Allard Nazarian Group, Inc. dba Granite State Manufacturing

CourtArmed Services Board of Contract Appeals
DecidedJanuary 31, 2024
Docket62413, 62414
StatusPublished

This text of Allard Nazarian Group, Inc. dba Granite State Manufacturing (Allard Nazarian Group, Inc. dba Granite State Manufacturing) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allard Nazarian Group, Inc. dba Granite State Manufacturing, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Allard Nazarian Group, Inc. dba Granite ) ASBCA Nos. 62413, 62414 State Manufacturing ) ) Under Contract Nos. N65540-00-D-0005 ) N65540-00-D-0045 ) N65540-04-D-0020 )

APPEARANCES FOR THE APPELLANT: C. Peter Dungan, Esq. Roger V. Abbott, Esq. Miles & Stockbridge P.C. Washington, D.C.

APPEARANCES FOR THE GOVERNMENT: Samuel W. Morris, Esq. DCMA Chief Trial Attorney Debra E. Berg, Esq. Ryan S. Johnstone, Esq. Evan Georgopoulos, Esq. Trial Attorneys Defense Contract Management Agency Hanscom AFB, MA

OPINION BY ADMINISTRATIVE JUDGE STINSON ON GOVERNMENT’S PARTIAL MOTION FOR RECONSIDERATION

The government requests partial reconsideration of our July 27, 2023, decision granting partial summary judgment to appellant Allard Nazarian Group, Inc. (Allard), dba Granite State Manufacturing. Allard Nazarian Grp., Inc. dba Granite State Mfg., ASBCA Nos. 62413, 62414, 23-1 BCA ¶ 38,408. Allard appealed two contracting officer final decisions assessing a decrement against fixed hourly labor rate charges incurred on a time and materials basis on various Indefinite Delivery, Indefinite Quantity (IDIQ) contracts. We granted Allard’s motion, finding that appellant’s alleged failure to submit auditable final indirect cost rate proposals on its time and material contracts did not provide a proper basis for the government to then assess a decrement on Allard’s costs for direct labor, which were determined by contractually mandated and agreed upon hourly labor rates. Familiarity with that decision is presumed. For the reasons stated below, the government’s motion for partial reconsideration is denied. DISCUSSION

“Motions for reconsideration do not afford litigants the opportunity to take a ‘second bite at the apple’ or to advance arguments that properly should have been presented in an earlier proceeding.” Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014). Reconsideration may be appropriate, however, “if we made mistakes in our findings of fact or conclusions of law, or [failed] to consider an appropriate matter” Supreme Foodservice GMBH, ASBCA No. 57884 et al., 20-1 BCA ¶ 37,716 at 183,090 (citation omitted). “[I]f we have made a genuine oversight that affects the outcome of the appeal, we will remedy it.” Relyant, LLC, ASBCA No. 59809, 18-1 BCA ¶ 37,146 at 180,841.

I. The Government’s Contentions

The government alleges three errors in our decision:

i. The Board committed manifest legal error in concluding that FAR 52.216-7, the Allowable Cost and Payment clause within Allard’s contracts, and the Government’s express remedies provided thereunder, do not apply to all direct costs that the clause required Allard to certify and claim as allowable costs. (See Decision at *21-25)

ii. The Board erred in finding that the Government applied “unilaterally-established final indirect cost rates as a decrement” to Allard’s “direct labor hour rates” due to Allard’s failure to submit a certified and auditable Incurred Cost Proposal (“ICP”). (See Decision at *27-30)

iii. The Board erred by construing and applying a contract clause implementing regulation, FAR 16.307(a)(1), which is not incorporated in any contract, to negate the explicit terms of the Allowable Cost and Payment clause, FAR 52.216-7, to which Allard had a contractual obligation to comply, but which it breached. (See Decision at *20)

(Gov’t mot. at 1-2).

2 II. Government Remedies Under FAR 52.216-7

The government’s first assignment of error is based upon the suggestion that we “committed reversible error” by “concluding that ‘FAR 52.216-7(g) does not provide the government the right to recoup prior overpaid amounts where no auditable support is submitted” (gov’t mot. at 4 (internal citations omitted (citing Allard, 23-1 BCA ¶ 38,408 at 186,625 (quoting the government’s opposition brief to appellant’s motion for partial summary judgment (gov’t opp’n at 2)))). The government misstates our holding. 1 Regarding the government’s reliance upon Federal Acquisition Regulation (FAR) 52.216-7(g), we stated that “[t]he government cites FAR 52.216-7(g) as absolute authority for the contracting officer ‘applying these decrements to all billed costs’ (gov’t opp’n at 2; see also id. at 12-13).” Allard, 23-1 BCA ¶ 38,408 at 186,625. As we explained, the government had argued that FAR 52.216-7(g) permits “reductions to payments due to the billing of unallowable costs or to recoup prior overpaid amounts where no auditable support is submitted.” Id. (citing gov’t opp’n at 2).

In response to the government’s argument, we stated:

FAR 52.216-7(g) provides the government the right to conduct an audit prior to final payment and to reduce or adjust any such payments determined by the contracting officers to be unallowable costs. FAR 52.216-7(g) does not provide the government the right to “recoup prior overpaid amounts where no auditable support is submitted” (id.). Here, the contracting officer's application of a decrement on appellant’s direct labor rate costs was not based upon a payment “found by the Contracting Officer not to constitute allowable costs.” FAR 52.216-7(g). Rather, the government applied a decrement to appellant’s direct labor rate costs based upon appellant’s alleged failure to submit auditable indirect cost rate proposals. FAR 52.216-7(g) does not provide a proper justification, or regulatory authority, for the government’s actions taken here.

Allard, 23-1 BCA ¶ 38,408 at 186,625.

1 We note that our decision was not based solely upon alleged audit rights granted the government pursuant to FAR 52.216-7. Rather, we found that the plain language of FAR 16.307(a)(1) - the same FAR clause that required us to read FAR 52.216-7 into all four contracts - also “limits the application of FAR 52.216-7 to ‘the portion of the contract that provides for reimbursement of materials.’” Allard, 23- 1 BCA ¶ 38,408 at 186,624 (citing FAR 16.307(a)(1)). We discuss the import and application of this FAR provision in section V below. 3 FAR 52.216-7(g) could not be more clear, stating, beneath the heading “Audit,” that “[a]t any time or times before final payment, the Contracting Officer may have the Contractor’s invoices or vouchers and statements of cost audited,” and that “[a]ny payment may be (1) [r]educed by amounts found by the Contracting Officer not to constitute allowable costs; or (2) [a]djusted for prior overpayments or underpayments.” FAR 52.216-7(g). In its opposition to Allard’s motion for partial summary judgment, the government did not allege that its application of the decrement reducing Allard’s costs, including its direct, fixed labor costs, was based upon a determination by the contracting officer that such costs were not allowable or a finding of overpayment. Allard, 23-1 BCA ¶ 38,408 at 186,626. 2 Instead, the government alleged that it “could not validate, through audit, the number of hours and categories of labor claimed and paid over the course of a contractor’s fiscal year” – the premise for the government’s argument being that “labor costs under a T&M contract are based on fixed labor rates multiplied by a variable–i.e. actual time incurred” (gov’t opp’n to app. mpsj at 9; see Allard, 23-1 BCA ¶ 38,408 at 186,627). We pointed out that the government cited no specific language in FAR 52.216-7(g) that gave it the right – in its words – to “recoup prior overpaid amounts where no auditable support is submitted” (Allard, 23-1 BCA ¶ 38,408 at 186,625). Although the government may have a right of recoupment based upon other regulatory provisions, FAR 52.216-7(g) does not provide the government that authority in the context of these appeals.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)
K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Allard Nazarian Group, Inc. dba Granite State Manufacturing, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allard-nazarian-group-inc-dba-granite-state-manufacturing-asbca-2024.