Korte Construction Co. v. Secretary of the Army

Court of Appeals for the Federal Circuit·Decided April 9, 2026·No. 24-2232·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

KORTE CONSTRUCTION CO.,

Appellant

v.

SECRETARY OF THE ARMY,

Appellee

2024-2232

Appeal from the Armed Services Board of Contract Appeals in No. 63148, Administrative Judge Michael N. O’Connell, Administrative Judge Owen C. Wilson.

Decided: April 9, 2026

MICHAEL WILSON, UB Greensfelder, LLP, Saint Louis, MO, argued for appellant.

PATRICIA M. MCCARTHY, Commercial Litigation Branch, Civil Division, United States Department of Justice , Washington, DC, argued for appellee. Also represented by CORINNE ANNE NIOSI, BRETT SHUMATE.

2 KORTE CONSTRUCTION CO. v. SECRETARY OF THE ARMY

Before HUGHES, LINN, and STOLL, Circuit Judges.

LINN, Circuit Judge.

Korte Construction (“Korte”) appeals the decision of the Armed Services Board of Contract Appeals (“Board”), granting summary judgment in favor of the Secretary of the Army (“Army”) and awarding a refund to the Army for the cost of chilled water improvements at Tinker Air Force Base that the Board held were required by the contract (“RFP”) as awarded but were later unilaterally deleted by the Army. In re Korte Constr. Co., ASBCA No. 63148, 2023 WL 7476103 (Oct. 26, 2023), on reconsideration, In re Korte Constr. Co., 2024 WL 2698015 (May 6, 2024). For the following reasons, we affirm.

BACKGROUND

Beginning with Phase 2 of the RFP and in all subsequent versions, the RFP included the following provision:

Extend the base wide chilled water, hot water, and compressed air piping to the slab edge of the hangar. Provide connection location for future projects.

J.App’x 1202 (emphasis added). As stipulated by the parties , the government added the requirement to “[p]rovide connection location for future projects” as an amendment. J.App’x 183 (¶ 26). There is no dispute that there was no pre-existing base wide chilled water system to extend at Tinker Air Force Base. J.App’x 195 (¶ 70).

Korte submitted its final Phase 2 proposal on May 31, 2019, which included a confirmation that it was “not proposing any deviations, exceptions or assumptions to the terms or conditions of the Solicitation.” J.App’x 7423; J.App’x 185 (¶ 33). Korte’s submission included schematic drawings showing the “CW” lines as in the Solicitation. J.App’x 7244, J.App’x 7251. In September 2019, Korte was

KORTE CONSTRUCTION CO. v. SECRETARY OF THE ARMY 3

awarded the contract for a total of approximately $72.8 million . J. App’x 185 (¶ 37).

Between September 2020 and February 2021, the Army sought revisions to the contract, initially to install “new utilities valve vault for 14[-inch] chilled water supply and 14[-inch] chilled water return, and changing from three contractually required chilled water lines to two 14[-inch] underground chilled water mains,” J.App’x 7962, a modification from its reading of the RFP requiring three 12-inch chilled water lines and a valve vault, and later sought to delete the chilled water lines and valve vault entirely . The Army sought a credit for the value of the work Korte would no longer need to perform. Korte refused to award a credit, asserting that the RFP as awarded did not require such improvements. In April 2021, the Army issued a unilateral modification that deleted the chilled water lines and valve vault and credited the Army with $493,639.43. J.App’x 194; J.App’x 7265. Korte thereafter submitted a claim to the contracting officer seeking to rescind the modification. The contracting officer denied Korte’s claim. He held that the RFP required Korte to build the chilled water improvements, and that if Korte believed that the chilled water improvements were mistakenly included, it had a duty to point out the ambiguity before bidding. J.App’x 7966.

Korte appealed. The Board affirmed the contracting officer’s decision at summary judgment on two grounds. First, that it was not reasonable for Korte to simply ignore the requirements in the specification that it knew were ambiguous . J.App’x 25–30. Second, because Korte knew about the ambiguity in the contract prior to bidding, it had a duty to inquire, which it did not satisfy, and thus bore the risk of the Army adopting a contrary interpretation. J.App’x 30–32. On reconsideration, the Board maintained its disposition awarding a refund to the Army.

Korte appeals.

4 KORTE CONSTRUCTION CO. v. SECRETARY OF THE ARMY

DISCUSSION

I

Despite the somewhat unusual posture of this case, our decision turns entirely on a contract interpretation question : whether the RFP required Korte to install the chilled water improvements, a legal question we review de novo. Hahnenkamm, LLC v. United States, 104 F.4th 1333, 1341 (Fed. Cir. 2024); K-Con, Inc. v. Sec’y of Army, 908 F.3d 719, 722–23 (Fed. Cir. 2018) (stating that whether an RFP is ambiguous and whether the ambiguity is latent or patent are reviewed de novo). We give the Board’s contract interpretation “careful consideration in view of the Board’s considerable experience in construing government contracts.” Elec. Boat Corp. v. Sec’y of Navy, 958 F.3d 1372, 1375 (Fed. Cir. 2020).

Because the Army is seeking a refund for a revision after the contract award, it carries the burden to show that the chilled water improvements were required by the RFP. Nager Elec. Co. v. United States, 442 F.2d 936, 946 (Ct. Cl. 1971). We interpret a contract from the perspective of “a reasonable and prudent contractor.” Int’l Tech. Corp. v. Winter, 523 F.3d 1341, 1349 (Fed. Cir. 2008) (quoting H.B. Mac, Inc. v. United States, 153 F.3d 1338, 1345 (Fed. Cir. 1998)).

II

Korte argues that it was impossible to extend a base wide chilled water system that did not exist, and therefore any reading requiring satisfaction of that term is unreasonable . See Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1294 (Fed. Cir. 2002) (explaining that impossibility of performance may excuse contractor performance). Korte argues that the lack of essential information about the specifications for the pipes and vault confirms that building these improvements was not part of the RFP. Korte also argues that the schematic drawings CU101 and

KORTE CONSTRUCTION CO. v. SECRETARY OF THE ARMY 5

CG101, which show three small lines labeled “CW” running parallel to the hangar and terminating in unlabeled boxes at either end, cannot require the installation of three 12- inch chilled water lines and a valve vault because the drawings do not show keynotes associated with these components , do not define “CW” in the referenced legends at C- 0001 and C-0002 or on the schematic drawings, and show the lines running parallel to the hangar rather than “to the slab edge of the hangar” as required by the written specification . Korte further contends the impossible-to-perform text in the specification takes precedence over the drawings under FAR § 52.236-21(a) (“In case of difference between drawings and specifications, the specifications shall govern.”).

The Army responds that the only reasonable interpretation of the RFP, when reading the drawings and specification together, requires the installation of chilled water improvements, per the written specification, in the locations shown by the CW lines and valve vault box in the schematic drawings. A reasonably prudent contractor, the Army argues, would have recognized that the CW lines represented chilled water pipes because the schematic drawings refer the contractor to the legends on C-001 and C-002 for definitions of items on the drawings. For example, C- 001 defines “—12” CWS1—” and “—12” CWR1—” as “CHILLED WATER SUPPLY” and “CHILLED WATER RETURN,” respectively, and C-002 identifies item “—w— w—w—w—” as “water line.”

Free access — add to your briefcase to read the full text and ask questions with AI

Korte Construction Co. v. Secretary of the Army, (Fed. Cir. 2026).

Korte Construction Co. v. Secretary of the Army (Korte Construction Co. v. Secretary of the Army) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
Hahnenkamm, LLC v. United States
104 F.4th 1333 (Federal Circuit, 2024)