Electric Boat Corporation v. Secretary of the Navy

958 F.3d 1372
CourtCourt of Appeals for the Federal Circuit
DecidedMay 19, 2020
Docket19-1621
StatusPublished
Cited by23 cases

This text of 958 F.3d 1372 (Electric Boat Corporation v. Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Boat Corporation v. Secretary of the Navy, 958 F.3d 1372 (Fed. Cir. 2020).

Opinion

Case: 19-1621 Document: 42 Page: 1 Filed: 05/19/2020

United States Court of Appeals for the Federal Circuit ______________________

ELECTRIC BOAT CORPORATION, Appellant

v.

SECRETARY OF THE NAVY, Appellee ______________________

2019-1621 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in No. 58672, Administrative Judge David D’Alessan- dris, Administrative Judge J. Reid Prouty, Administrative Judge Richard Shackleford. ______________________

Decided: May 19, 2020 ______________________

IAN GERSHENGORN, Jenner & Block LLP, Washington, DC, argued for appellant. Also represented by MATTHEW S. HELLMAN, D. JOE SMITH.

WILLIAM JAMES GRIMALDI, Commercial Litigation Branch, Civil Division, United States Department of Jus- tice, Washington, DC, argued for appellee. Also repre- sented by JOSEPH H. HUNT, MARTIN F. HOCKEY, JR., ROBERT EDWARD KIRSCHMAN, JR.; ALANA M. SITTERLY, RUSSELL SHULTIS, Naval Litigation Office, United States Department of the Navy, Washington, DC. Case: 19-1621 Document: 42 Page: 2 Filed: 05/19/2020

2 ELEC. BOAT CORP. v. SEC’Y OF THE NAVY

______________________

Before LOURIE, MOORE, and CHEN, Circuit Judges. MOORE, Circuit Judge. Electric Boat Corporation appeals from the Armed Ser- vices Board of Contract Appeals’ grant of partial summary judgment to the United States Department of the Navy, holding that Electric Boat’s Contract Dispute Act (CDA) claim is barred by the statute of limitations. Because the Board correctly held that Electric Boat’s claim is barred by the statute of limitations, we affirm. BACKGROUND On August 14, 2003, Electric Boat and the Navy en- tered into a contract (the Contract) for the construction of up to six separate Virginia-class nuclear-powered subma- rines (SSNs), SSN 778 through SSN 783. 1 The Contract established a target price for each submarine, comprising the sum of the target cost and the target profit. See J.A. 84 (SSN 783). Electric Boat was entitled to periodic progress payments proportional to Electric Boat’s overall construc- tion progress. J.A. 271–79 (Clause H-29). The Navy was required to fully compensate Electric Boat under the Con- tract until Electric Boat’s invoiced costs exceeded

1 The Contract between Electric Boat and the Navy funded full construction of only the first submarine, SSN 778. Pursuant to Clause H-17 of the Contract, the remain- ing five submarines were funded on an installment basis and the parties’ obligations under the Contract were en- tirely contingent on the future availability of funds. J.A. 238–39. The Navy modified the Contract in January 2004, transitioning the contract to a multi-year procurement con- tract for the remaining five submarines. J.A. 396. Clause H-20 of the modified contract maintained the installment funding and contingency provisions of Clause H-17. Case: 19-1621 Document: 42 Page: 3 Filed: 05/19/2020

ELEC. BOAT CORP. v. SEC’Y OF THE NAVY 3

construction progress at the target price, less certain ad- justments. Id. The Contract incorporates by reference the standard Changes Clause under 48 C.F.R. §§ 52.243-1, -2. J.A. 335, 344. The Changes Clause requires that the Navy’s Con- tracting Officer “make an equitable adjustment in the con- tract price, the delivery schedule, or both” in the event that the Contracting Officer makes a change to the contract that “causes an increase or decrease in the cost of, or the time required for, performance.” 48 C.F.R. § 52.243-1(b). The Contract also includes a “Change-of-Law Clause,” which provides for a price adjustment in the event that compli- ance with a new federal law, or a change to existing federal laws or regulations, directly increases or decreases Electric Boat’s costs of performance. J.A. 279–81 (Clause H-30). The Change-of-Law Clause specifies that no cost adjust- ments shall be made thereunder for the first two years af- ter the effective date of the Contract (i.e., until August 15, 2005). J.A. 280. After two years, adjustments shall only be made if a qualifying change of law increases Electric Boat’s costs of performance “in excess of $125,000 per ship.” J.A. 281 (Clause H-30(c)). The Change-of-Law Clause requires that Electric Boat promptly notify the Navy’s Contracting Officer of a quali- fying enactment or change in federal law. J.A. 281 (Clause H-30(d)). Section (e) of the Change-of-Law Clause further provides that requests for price adjustments thereunder be made in accordance with the procedures set forth in Clause H-9, entitled “Documentations of Requests for Equitable Adjustment.” J.A. 281 (Clause H-30(e)). Clause H-9 sets forth uniform procedures for submitting requests for equi- table adjustments under all articles of the Contract, includ- ing the standard Changes Clause. J.A. 228. On September 15, 2004, OSHA issued a new federal regulation entitled Fire Protection in Shipyard Employ- ment (the OSHA Regulation). See 69 Fed. Reg. 55,668 Case: 19-1621 Document: 42 Page: 4 Filed: 05/19/2020

4 ELEC. BOAT CORP. v. SEC’Y OF THE NAVY

(Sept. 15, 2004) (codified at 29 C.F.R. § 1915.501 et seq.). The OSHA Regulation, which became effective on Decem- ber 14, 2004, required companies to post a fire watch if cer- tain conditions are present during “hot work” in shipyard employment. See id.; 29 C.F.R. § 1915.504(b). On Febru- ary 24, 2005, Electric Boat submitted a Notification of Change to the Navy. J.A. 453–57. The Notification stated that “Electric Boat anticipates that compliance with [the OSHA Regulation] will result in an increase in the cost of performance [under the Contract] in excess of $125,000 per ship.” J.A. 453. On June 27, 2007, Electric Boat submitted a cost pro- posal to the Navy, seeking price adjustments across all six submarines. J.A. 459–69. In October 2008, the Navy coun- tered, challenging Electric Boat’s calculations of certain costs. J.A. 554–57. In April 2009, Electric Boat submitted a revised cost proposal to the Navy. J.A. 559–67. On May 2, 2011, the Contracting Officer of the Navy issued a mem- orandum decision formally denying Electric Boat “entitle- ment to an adjustment of the contract price.” J.A. 705–10. The memorandum stated that Electric Boat’s cost pro- posals had “inadequate support” and that there were “dis- crepancies between [Electric Boat’s] proposal and the Government’s review of various documents related to the OSHA change.” J.A. 708. The memorandum further stated that if Electric Boat decided to further pursue an adjust- ment related to the OSHA Regulation, “it should seek ad- justment pursuant to [regulations governing] ‘Requests for Equitable Adjustment’” by June 3, 2011. Id. On December 19, 2012, Electric Boat filed a certified claim with the Navy, seeking a price adjustment for in- creased costs it allegedly incurred in complying with the OSHA Regulation. J.A. 711–12. On February 27, 2013, the government issued a Contracting Officer’s Final Decision denying Electric Boat’s claim. J.A. 713–30. Electric Boat appealed the Contracting Officer’s Final Decision to the Board. The Navy moved for summary judgment that Case: 19-1621 Document: 42 Page: 5 Filed: 05/19/2020

ELEC. BOAT CORP. v. SEC’Y OF THE NAVY 5

Electric Boat’s claim was barred by the statute of limita- tions. Electric Boat filed a cross-motion for summary judg- ment that its claim was timely filed. On December 10, 2018, the Board granted-in-part the Navy’s motion for summary judgment and dismissed Elec- tric Boat’s complaint. 2 J.A. 17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
Kandahar Mahali Transit & Forwarding LTD.
Armed Services Board of Contract Appeals, 2024
Restoration Specialists, LLC
Armed Services Board of Contract Appeals, 2023
Patricia I. Romero, Inc. d/b/a Pacific West Builders
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Afghan Premier Logistics
Armed Services Board of Contract Appeals, 2022
Globe Trailer Manufacturing, Inc.
Armed Services Board of Contract Appeals, 2021
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)
Thomas J. Davis, Inc.
Armed Services Board of Contract Appeals, 2021

Cite This Page — Counsel Stack

Bluebook (online)
958 F.3d 1372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-boat-corporation-v-secretary-of-the-navy-cafc-2020.