Labarge Products, Inc. v. Togo D. West, Jr., Secretary of the Army

46 F.3d 1547, 40 Cont. Cas. Fed. 76,733, 1995 U.S. App. LEXIS 1484
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 26, 1995
Docket18-1880
StatusPublished
Cited by90 cases

This text of 46 F.3d 1547 (Labarge Products, Inc. v. Togo D. West, Jr., Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Labarge Products, Inc. v. Togo D. West, Jr., Secretary of the Army, 46 F.3d 1547, 40 Cont. Cas. Fed. 76,733, 1995 U.S. App. LEXIS 1484 (Fed. Cir. 1995).

Opinion

MICHEL, Circuit Judge.

LaBarge Products, Inc. (LaBarge) appeals from a November 23, 1992 decision of the Armed Services Board of Contract Appeals (Board). In its decision, the Board denied LaBarge’s appeal of the contracting officer’s final decision rejecting LaBarge’s claim for reformation of its contract with the United States Army to provide a quantity of pipe couplings.' LaBarge Prods., Inc., ASBCA No. 33593, 93-2 BCA ¶ 25,630 (Nov. 23,1991) (LaBarge II). Previously, the Board had denied the government’s motion to dismiss for the lack of jurisdiction. LaBarge Prods., Inc., ASBCA No. 33593, 91-3 BCA ¶ 24,110 (June 14, 1991) (LaBarge I). We hold that the Board did have jurisdiction under the Contract Disputes Act of 1978 (CDA or Act), 41 U.S.C. §§ 601-13 (1988), to hear La-Barge’s appeal. We affirm the Board’s decision on the merits as untainted by legal error and as supported by substantial evidence.

I. BACKGROUND

This case arises out of a procurement by the Army for aluminum pipe sections and couplings to connect the pipe sections. On July 9, 1984, the Army issued a Request for Proposals (RFP) for the pipe and couplings. Representatives of the Victaulic Company of *1549 America (Victaulic) worked closely with Army representatives throughout the development of specifications for the RFP. Before the RFP had issued, Lieutenant Colonel Andrew Foster, the project manager for the contract, attempted on several occasions to direct the proposed contract to Victaulic on a sole source basis. Shortly before the RFP was issued a decision was made that the coupling procurement should be competitive.

To ensure that the pipe and couplings would be compatible, the Army originally intended to award one contract to cover both. However, in response to a complaint from a potential contractor who wanted only to bid on the pipe, George O’Brien, who was overseeing the procurement, amended the RFP to allow bidders the option to bid on either the pipe or the couplings alone. On August 16, 1984, bids were received on both the pipe and coupling portions of the procurement. Reynolds Aluminum Co. (Reynolds) was the low bidder on the pipe portion. On August 31, the Army awarded Reynolds a contract on that portion of the procurement. La-Barge was the low bidder on the coupling portion of the procurement. It bid $38.50 per coupling for the base quantity and for the first option year and $40.80 per coupling for the second option year. Victaulic was the second lowest bidder. The Army did not at that time award a contract for the coupling portion of the procurement, however. In late August or early September, Captain Paul Daily of the Army Materiel Command communicated to Victaulic that LaBarge had submitted the lowest bid.

On September 12, 1984, O’Brien met with three representatives from LaBarge to explain that he intended to request best and final offers. O’Brien had become concerned over the amendment to the RFP which allowed for separate coupling and pipe contracts because the government would be responsible for any problems of incompatibility between the couplings and pipes. He was also concerned that pipes and couplings purchased in one year from one manufacturer should be interchangeable with those from a different manufacturer or a different year. O’Brien intended to request best and final offers which would include confirmation that the contractor would accept option provisions for the government to purchase production tooling and level three production drawings. O’Brien believed that government access to the production tooling and level three drawings could reduce variations between procurements and incompatibility problems. Charles LaBarge, then president of the company, saw this explanation as a device to avoid awarding the contract to LaBarge. He responded that the company would not lose the contract and would rebid in the “low 30’s.”

On September 12, the Army requested best and final offers for the coupling contract, including confirmation of the government’s option to purchase the production tooling and level three drawings. On September 13, 1984, before best and final offers were due, Michael Gorsky, Victaulie’s Contract Administrator, received a phone call in which an unknown person stated, “your competition on the coupling bid ... [is] going to bid in the low 30’s this time.”

Two bids were received in response to the request for best and final offers: a bid from LaBarge and a bid from Reynolds and Vic-taulic as joint venturers. LaBarge’s bid of $32.90 per coupling for the base year and each of the option years made it the low bidder over Reynolds/Vietaulic, which bid $32.50 per coupling for the base year but a higher price for the option years. LaBarge was not aware of the disclosures to Victaulic regarding its bids before submitting its best and final offer.

When it became clear, that LaBarge had submitted the low bid, Foster attempted to have the company declared technically deficient and unacceptable by requesting an additional evaluation of the company. This matter was not pursued, however, because O’Brien refused to allow such an evaluation.

The Army planned to announce LaBarge as the winner of the contract on November 15. Before the announcement could be made, however, Victaulic filed a pre-award bid protest with the General Accounting Office (GAO) alleging that the amendment to the RFP was unfair to Victaulic and that the government had violated its proprietary rights. -In a letter to the GAO in support of *1550 the protest, Victaulic revealed the disclosure of LaBarge’s bid by Daily and the September 13 telephone call to Gorsky.

By letter dated December 20, LaBarge joined the protest, claiming that preferential treatment had been given to Victaulic by Army personnel. In its letter, LaBarge stated that it had offered “a proper and bonafide proposal ... on August 16,1984” and that its offer of August 16 “should be accepted and [the] contract awarded properly-” La-Barge was referring to its original bid of $38.50 per coupling for the base quantity and for the first option year and $40.80 per coupling for the second option year.

On May 6, 1985, the GAO denied the Vic-taulic protest. Thereafter, on June 21, the Army awarded the coupling contract to La-Barge at its best and final offer price of $32.90 per coupling. Subsequently, LaBarge successfully completed contract performance.

Following contract completion, LaBarge submitted a claim to the contracting officer in which it sought to have the coupling contract reformed to the August 16, 1984 bid price. This would have resulted in a total contract price increase of about $800,000. LaBarge claimed that reformation of the contract to the higher price was necessary in order to compensate it for the improper acts of certain Army personnel involved in the procurement. LaBarge asserted that there had been a conspiracy to direct the contract to Victaulic even though LaBarge had submitted the low bid in response to the RFP. According to LaBarge, its August 16 bid had been disclosed to Victaulic and the best and final offer round was merely a “sham.” La-Barge claimed that, but for improper conduct, it would have been awarded the coupling contract at its higher, initial bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chugach Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
Mercom, Incorporated v. United States
131 Fed. Cl. 32 (Federal Claims, 2017)
Phoenix Management, Inc. v. United States
127 Fed. Cl. 358 (Federal Claims, 2016)
River Ridge Development Authority
Armed Services Board of Contract Appeals, 2016
Lee's Ford Dock, Inc.
Armed Services Board of Contract Appeals, 2016
Kenneth Earman v. United States
114 Fed. Cl. 81 (Federal Claims, 2013)
Glenn Defense Marine (Asia), PTE Ltd. v. States
105 Fed. Cl. 541 (Federal Claims, 2012)
Bona Fide Conglomerate, Inc. v. United States
96 Fed. Cl. 233 (Federal Claims, 2010)
Crassociates, Inc. v. United States
95 Fed. Cl. 357 (Federal Claims, 2010)
Mobile Medical International Corp. v. United States
95 Fed. Cl. 706 (Federal Claims, 2010)
Todd Construction, L.P. v. United States
94 Fed. Cl. 100 (Federal Claims, 2010)
Electronic Data System, LLC v. United States
93 Fed. Cl. 416 (Federal Claims, 2010)
Metropolitan Van & Storage, Inc. v. United States
92 Fed. Cl. 232 (Federal Claims, 2010)
Bannum, Inc. v. United States
91 Fed. Cl. 160 (Federal Claims, 2009)
NEQ, LLC v. United States
88 Fed. Cl. 38 (Federal Claims, 2009)
Academy Facilities Management v. United States
87 Fed. Cl. 441 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
46 F.3d 1547, 40 Cont. Cas. Fed. 76,733, 1995 U.S. App. LEXIS 1484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/labarge-products-inc-v-togo-d-west-jr-secretary-of-the-army-cafc-1995.