Mountain Home Contractors v. United States

425 F.2d 1260, 192 Ct. Cl. 16, 1970 U.S. Ct. Cl. LEXIS 124
CourtUnited States Court of Claims
DecidedMay 15, 1970
Docket87-63
StatusPublished
Cited by5 cases

This text of 425 F.2d 1260 (Mountain Home Contractors v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mountain Home Contractors v. United States, 425 F.2d 1260, 192 Ct. Cl. 16, 1970 U.S. Ct. Cl. LEXIS 124 (cc 1970).

Opinion

425 F.2d 1260

MOUNTAIN HOME CONTRACTORS, a Joint Venture, Consisting of Arthur A. Danekas, W. G. Ellis, John J. Martin and Sea View Lumber Co., Inc., a California Corporation
v.
The UNITED STATES.

No. 87-63.

United States Court of Claims.

May 15, 1970.

Peter A. Lewi, Los Angeles, Cal., for plaintiff. John J. Geraghty, Raleigh, N. C., attorney of record; Peter A. Lewi, Los Angeles, Cal., of counsel.

Robert R. Donlan, Washington, D. C., with whom was Asst. Atty. Gen. William D. Ruckelshaus, for defendant.

Before COWEN, Chief Judge, and LARAMORE, DURFEE, DAVIS, COLLINS, SKELTON, and NICHOLS, Judges.

ON DEFENDANT'S MOTION AND PLAINTIFF'S CROSS-MOTION FOR SUMMARY JUDGMENT

SKELTON, Judge.

This lawsuit by plaintiff, Mountain Home Contractors,1 arises out of a Capehart-Housing contract with the Department of the Air Force for the construction of 300 housing units at a total contract price of $4,918,600. Plaintiff's original and amended petitions allege two causes of action, however, only the second claim, set forth in plaintiff's amended petition, is now before us for decision. The dispute concerns the installation of 298 kitchen exhaust fans in 298 of the 300 housing units. Plaintiff says the installation of these fans was not called for in the contract, and seeks compensation for costs incurred due to the contracting officer's demand that the fans be installed. Both the contracting officer and the Armed Services Board of Contract Appeals (ASBCA) denied plaintiff's claim (ASBCA No. 7961, 1963 B.C.A. ¶ 3725) on the ground that installation of the fans was a part of the contract. The case is now before us on cross-motions for summary judgment. We have concluded that plaintiff is entitled to recover.

This contract was for the construction of 149 duplex buildings (containing 298 housing units) and two separate one unit buildings at Mountain Home Air Force Base, Idaho. There were six basic types of buildings, as follows:

                            Number
        Building Type       of units             Description

      1-A & 1-B __________     116       Airman, 3-Bedroom, Single-story,
                                           Duplex.
      2-A ________________      68       Airman & Officers, 4-Bedroom,
                                           Two-story, Duplex.
      3-A & 3-B __________      72       Officers, 3-Bedroom, Single-story,
                                           Duplex.
      4-A, 4-B, & 4-C ____      36       Officers, 3-Bedroom, Single-story,
                                           Duplex.
      5-A ________________       6       Officers, 4-Bedroom, Two-story,
                                           Duplex.
      6-A & 6-B __________       2       Colonels, 4-Bedroom, Single-story,
                                           Single unit.

As can be seen by this list, 298 of the 300 units were in duplex type buildings. The specifications called for installation of the kitchen exhaust fans where shown on the contract drawings. Drawings numbers 72-77 related to all the buildings (types 1-A through 6-B), and picture kitchen exhaust fans. But drawings 72-76, covering the 298 duplex type units (types 1-A through 5-A), contained the following notation:

NOTE: KITCHEN EXHAUST FANS, DUCT WORK & GRILLE TO BE UNDER ALTERNATE BID

Drawing 77, for the two single-unit buildings designed for the colonels, did not contain this notation.

Under a government contract like the present one, additive alternates are bid separately, and the government has the option of selecting any or all of the alternate items to be included in the contract work. In Section C of the present specifications, 19 alternates were listed, none of which included a kitchen exhaust fan. Of these 19, the defendant ultimately selected 12 for inclusion in the contract work. Plaintiff interpreted this lack of an alternate covering a kitchen exhaust fan to mean that the government did not desire the fans in the 298 duplex units, but only wanted them in the two more expensive units designed for the colonels. Based on this interpretation, plaintiff included in its bid price the cost of only two kitchen fans, and in fact, constructed the 300 units, installing only two kitchen fans (in units 6-A and 6-B). The contracting officer concluded that the contract called for fans in all 300 units, and ordered plaintiff to proceed with installation. This the plaintiff did, and requested additional consideration for the work. On November 29, 1961, the contracting officer denied plaintiff's request. This decision was appealed to the ASBCA, which denied the appeal. Plaintiff is now before us alleging that the decision of the ASBCA is arbitrary and is not supported by substantial evidence. Plaintiff says his interpretation of the contract was reasonable. Defendant, of course, says the decision of the ASBCA is neither arbitrary nor capricious, and is supported by substantial evidence, and that, therefore, under the Wunderlich Act, 41 U.S.C. §§ 321-322 (1964), the decision is final and conclusive.

Defendant justifies its inadvertent failure to remove the troublesome notation from the drawings by citing Paragraph 4 of the Invitation for Bids, which stated:

* * * Should the bidder find discrepancies in, or omissions from, such Drawings and Specifications or other documents attached hereto, or should he be in doubt as to their meaning, he should at once notify the Contracting Officer, Mountain Home Air Force Base, Idaho and obtain clarification prior to submitting a bid. * * *

This general language was repeated in Paragraph 2(d) of the General Provisions of the contract. Therefore, says defendant, plaintiff had the burden of clarifying this discrepancy, and having failed to do so, the government is under no obligation to pay for the fans.

Supplementing this argument, the goverment cites Paragraph 2(c) of the General Provisions of the contract, which states, "In case of difference between drawings and specifications, the specifications shall govern." Since the specifications called for fans "where shown," and the drawings showed fans, the government says it was not reasonable for plaintiff to rely on the notation subjecting the fans to an alternate bid, and that the specifications should govern.

The plaintiff says that in any event the contract documents were ambiguous. We agree. This ambiguity will be apparent in the following paragraphs of this opinion.

Thus, the parties have framed the two issues in this case, which must be answered consecutively. See L. Rosenman Corp. v. United States, 182 Ct.Cl. 586, 590, 390 F.2d 711, 713 (1968). The first issue is whether the discrepancy, omission or ambiguity was drastic, glaring or patent. Beacon Constr. Co. v. United States, 161 C.Cl. 1, 314 F.2d 501 (1963); WPC Enterprises, Inc. v. United States, 163 Ct.Cl. 1, 323 F.2d 874 (1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)
United States v. Schlesinger
88 F. Supp. 2d 431 (D. Maryland, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
425 F.2d 1260, 192 Ct. Cl. 16, 1970 U.S. Ct. Cl. LEXIS 124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mountain-home-contractors-v-united-states-cc-1970.