The Cessna Aircraft Company v. John H. Dalton, Secretary of Navy

126 F.3d 1442
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 27, 1998
Docket19-2175
StatusPublished
Cited by49 cases

This text of 126 F.3d 1442 (The Cessna Aircraft Company v. John H. Dalton, Secretary of Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Cessna Aircraft Company v. John H. Dalton, Secretary of Navy, 126 F.3d 1442 (Fed. Cir. 1998).

Opinion

SCHALL, Circuit Judge.

The Cessna Aircraft Company (“Cessna”) appeals from March 12, 1993 decision of *1444 Armed Services Board of Contract Appeals (“Board”) on cross-motions for partial summary judgment in Cessna Aircraft Co., ASBCA No. 43196, 93-3 BCA ¶ 25,912, 1993 WL 89795 (Mar. 12, 1993) (Cessna I). Cessna also appeals from Board’s September 21, 1995 decision following a hearing in same case, 96-1 BCA ¶ 27,966, 1995 WL 575173 (Sept. 21, 1995) (Cessna II). In those decisions, Board denied Cessna’s claims that Naval Air Systems Command of United States Navy (“Navy” or “NAVAIR”) failed to exercise, in a proper and timely manner, certain options under a contract between Cessna and Navy. We affirm.

BACKGROUND

I.

This appeal arises out of Contract No. N00019-83-C-0090, awarded to Cessna by Navy, under which Cessna was required to provide training, and related technical and maintenance support, for undergraduate naval flight officers at U.S. Naval Air Station in Pensacola, Florida. See Cessna I, 93-3 BCA at 128,876. 1

The contract called for Cessna to provide flight training services during five program years, commencing August 1, 1984, and ending September 30, 1988. Cessna I, 93-3 BCA at 128,876. Each program year ended on last day of government’s fiscal year, September 30. Id. In addition, contract contained an option provision allowing Navy to extend contract performance for three additional years. Id. Section H-6 of contract Schedule, entitled “Exercise of Option,” established conditions on Navy’s exercise of option. Section H-6 provided as follows:

Pursuant to “Option to Extend Services” clause, option for three years will be exercised, if at all, in writing by a unilateral modification to this contract issued by Contracting Officer, Naval Air Systems Command, not later than 1 October 1988.

Id. Each option year ran from October 1 to September 30; that is, first option year ran from October 1, 1988 to September 30, 1989, second option year ran from October 1, 1989 to September 30, 1990, and third option year ran from October 1, 1990 to September 30, 1991. Cessna I, 93-3 BCA at 128,876. The Navy had to notify contractor of availability of funds for second and third option years.

The timing of this notification was addressed by section H-8 of contract Schedule, entitled “Multiyear Procurement,” which stated that:

If three year option is exercised, date within which contracting officer ... will notify Contractor of availability of funds sufficient for performance of requirements for the
Second Option Year (Fiscal Year 1990) is 1 October 1989. Third Option Year (Fiscal Year 1991) is 1 October 1990.

Id. at 128,877. The contract further incorporated by reference, inter alia, two Defense Acquisition Regulation (“DAR”) provisions concerning multiyear aspects of contract. The first, named “Cancellation of Items” clause, addressed cancellation of contract based on a lack of availability of funds. This clause stated in pertinent part:

(b)As used herein, term “cancellation” means that Government is canceling, pursuant to this clause, its requirements for items as set forth in Schedule for all fiscal years (1 October — 30 September) subsequent to that in which notice of cancellation is provided. Such cancellation shall occur only if Contracting Officer (i) notifies Contractor that funds will not be available for contract performance for next succeeding fiscal year and any subsequent fiscal year; or (ii) fails to notify Contractor prior to beginning of next succeeding fiscal year that funds have been made available for performance in succeeding fiscal year.

DAR § 7-1903.33(d). 2 A related clause addressed contract execution once funds became available. It stated in pertinent part that:

Upon availability to Contracting Officer of funds for performance of requirements in *1445 next succeeding fiscal year, Contracting Officer shall notify Contractor in writing of amount of funds available for contract performance in next succeeding fiscal year and contract shall be modified accordingly.

DAR § 7-1903.33(c). 3

The contract was awarded on May 10, 1983. Sometime in either late March or early April of 1988, during final program year of original five-year term of contract, Cessna contacted contracting officer (“CO”) to inquire about whether Navy intended to exercise three year option. Cessna II, 96-1 BCA at 139,686. In response, by letter dated April 18, 1988, CO informed Cessna that Navy did intend to exercise option, stating that:

1. You are hereby notified of our intent to exercise option for three option years under Contract N00019-83-C-0090. Pursuant to Special Provision H-6, “Exercise of Option,” we will exercise option for three option years, if at all, not later than 1 October 1988.

Id.

On August 3, 1988, during negotiation meetings concerning unrelated claim for equitable adjustment made by Cessna, Cessna again raised issue of when Navy intended to exercise option. Id. At that time, Cessna expressed its view that option had to be exercised before October 1, 1988. Id. On September 26, 1988, in a telephone conversation between CO and a Cessna official, CO asked whether, because October 1, 1988 was a Saturday, it would be acceptable for option to be exercised on October 3, 1988. Cessna II, 96-1 BCA at 139,687. The Cessna official responded that October 3 would be a problem and that Cessna needed to receive exercised option on October 1. Id. CO informed Cessna official at that time that she would exercise option via facsimile on October 1. Id.

During period September 27-30, 1988, in midst of further negotiations regarding Cessna’s equitable adjustment claim, Cessna reiterated its view that Navy had to exercise option by September 30, 1988, while the Navy contended that it had until October 1. Id. As of September 30, 1988, the Department of Defense Appropriation Act, 1989, Pub.L. No. 100^163, 102 Stat. 2270 (1988), from which the contract at issue would be funded, had been passed by Congress but had not yet been signed by the President. Cessna II, 96-1 BCA at 139,687. On September 30, the CO informed Cessna that the option would be faxed on October 1. Id. at 139,688. Anticipating the passage of the appropriation act, on September 30, 1988, a NAYAIR budget analyst executed a “Financial Accounting Data Sheet” — used to make funds available for obligation — with the proviso “EXECUTION OF THIS DOCUMENT IS CONTINGENT ON CONGRESSIONAL PASSAGE OF THE FY89 APPROPRIATION ACT OR OTHER AUTHORITY.” Id. at 139,687-88.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Samho Enterprise
Armed Services Board of Contract Appeals, 2025
AICI-Archirodon JV
Armed Services Board of Contract Appeals, 2021
Parsons Evergreene, LLC
Armed Services Board of Contract Appeals, 2018
Parsons Government Services, Inc.
Armed Services Board of Contract Appeals, 2017
Saighi v. General Services Administration
645 F. App'x 993 (Federal Circuit, 2016)
Savantage Financial Services, Inc. v. United States
123 Fed. Cl. 7 (Federal Claims, 2015)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
Allen Engineering Contractor, Inc. v. United States
115 Fed. Cl. 457 (Federal Claims, 2014)
International Genomics Consortium v. United States
104 Fed. Cl. 669 (Federal Claims, 2012)
Todd Construction, L.P. v. United States
656 F.3d 1306 (Federal Circuit, 2011)
BLR Group of America, Inc. v. United States
94 Fed. Cl. 354 (Federal Claims, 2010)
K-LAK Corp. v. United States
93 Fed. Cl. 749 (Federal Claims, 2010)
Todd Construction, L.P. v. United States
94 Fed. Cl. 100 (Federal Claims, 2010)
Magnum Opus Technologies, Inc. v. United States
94 Fed. Cl. 512 (Federal Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
126 F.3d 1442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-cessna-aircraft-company-v-john-h-dalton-secretary-of-navy-cafc-1998.