Electric Boat Corporation v. Secretary of the Navy

958 F.3d 1372
Court of Appeals for the Federal Circuit·Decided May 19, 2020·No. 19-1621·Published·Cited by 23 cases

Opinion

United States Court of Appeals for the Federal Circuit

ELECTRIC BOAT CORPORATION, Appellant

v.

SECRETARY OF THE NAVY, Appellee

2019-1621

Appeal from the Armed Services Board of Contract Appeals in No. 58672, Administrative Judge David D’Alessandris , Administrative Judge J. Reid Prouty, Administrative Judge Richard Shackleford.

Decided: May 19, 2020

IAN GERSHENGORN, Jenner & Block LLP, Washington, DC, argued for appellant. Also represented by MATTHEW S. HELLMAN, D. JOE SMITH.

WILLIAM JAMES GRIMALDI, Commercial Litigation Branch, Civil Division, United States Department of Justice , Washington, DC, argued for appellee. Also represented by JOSEPH H. HUNT, MARTIN F. HOCKEY, JR., ROBERT EDWARD KIRSCHMAN, JR.; ALANA M. SITTERLY, RUSSELL SHULTIS, Naval Litigation Office, United States Department of the Navy, Washington, DC.

2 ELEC. BOAT CORP. v. SEC’Y OF THE NAVY

Before LOURIE, MOORE, and CHEN, Circuit Judges.

MOORE, Circuit Judge.

Electric Boat Corporation appeals from the Armed Services Board of Contract Appeals’ grant of partial summary judgment to the United States Department of the Navy, holding that Electric Boat’s Contract Dispute Act (CDA) claim is barred by the statute of limitations. Because the Board correctly held that Electric Boat’s claim is barred by the statute of limitations, we affirm.

BACKGROUND On August 14, 2003, Electric Boat and the Navy entered into a contract (the Contract) for the construction of up to six separate Virginia-class nuclear-powered submarines (SSNs), SSN 778 through SSN 783. 1 The Contract established a target price for each submarine, comprising the sum of the target cost and the target profit. See J.A. 84 (SSN 783). Electric Boat was entitled to periodic progress payments proportional to Electric Boat’s overall construction progress. J.A. 271–79 (Clause H-29). The Navy was required to fully compensate Electric Boat under the Contract until Electric Boat’s invoiced costs exceeded

1 The Contract between Electric Boat and the Navy funded full construction of only the first submarine, SSN 778. Pursuant to Clause H-17 of the Contract, the remaining five submarines were funded on an installment basis and the parties’ obligations under the Contract were entirely contingent on the future availability of funds. J.A. 238–39. The Navy modified the Contract in January 2004, transitioning the contract to a multi-year procurement contract for the remaining five submarines. J.A. 396. Clause H-20 of the modified contract maintained the installment funding and contingency provisions of Clause H-17.

ELEC. BOAT CORP. v. SEC’Y OF THE NAVY 3

construction progress at the target price, less certain adjustments . Id.

The Contract incorporates by reference the standard Changes Clause under 48 C.F.R. §§ 52.243-1, -2. J.A. 335, 344. The Changes Clause requires that the Navy’s Contracting Officer “make an equitable adjustment in the contract price, the delivery schedule, or both” in the event that the Contracting Officer makes a change to the contract that “causes an increase or decrease in the cost of, or the time required for, performance.” 48 C.F.R. § 52.243-1(b). The Contract also includes a “Change-of-Law Clause,” which provides for a price adjustment in the event that compliance with a new federal law, or a change to existing federal laws or regulations, directly increases or decreases Electric Boat’s costs of performance. J.A. 279–81 (Clause H-30). The Change-of-Law Clause specifies that no cost adjustments shall be made thereunder for the first two years after the effective date of the Contract (i.e., until August 15, 2005). J.A. 280. After two years, adjustments shall only be made if a qualifying change of law increases Electric Boat’s costs of performance “in excess of $125,000 per ship.” J.A. 281 (Clause H-30(c)).

The Change-of-Law Clause requires that Electric Boat promptly notify the Navy’s Contracting Officer of a qualifying enactment or change in federal law. J.A. 281 (Clause H-30(d)). Section (e) of the Change-of-Law Clause further provides that requests for price adjustments thereunder be made in accordance with the procedures set forth in Clause H-9, entitled “Documentations of Requests for Equitable Adjustment.” J.A. 281 (Clause H-30(e)). Clause H-9 sets forth uniform procedures for submitting requests for equitable adjustments under all articles of the Contract, including the standard Changes Clause. J.A. 228.

On September 15, 2004, OSHA issued a new federal regulation entitled Fire Protection in Shipyard Employment (the OSHA Regulation). See 69 Fed. Reg. 55,668 4 ELEC. BOAT CORP. v. SEC’Y OF THE NAVY

(Sept. 15, 2004) (codified at 29 C.F.R. § 1915.501 et seq.). The OSHA Regulation, which became effective on December 14, 2004, required companies to post a fire watch if certain conditions are present during “hot work” in shipyard employment. See id.; 29 C.F.R. § 1915.504(b). On February 24, 2005, Electric Boat submitted a Notification of Change to the Navy. J.A. 453–57. The Notification stated that “Electric Boat anticipates that compliance with [the OSHA Regulation] will result in an increase in the cost of performance [under the Contract] in excess of $125,000 per ship.” J.A. 453.

On June 27, 2007, Electric Boat submitted a cost proposal to the Navy, seeking price adjustments across all six submarines. J.A. 459–69. In October 2008, the Navy countered , challenging Electric Boat’s calculations of certain costs. J.A. 554–57. In April 2009, Electric Boat submitted a revised cost proposal to the Navy. J.A. 559–67. On May 2, 2011, the Contracting Officer of the Navy issued a memorandum decision formally denying Electric Boat “entitlement to an adjustment of the contract price.” J.A. 705–10. The memorandum stated that Electric Boat’s cost proposals had “inadequate support” and that there were “discrepancies between [Electric Boat’s] proposal and the Government’s review of various documents related to the OSHA change.” J.A. 708. The memorandum further stated that if Electric Boat decided to further pursue an adjustment related to the OSHA Regulation, “it should seek adjustment pursuant to [regulations governing] ‘Requests for Equitable Adjustment’” by June 3, 2011. Id.

On December 19, 2012, Electric Boat filed a certified claim with the Navy, seeking a price adjustment for increased costs it allegedly incurred in complying with the OSHA Regulation. J.A. 711–12. On February 27, 2013, the government issued a Contracting Officer’s Final Decision denying Electric Boat’s claim. J.A. 713–30. Electric Boat appealed the Contracting Officer’s Final Decision to the Board. The Navy moved for summary judgment that

ELEC. BOAT CORP. v. SEC’Y OF THE NAVY 5

Electric Boat’s claim was barred by the statute of limitations . Electric Boat filed a cross-motion for summary judgment that its claim was timely filed.

On December 10, 2018, the Board granted-in-part the Navy’s motion for summary judgment and dismissed Electric Boat’s complaint. 2 J.A. 17. The Board determined that Electric Boat knew of its claim no later than February 2005, when Electric Boat submitted its Notification of Change to the Navy. J.A. 10. The Board further held that Electric Boat “suffered some injury not later than August 15, 2005, the date two years after the effective date of the [C]ontract when [the Change-of-Law Clause] would first provide the right to a price adjustment.” J.A. 10. Because Electric Boat’s Claim was not filed until December 2012, more than six years after the August 2005 accrual date, the Board held that Electric Boat’s claim was untimely. J.A. 17. Electric Boat appeals. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

Free access — add to your briefcase to read the full text and ask questions with AI

Electric Boat Corporation v. Secretary of the Navy, 958 F.3d 1372 (Fed. Cir. 2020).

958 F.3d 1372 (Electric Boat Corporation v. Secretary of the Navy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
Kandahar Mahali Transit & Forwarding LTD.
Armed Services Board of Contract Appeals, 2024
Restoration Specialists, LLC
Armed Services Board of Contract Appeals, 2023
Patricia I. Romero, Inc. d/b/a Pacific West Builders
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Afghan Premier Logistics
Armed Services Board of Contract Appeals, 2022
Globe Trailer Manufacturing, Inc.
Armed Services Board of Contract Appeals, 2021
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)
Thomas J. Davis, Inc.
Armed Services Board of Contract Appeals, 2021