K-Con, Inc. v. Secretary of the Army

908 F.3d 719
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 5, 2018
Docket2017-2254
StatusPublished
Cited by17 cases

This text of 908 F.3d 719 (K-Con, Inc. v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K-Con, Inc. v. Secretary of the Army, 908 F.3d 719 (Fed. Cir. 2018).

Opinion

Stoll, Circuit Judge.

K-Con, Inc. and the Army entered into two contracts for pre-engineered metal buildings. The Armed Services Board of Contract Appeals ("Board") held that bonding requirements were included in the contracts by operation of law at the time they were awarded, pursuant to the Christian doctrine. 1 See G. L. Christian & Assocs. v. United States ( Christian I ), 312 F.2d 418 (Ct. Cl. 1963). K-Con appeals. We conclude that the two contracts are construction contracts and that, under the Christian doctrine, the standard bond requirements in construction contracts were incorporated into K-Con's contracts by operation of law. Accordingly, we affirm.

I

K-Con claims that, after the Army awarded two contracts for pre-engineered metal buildings, the Army delayed issuance of a notice to proceed for two years, resulting in $116,336.56 in increases in costs and labor. According to K-Con, this delay was due solely to the government's decision to add to each contract the performance and payment bonds set forth in Federal Acquisition Regulation ("FAR") 52.228-15, Performance and Payment Bonds-Construction.

In September 2013, the government awarded to K-Con task orders for the design and construction of a laundry facility and the construction of a communications equipment shelter at Camp Edwards, Massachusetts. The contracting officer issued both solicitations using the General Services Administration eBuy system using Standard Form 1449, Solicitation/Contract/Order for Commercial Items. Neither solicitation included an express requirement *722 that K-Con provide performance and payment bonds. Nor did the solicitations include FAR clause 52.228-15, Performance and Payment Bonds-Construction, the standard language for performance and payment bonds included in government construction contracts, mirroring the requirements in FAR 28.102-2(b).

In October 2013, the Army instructed K-Con to provide performance and payment bonds in accordance with FAR 28.102-2(b) before the Army could issue its notice to proceed with the contracts. Nearly two years later, in September 2015, K-Con provided the required bonds and the parties modified each contract to compensate K-Con for the cost of the bonding fees. In January 2016, K-Con submitted a request for equitable adjustment ("REA") for each contract, requesting a total of $116.336.56 2 for increases in costs and labor over the two-year period. Subsequently, the contracting officer issued Final Decisions for each contract. The contracting officer determined that the contracts were for construction, and therefore the performance and payment bond requirements were mandatory. The contracting officer further denied both requests on the basis that the bond requirements set forth in FAR 58.228-15 were incorporated into the contracts at the time they were awarded, under the Christian doctrine. On appeal, the Board agreed with the contracting officer. K-Con filed a motion for reconsideration, which the Board denied.

K-Con appeals, seeking reversal of the Board's determination. K-Con argues that the contracts were not construction contracts and, alternatively, that the bond requirements were not incorporated into the contracts by way of the Christian doctrine. Based on these arguments, K-Con requests a remand to the Board to determine the amount to be awarded for K-Con's claims. We have jurisdiction under 28 U.S.C. § 1295 (a)(10).

II

A

K-Con first argues that the Board erred in holding that the contracts at issue are construction contracts. K-Con asserts that they are contracts for commercial items, which do not carry mandatory bonding requirements. The government responds that both contracts are patently ambiguous as to whether they are construction contracts and, thus, it was incumbent on K-Con to inquire as to whether the contracts were for construction or commercial items. Because it did not do so, the government contends that K-Con is precluded from now arguing that the contracts are for commercial items. We agree.

"A patent ambiguity is present when the contract contains facially inconsistent provisions that would place a reasonable contractor on notice and prompt the contractor to rectify the inconsistency by inquiring of the appropriate parties." Stratos Mobile Networks USA, LLC v. United States , 213 F.3d 1375 , 1381 (Fed. Cir. 2000). This is distinct from a latent ambiguity, which exists when the ambiguity is "neither glaring nor substantial nor patently obvious." Cmty. Heating & Plumbing Co. v. Kelso , 987 F.2d 1575 , 1579 (Fed. Cir. 1993) (citing Mountain Home Contractors v. United States , 425 F.2d 1260 , 1264 (Ct. Cl. 1970) ). We review de novo both the existence of an ambiguity and whether any ambiguity is patent or latent because they are both issues of law.

*723 Stratos , 213 F.3d at 1380 (citing Grumman Data Sys. Corp. v. Dalton , 88 F.3d 990 , 997 (Fed. Cir. 1996) ).

We conclude that the contracts were patently ambiguous. On the one hand, as the Army admits, if the contracts had been issued using the standard construction contract form, they would have been construction contracts without any ambiguity. But that is not what happened here. Instead, these contracts issued using the standard commercial items contract form. The line item descriptions even included the phrase "FOB: Destination," which is typically used for commercial items contracts. J.A. 31, 53.

On the other hand, there were many indications that the contracts were for construction, not commercial items.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Konecranes Nuclear Equipment & Services, LLC
Armed Services Board of Contract Appeals, 2024
Allard Nazarian Group, Inc. dba Granite State Manufacturing
Armed Services Board of Contract Appeals, 2024
Bridges v. United States
Federal Claims, 2021
The Boeing Company v. United States
968 F.3d 1371 (Federal Circuit, 2020)
Inserso Corp. v. United States
961 F.3d 1343 (Federal Circuit, 2020)
Gadsden Industrial Park, LLC v. United States
956 F.3d 1362 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
908 F.3d 719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-con-inc-v-secretary-of-the-army-cafc-2018.