (quoting FAR 52.212-4(d))). FAR 52.212-4,

incorporated into the Contract in full and by reference, provides that “[t]he Government may

terminate this contract, or any part hereof, for cause in the event of any default by the Contractor,”

and, that in the event of such a termination, “the Government shall not be liable to the Contractor

for any amount for supplies or services not accepted . . . .” Contract at 15 (quoting FAR 52.212-

4(m)); see id. at 13–16 (incorporating full text of FAR 52.212-4(m)).

In December 2020, Taino submitted two invoices totaling $217,968.75—reflecting that it

had completed 22.5% of the Contract, which the Air Force paid in full. Ex. O (ECF No. 1-16) at

2; 3 see Compl. ¶ 39 (noting that the Air Force paid Taino $217,968.75). By March 2021, Taino’s

performance had begun to crumble. On March 19, 2021, the Air Force issued its first cure notice

to Taino. Compl. ¶ 31; Ex. G (ECF No. 1-8) (First Cure Notice) at 2. In its First Cure Notice, the

Air Force notified Taino of four “failures that need[ed] to be corrected,” including Taino’s

conflict between the bare allegations of the complaint and any exhibit attached . . . , the exhibit prevails.” (quoting Fayetteville Invs. v. Com. Builders, Inc., 936 F.2d 1462, 1465 (4th Cir. 1991))), aff’d, 611 F. App’x 701 (Fed. Cir. 2015); 5A Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 1327 (3d ed. 2004 & Supp. 2016) (Wright & Miller). 2 The Federal Acquisition Regulation (FAR) is contained in Chapter 48 of the Code of Federal Regulations. All references to the FAR are shorthand for “48 C.F.R. §.” 3 Citations throughout this Memorandum and Order correspond to the ECF-assigned page numbers, which do not always correspond to the pagination within the document. Exhibit O is the Contracting Officer’s Final Decision denying Taino’s Certified Claim, which contains a full record of the correspondence between Taino and the Air Force.

3 (i) failure to provide an “AF 3064 Contract Progress Schedule in a timely manner,” 4

(ii) unavailability of its superintendent on the work site during operations, (iii) failure to secure

Defense Biometric Identification System Passes for the work crew to begin work, and

(iv) nonresponsiveness to calls and emails. First Cure Notice at 2. The Air Force warned Taino

that if it failed to cure these issues within ten days, by March 29, 2021, “the Government may

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
McCarthy v. Dun & Bradstreet Corp.
482 F.3d 184 (Second Circuit, 2007)
Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Land v. Dollar
330 U.S. 731 (Supreme Court, 1947)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
McKart v. United States
395 U.S. 185 (Supreme Court, 1969)
Zenith Radio Corp. v. Hazeltine Research, Inc.
401 U.S. 321 (Supreme Court, 1971)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Mitsui Foods, Inc. v. The United States
867 F.2d 1401 (Federal Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Taino Construction Group, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taino-construction-group-llc-v-united-states-uscfc-2025.