Constructora Guzman, S.A. v. United States

CourtUnited States Court of Federal Claims
DecidedSeptember 7, 2022
Docket19-498
StatusPublished

This text of Constructora Guzman, S.A. v. United States (Constructora Guzman, S.A. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constructora Guzman, S.A. v. United States, (uscfc 2022).

Opinion

In the United States Court of Federal Claims No. 19-498 (Filed: September 7, 2022)

************************************** CONSTRUCTORA GUZMAN, S.A., * * Plaintiff, * Motion to Dismiss; RCFC 12(b)(1); * Standing; Motion for Summary v. * Judgment; RCFC 56; The Miller Act; * Third-Party Beneficiary; Retainage. THE UNITED STATES, * * Defendant. * **************************************

Joseph A. McManus, Jr., Carlton Fields, PA, Washington, DC, counsel for Plaintiff.

Joseph Alan Pixley, U.S. Department of Justice, Washington, DC, counsel for Defendant.

OPINION AND ORDER

DIETZ, Judge.

Plaintiff, Constructora Guzman, S.A. (“Guzman”), seeks payment from the United States for unpaid work that it completed as a subcontractor on a project to renovate the United States Embassy in Guyana. Though it did not have a contract with the United States, Guzman alleges that it was a third-party beneficiary to a modification to a contract between the Department of State (“DOS”) and the prime contractor, Enviro-Management & Research, Inc. (“EMR”). The contract modification allowed DOS to retain a percentage of each payment due EMR in lieu of a requirement for EMR to furnish performance and payment bonds. Guzman alleges that this retainage was intended to guarantee payment to EMR’s subcontractors and, therefore, DOS breached its obligations by releasing the retainage to EMR while Guzman went unpaid for its work.

Before the Court are the government’s motion to dismiss the complaint for lack of standing and the parties’ cross-motions for summary judgment. Guzman’s complaint is based upon its alleged status as a third-party beneficiary, which serves as an exception to the general rule that a plaintiff must be in privity of contract with the government to have standing to sue the government for breach of contract. Accordingly, the government’s motion to dismiss for lack of standing is DENIED. However, because Guzman cannot establish that it was an intended direct beneficiary to the DOS-EMR contract modification, the government’s motion for summary judgment is GRANTED. I. BACKGROUND

In September 2013, DOS awarded a firm-fixed price contract to EMR for the renovation of the United States Embassy in Georgetown, Guyana. [ECF 43-1] at 62-64.1 The total contract value paid to EMR upon completion of the work in 2017 was approximately $17 million. Id. at 89, 113. In January 2015, EMR entered into a subcontract with Guzman for Guzman to provide construction-related services on the embassy project for $8.3 million. Compl. [ECF 1] ¶ 15; see [ECF 43-1] at 31. Guzman completed its work, but EMR failed to pay Guzman in the amount of $1,484,914.43. See [ECF 1] ¶¶ 16-19; see also [ECF 41-8].

This case centers around a modification to the Miller Act bonding requirement contained in the contract between DOS and EMR. See [ECF 43-1] at 76. The Miller Act, 40 U.S.C. §§ 3131 et seq., requires prime contractors on federal construction projects to furnish a performance bond and a payment bond for the protection of the government and subcontractors, respectively. 40 U.S.C. § 3131(b)(1)-(2). The performance bond protects the government if the prime defaults on its work, and the payment bond protects subcontractors if the prime defaults on its payments. See id.; K-Con, Inc. v. Sec’y of Army, 908 F.3d 719, 725-26 (Fed. Cir. 2018). “A contracting officer may waive the requirement of a performance bond and payment bond for work under a contract that is to be performed in a foreign country if the officer finds that it is impracticable for the contractor to furnish the bonds.” 40 U.S.C. § 3131(d).

The DOS-EMR contract incorporated the Miller Act bonding requirements as follows:

H.4.1 Bonds Required The Contractor shall furnish (1) performance and payment bonds . . . in the amount of 100% of the contract price for the performance bond and 100% of the contract price for the payment bond, or (2) comparable alternate security approved by the Government as authorized and in accordance with Federal Acquisition Regulation (FAR) Section/Part 28.204, Alternatives in Lieu of Corporate or Individual Sureties.

***

H.4.3 Coverage The bonds or alternate performance security shall guarantee the Contractor’s execution and completion of the work within the contract time and the correction of any defects after completion as required by this contract, the payment of all wages and other amounts payable by the Contractor under its subcontracts or for labor and materials, and the satisfaction or removal of any liens or encumbrances placed on the work.

[ECF 43-1] at 71.

In October 2013, EMR sent a letter informing the DOS Contracting Officer that EMR was unable to obtain the required performance and payment bonds. [ECF 43-1] at 78. EMR proposed an alternative arrangement in which DOS would retain ten percent of the amounts due EMR for each invoice until certain completion milestones were met, at which point the retainage 1 Pages referenced herein are to those appearing on the electronically-filed docket entry.

2 would be released to EMR. Id. As reflected in an “Action Memorandum” and emails with agency personnel, the Contracting Officer considered three options in response to EMR’s failure to obtain bonds: (1) waive the payment and performance bonds for the award to EMR and withhold retainage until substantial completion is achieved in lieu of bonds; (2) terminate for convenience or default and award the contract to the next acceptable bidder; or (3) terminate for convenience or default and reprocure the solicitation. [ECF 43-1] at 95, 99-100.

In February 2014, the Contracting Officer issued a contract modification which stated that DOS would “[r]etain 10% per invoice in lieu of bonds and additional 10% if the contractor is not performing.” [ECF 43-1] at 76. Because EMR would no longer be required to furnish performance and payment bonds, the modification reduced the contract price by the cost to obtain such bonds. See id. The modification further stated that “[a]ll other terms and conditions remain[ed] unchanged.” Id.

The DOS-EMR contract made EMR responsible for payment of its subcontractors. See [ECF 43-1] at 73. Section H.33.1 required EMR to “satisfy as due all lawful claims of any persons or entities employed by the Contractor, including subcontractors, . . . for all labor performed and materials furnished under this contract, . . . unless the Government shall be directly liable therefore by contract.” Id. at 73-74. Further, with each request for payment, EMR was required to submit to DOS a “certification of payment to subcontractors.” Id. at 69 (capitalization modified).

During performance of the contract, DOS began receiving complaints that EMR was not fulfilling its payment obligations. See [ECF 43-1] at 19-20, 53; see also id. at 117. By letter dated July 7, 2016, DOS informed EMR that “[v]endors, subcontractors, and employees continue to contact [Overseas Buildings Operations (“OBO”)] Georgetown and US Embassy Georgetown with concerns regarding delinquent and non-payment for services rendered.” Id. at 115. The letter stated that EMR’s contractually obligated certifications that it had paid its subcontractors “appear[] to have been at best, disingenuous.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

German Alliance Insurance v. Home Water Supply Co.
226 U.S. 220 (Supreme Court, 1912)
Warth v. Seldin
422 U.S. 490 (Supreme Court, 1975)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
J.G.B. Enterprises, Inc. v. United States
497 F.3d 1259 (Federal Circuit, 2007)
Flexfab, L.L.C. v. United States
424 F.3d 1254 (Federal Circuit, 2005)
Astra USA, Inc. v. Santa Clara County
131 S. Ct. 1342 (Supreme Court, 2011)
Fireman's Fund Insurance Company v. The United States
909 F.2d 495 (Federal Circuit, 1990)
D & H Distributing Company v. United States
102 F.3d 542 (Federal Circuit, 1997)
State of Montana v. United States
124 F.3d 1269 (Federal Circuit, 1997)
Glass v. United States
258 F.3d 1349 (Federal Circuit, 2001)
G4s Technology LLC v. United States
114 Fed. Cl. 662 (Federal Claims, 2014)
G4s Technology LLC v. United States
779 F.3d 1337 (Federal Circuit, 2015)
Crow Creek Sioux Tribe v. United States
900 F.3d 1350 (Federal Circuit, 2018)
K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Constructora Guzman, S.A. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constructora-guzman-sa-v-united-states-uscfc-2022.