Allen Engineering Contractor, Inc. v. United States

115 Fed. Cl. 457, 2014 U.S. Claims LEXIS 118, 2014 WL 1277907
United States Court of Federal Claims·Decided March 27, 2014·No. 1:13-cv-00684·Published·Cited by 10 cases

Opinion

ORDER

Merow, Senior Judge

In its complaint, plaintiff alleges that the government, under several theories of liabili *460 ty, improperly terminated a contract between the parties involving construction work at Marine Corps Base, Camp Pendleton, California. See Doc. 1. The government has moved the court to dismiss the complaint in its entirety, arguing that plaintiff has failed to state any claim on which relief may be granted. See Doe. 7. The court finds as follows.

I. FACTS

The parties executed a contract for construction work at Camp Pendleton on July 29, 2012. See Doc. 1, ¶ 4. Plaintiff provided the required performance and payment bonds from Liberty Mutual Insurance Company (“Liberty”) to the Navy on August 20, 2012. See id,., ¶ 8. After initially rejecting the bonds, the Navy ultimately accepted them by letter dated September 6, 2012. See id.

On February 13, 2013, plaintiff submitted a second set of bonds, from Pacific Indemnity Company (“PIC”), and asked that if the PIC bonds were approved by the Navy, that they be substituted for the Liberty bonds. See id., ¶ 9. Plaintiff acquired the PIC bonds from Individual Surety Group, LLC (“ISG”), a company which represented itself as a broker for PIC, a subsidiary of Chubb Group. See id. Plaintiff alleges that upon receipt of the PIC bonds, the Navy began an investigation into whether the bonds were an acceptable substitute for the Liberty bonds. See id., ¶ 11.

The Navy verbally confirmed the authenticity of the bonds by calling a man named Ed Campbell, who allegedly worked for PIC. See id., ¶ 12. Plaintiff believes that the Navy actually spoke to Eric Campbell, a purported representative of ISG. See id., at n.3. Plaintiff further believes that the Navy did not call the telephone number for PIC listed in the Treasury Circular 570. See id., ¶ 13. The Navy followed this verbal confirmation with a letter, dated March 14, 2013, requesting written confirmation that the PIC bonds were authentic. See id, ¶ 12. Plaintiff alleges that the Navy did not contact the proper person for authentication and that the Navy did not actually send the letter requesting written confirmation to PIC, in violation of its duty to do so under certain Navy regulations, Federal Acquisition regulations, and other federal laws. See id.

The Navy approved the PIC bonds and the Liberty bonds were returned to Liberty on April 10, 2013. See id., ¶ 14. In the complaint, Plaintiff alleges that the Navy sent the Liberty bonds back to Liberty, but Exhibit F to the same complaint indicates otherwise. Liberty sent a letter to the Navy, dated May 2, 2013, stating: “Liberty’s original performance and payment bonds for this contract (024039638), for which the new Pacific Indemnity bonds were substituted, have been returned to Allen Engineering Contractors, Inc., who has in turn forwarded the original bonds to Liberty.” Id. at Exhibit F. On May 2, 2013, Liberty notified PIC that the PIC bonds had been substituted for the Liberty bonds on the project. See id., ¶ 15. On May 6, 2013, Walter Maxwell of Chubb Group, informed plaintiff that the PIC bonds were not issued by PIC, and therefore, were invalid. See id. The next day, May 7, 2013, PIC informed the Navy that the bonds were invalid. See id., ¶ 15. And on May 8, 2013, the Navy sent a letter to plaintiff stating that the PIC bonds were fraudulent, and requesting that plaintiff provide replacement bonds. See id., ¶ 16.

On May 20, 2013, the Navy suspended performance of the contract and requested that plaintiff provide valid replacement bonds. See id., ¶ 17. In response, plaintiff explained that it was having trouble securing replacement bonds, see id., Exhibit I at 2, and proposed alternatives to allow the project to move forward, see id., ¶ 18.

The Navy issued a cure notice on June 11, 2013, giving plaintiff 10 days to provide valid bonds. See id., ¶ 18 and Exhibit J. And on June 17, 2013, the Navy rejected plaintiffs alternative proposals, stating that the suggestions did not meet the FAR bonding requirements. -See id., ¶ 19 and Exhibit K.

The Navy then issued a show cause letter on June 24, 2013, giving plaintiff a final opportunity to provide additional information relating to its failure to provide replacement bonds. See id., ¶ 20 and Exhibit L. Plaintiff responded to the show cause letter on July 3, *461 2013, and again proposed alternatives to providing replacement bonds. See id., ¶ 20 and Exhibit M. On July 10, 2013, the Navy issued a notice of termination for default. See id., ¶ 20 and Exhibit N. Plaintiff alleges that at the time of termination, the project was 40% complete. See id., ¶ 20.

Plaintiff also attaches to its complaint a copy of a lawsuit filed by Chubb against Erie Campbell, ISG and others, relating to fraudulent bonds. See id., ¶22 and Exhibit O. Although plaintiff argues in its response to the government’s motion to dismiss that the Navy “was fully aware” of Eric Campbell’s fraudulent activity, and was therefore in a position to protect plaintiff, see Doc. 10 at 19 and 29, the complaint does not make any such allegation and the attached exhibits do not supply such facts.

Plaintiff alleges that throughout the bonding process, the Navy violated a variety of its own regulations contained in the Naval Facilities Engineering Command (“NAVFAC”) Contracting Manual (NAVFAC P-68) and several FAR provisions, including the following: (1) the contracting officer, Leilani J. Murray, was not a Level III contracting officer, as required by Navy regulations, and was therefore unauthorized to approve the new bonds, see Doc. 1, ¶ 22 (The paragraphs in the complaint are mis-numbered, and include two paragraphs 22. This reference is contained in the second such paragraph.); (2) the Navy failed to contact the correct representative from PIC to authenticate the bonds, see id.; (3) the Navy failed to notify the surety and principal of the effective date of the new bonds, see id., ¶ 23; (4) the Navy unreasonably refused to accept plaintiffs alternative proposals, see id., ¶¶ 24 and 27; (5) the Navy improperly terminated the contract because 48 C.F.R. § 52.249-10 does not permit termination for failure to provide replacement bonds, see id., ¶¶ 25, 26, and 28.

II. ANALYSIS

The government has moved the court to dismiss plaintiffs complaint under Court of Federal Claims Rule 12(b)(6), on the basis that it fails to state a claim upon which relief could be granted. See Doc. 7 at 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Allen Engineering Contractor, Inc. v. United States, 115 Fed. Cl. 457, 2014 U.S. Claims LEXIS 118, 2014 WL 1277907 (uscfc 2014).

115 Fed. Cl. 457 (Allen Engineering Contractor, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related