Siemens Government Technologies, Inc. v. Secretary of the Navy

Court of Appeals for the Federal Circuit·Decided May 8, 2024·No. 22-2240·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

SIEMENS GOVERNMENT TECHNOLOGIES, INC., Appellant

v.

SECRETARY OF THE NAVY, Appellee

2022-2240

Appeal from the Armed Services Board of Contract Appeals in Nos. 62601, 62602, Administrative Judge David D’Alessandris, Administrative Judge Owen C. Wilson, Administrative Judge Richard Shackleford.

Decided: May 8, 2024

MICHAEL BHARGAVA, Nichols Liu LLP, Washington, DC, argued for appellant. Also represented by ROBERT NICHOLS, SAMUEL VAN KOPP.

ELIZABETH ANNE SPECK, Commercial Litigation Branch, Civil Division, United States Department of Justice , Washington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, WILLIAM JAMES GRIMALDI, PATRICIA M. MCCARTHY; ROBYN L. HAMADY, Office of the 2 SIEMENS GOVERNMENT TECHNOLOGIES, INC. v.

SECRETARY OF THE NAVY

General Counsel, United States Department of the Navy, Washington, DC.

Before REYNA, MAYER, and CUNNINGHAM, Circuit Judges. PER CURIAM.

Siemens Government Technologies, Inc. (“Siemens”)

appeals a decision of the Armed Services Board of Contract Appeals (“board”) rejecting its claim seeking recovery of the development costs it incurred investigating potential energy conservation measures at military installations in Djibouti and Greece. For the reasons discussed below, we affirm.

I. BACKGROUND The relevant facts are set out in detail in the board’s decision, see J.A. 2–11, and need only be briefly summarized here. Pursuant to 42 U.S.C. § 8287(a)(1), a federal agency can “enter into contracts . . . solely for the purpose of achieving energy savings and benefits ancillary to that purpose.” Under such contracts, a contractor incurs the upfront cost of installing energy savings measures and, in exchange, is entitled to “a share of any energy savings directly resulting from implementation of such measures during the term of the contract.” Id.

In 2007, the Department of Energy (“DOE”) entered into Contract DE-AM36-09GO29041 (the “DOE Master Contract”) with Siemens’ predecessor, Siemens Government Services, Inc. J.A. 309–10, 613. This contract provided the Navy with the authority to issue task orders to Siemens for energy savings performance contract (“ESPC”) work. J.A. 630, 654. It specified that an agency task order was “[t]he obligating document that provides the details and requirements for the order of an [ESPC] project, placed against an established master indefinite delivery/indefinite quantity contract.” J.A. 706.

SIEMENS GOVERNMENT TECHNOLOGIES, INC. v. 3 SECRETARY OF THE NAVY

Section H of the DOE Master Contract outlines the steps required for issuance of a task order: (1) the agency’s contracting officer issues a notice of opportunity; (2) the contractor submits an expression of interest; (3) the contractor submits a preliminary assessment; (4) the contracting officer issues a notice of intent to award (“NIA”); (5) the contracting officer issues a request for proposal; (6) the contractor submits an investment grade audit (“IGA”); (7) the contractor submits a final proposal based on the IGA; and (8) a task order is awarded. See J.A. 657–72; see also J.A. 2–3. The DOE Master Contract makes clear that an “agency will not be responsible for any costs incurred [by a contractor], such as [p]roposal preparation costs or the costs incurred in conducting the IGA, unless a [task order] is awarded or authorized by the agency [contracting officer ].” J.A. 666.

In 2014, the Navy issued a request for preliminary assessment which identified potential energy conservation measures at the following installations: (1) Camp Lemonnier in Djibouti (“CLDJ”); (2) the Naval Support Activity in Souda Bay, Greece; (3) the Naval Air Station in Sigonella, Italy; (4) the Naval Station in Rota, Spain; (5) the Naval Support Activity in Naples, Italy; and (6) the Naval Support Activity in Bahrain. See J.A. 789–92. Siemens thereafter submitted preliminary assessments for work at these sites. See J.A. 43, 1861–67, 1962–67.

On December 1, 2015, the Navy issued an NIA stating that it intended to award up to five proposed task orders pursuant to the DOE Master Contract. J.A. 803. In this notice, the Navy informed Siemens that it was required to perform IGAs of potential energy savings measures at the “applicable project site facilities” and provide “five Final Proposals summarizing the survey results.” J.A. 803. The Navy further stated that Siemens was required to “verify the accuracy of the estimated annual cost savings [it] originally proposed for these projects.” J.A. 803. Additionally, the Navy cautioned that the NIA did “not commit the 4 SIEMENS GOVERNMENT TECHNOLOGIES, INC. v.

SECRETARY OF THE NAVY

Government to award a [t]ask [o]rder, or to pay for any of the costs incurred in making the necessary studies or designs for the preparation thereof, or to contract for said services or designs.” J.A. 803.

The Navy issued a task order request for proposal for energy saving measures at Souda Bay on December 2, 2015, J.A. 804–06, and a task order request for proposal for CLDJ on March 8, 2016, J.A. 884–86. In June 2016, Siemens informed the Navy that it had concluded that energy conservation measures at CLDJ and Souda Bay were no longer viable. J.A. 976, 982.

On September 26, 2018, the Navy awarded Task Order N39430-18-F-9924 (the “Awarded Task Order”) to Siemens . J.A. 1005–266. This task order authorized energy conservation measures at Navy installations in Naples, Rota, and Sigonella, see J.A. 1007–09, but did not authorize any such measures at CLDJ or Souda Bay.

Siemens subsequently submitted certified claims to the Navy seeking reimbursement of the approximately $5.2 million in costs it allegedly incurred evaluating potential energy cost savings measures at CLDJ and Souda Bay. J.A. 1824–35. After the Navy’s contracting officer issued final decisions denying both claims, see J.A. 1836–45, Siemens appealed to the board, see J.A. 38–55.

Before the board, Siemens asserted that the Navy violated the covenant of good faith and fair dealing and the superior knowledge doctrine by asking it to incur proposal development costs at CLDJ and Souda Bay even though the Navy knew that energy conservation measures at those locations were not viable. J.A. 38, 49–54. On May 24, 2022, the board issued a decision granting the Navy’s motion for summary judgment. See J.A. 13. The board rejected Siemens ’ claim for breach of the duty of good faith and fair dealing, explaining that this duty “applies to government conduct during the performance of the contract, and does not apply to government actions during the formation of

SIEMENS GOVERNMENT TECHNOLOGIES, INC. v. 5 SECRETARY OF THE NAVY

the contract.” J.A. 14. The board likewise rejected Siemens ’ superior knowledge claim, stating that the doctrine of superior knowledge applies only during contract performance and the parties’ contract was limited to work at Naples , Rota, and Sigonella. J.A. 17–18. Additionally, the board held that it lacked jurisdiction over Siemens’ claim that it was treated unfairly during the bidding process for work at CLDJ and Souda Bay because “an implied contract to treat a bidder honestly is not a contract for the procurement of goods, and thus does not fall within the” board’s Contract Disputes Act (“CDA”) jurisdiction. J.A. 15.

Siemens then filed a timely appeal with this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

II. DISCUSSION A. Standard of Review This court reviews de novo the board’s interpretation of a government contract. See Forman v. United States, 329 F.3d 837, 841 (Fed. Cir. 2003). The board’s grant of summary judgment on a question of law is likewise subject to de novo review. Id.; see also Elec. Boat Corp. v. Sec’y of Navy, 958 F.3d 1372, 1375 (Fed. Cir. 2020).

Free access — add to your briefcase to read the full text and ask questions with AI

Siemens Government Technologies, Inc. v. Secretary of the Navy, (Fed. Cir. 2024).

Siemens Government Technologies, Inc. v. Secretary of the Navy (Siemens Government Technologies, Inc. v. Secretary of the Navy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related