Sundstrand Turbo, a Division of Sundstrand Corporation v. The United States

389 F.2d 406, 182 Ct. Cl. 31, 1968 U.S. Ct. Cl. LEXIS 47
CourtUnited States Court of Claims
DecidedJanuary 19, 1968
Docket300-65
StatusPublished
Cited by51 cases

This text of 389 F.2d 406 (Sundstrand Turbo, a Division of Sundstrand Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sundstrand Turbo, a Division of Sundstrand Corporation v. The United States, 389 F.2d 406, 182 Ct. Cl. 31, 1968 U.S. Ct. Cl. LEXIS 47 (cc 1968).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT'S CROSS MOTION FOR SUMMARY JUDGMENT

SKELTON, Judge.

This is a suit to recover claims based on the termination for convenience by the government of two cost-plus-fixed fee (CPFF) contracts. The defendant awarded contract number AF 04(645)-27 (hereinafter referred to as contract 27) to American Machine and Foundry Company (hereinafter called AMF) for research, development, and design of an accessory power system (APS) for the Atlas Missile for an estimated $5,930,-539.25, on July 19, 1956. A second contract was awarded to this company on February 14, 1957, being number AF 04(647)-73 (hereinafter called contract 73), which called for the manufacture of 112 APS at the company’s “Turbo Division” plant at Pacoima, California, and funded in the amount of $6,206,466. The power system was to be of the gas-generated type. These contracts were amended from time to time so that by the date they were terminated their estimated costs and fixed fees had been increased to $27,112,668.23. The 112 APS units were required to be delivered by December 31, 1959.

AMF began work on the two contracts in a building known as No. 10, which it had constructed in 1956. This building was sold by AMF to the Aetna Life Insurance Company and leased back from this company for a period of ten years at an annual rental of $62,183.

On January 31, 1958, the plaintiff, Sundstrand Turbo, a division of Sund-strand Corporation, an Illinois Corporation (hereinafter called plaintiff or Sundstrand) purchased the properties and fixed assets, including the two contracts involved here, of AMF’s Turbo Division for the sum of one million dollars, based on the appraisal of private appraisers employed by plaintiff to value the property. These fixed assets had previously been carried on the books of AMF in the approximate amount of *409 $500,000. The defendant accepted plaintiff as the successor of AMF on the two contracts in accordance with the provisions of a novation agreement signed February 1, 1958, by defendant, plaintiff, and AMF, the pertinent portions of which will be described in the ensuing paragraphs. The plaintiff immediately entered upon the performance of the two contracts.

During the performance of the contracts, the defendant decided to use a different propellant system for the Atlas missiles than that called for in the instant contracts, and, accordingly, terminated both contracts on February 10, 1959, for the convenience of the government under the “Termination for Convenience” clause of the contract. 1 2 There was no dissatisfaction with plaintiff’s performance of the contracts, and the termination was caused solely by the decision of the government to use a different propellant system for the missiles.

Upon the termination of the contracts, problems immediately arose as to the types, kinds, and extent of termination costs, fees, and expenses that should be paid to plaintiff by defendant. Situations of this kind always pose problems for all concerned, and this case is no exception. The plaintiff presented bills and vouchers for its fees and costs to defendant for payment. The fees were negotiated and agreed upon and defendant paid plaintiff as fees the sum of $786,000 on contract 27 and $650,000 on contract 73. Plaintiff was paid $14,792,-029.10 as costs on contract 27 .and $10,-884,639.13 on contract 73. However, plaintiff claimed that it was entitled to an additional $552,983.51 as reimbursement for its actual rental, occupancy, depreciation and general and administrative (G&A) costs, and an additional sum of $310,266.38 for breach of an implied contract by defendant. These items, except the breach of contract claim, which is now Count II, were presented by plaintiff to defendant in the form of five separate claims,® which comprise Count I before this court. They may be briefly described as follows:

Claim 1 — for depreciation costs on the purchase price valuation of approximately one million dollars plaintiff paid AMF for its fixed assets' from the date of purchase. Defendant’s contracting officer disallowed this valuation except as to the value of $500,-000 carried on the books of AMF for such fixed assets. Plaintiff claims the difference in its depreciation costs in the sum of $141,876.13.
Claim 2 — for rental costs incurred for building No. 10 from August 1, 1960, to June 1, 1962, in the amount of $151,725.
Claim 3 — for true depreciation costs for building No. 20 under a certificate of necessity for the remainder of the five-year depreciation period continuing after December 31, 1959, in the sum of $50,439.94.
Claim 4 3 — for costs of occupancy of building No. 10, representing idle space costs, from January 1, 1960, to August 1, 1960, in the sum of $100,841.
Claim 5 4 — for general and administrative costs relating to subcontract administration and termination, in the sum of $108,101.44.

All of these claims were submitted to the contracting officer and they were denied by him. The plaintiff duly appealed to the Armed Services Board of Contract Appeals (ASBCA), which consolidated the claims into one case, conducted a trial and heard evidence, and handed down an opinion sustaining the decision of the *410 contracting officer and denying all of plaintiff’s claims. 5

Thereafter, plaintiff filed this suit in which it seeks recovery on the same claims which were denied by the ASBCA, together with its claim for breach of contract. It contends that the decision of the ASBCA (sometimes called the Board) on factual matters is not binding on this court because it is capricious, or arbitrary, or so grossly erroneous as to imply bad faith, or is not supported by substantial evidence. It also alleges that the decision of the Board on questions of law is erroneous and has no finality. The case is now before us for judicial review.

The defendant urges that the Board’s decision should be accorded finality in view of the Wunderlich Act, 68 Stat. 81, 41 U.S.C. §§ 321-322 (1964); Morrison-Knudsen v. United States, 345 F.2d 833, 170 Ct.Cl. 757 (1965); United States v. Carlo Bianchi & Co., 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963) and similar cases. Without doubt, the Board had jurisdiction of these claims and could have granted complete relief under the provisions of the two contracts. It conducted a full trial, received evidence and briefs of the parties, made findings and conclusions and disposed of all the claims involved. Under these circumstances, the scope of our review is narrow and limited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Veridyne Corp. v. United States
105 Fed. Cl. 769 (Federal Claims, 2012)
Naylor v. United States
53 Fed. Cl. 172 (Federal Claims, 2002)
J.F. Whalen & Company v. The United States
895 F.2d 1422 (Federal Circuit, 1990)
Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Marquardt Company v. The United States
822 F.2d 1573 (Federal Circuit, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)
Roflan Co. v. United States
32 Cont. Cas. Fed. 73,207 (Court of Claims, 1985)
Peterson-Sharpe Engineering Corp. v. United States
32 Cont. Cas. Fed. 72,873 (Court of Claims, 1984)
Entwistle Co. v. United States
32 Cont. Cas. Fed. 72,807 (Court of Claims, 1984)
Flexible Metal Hose Manufacturing Co. v. United States
31 Cont. Cas. Fed. 72,120 (Court of Claims, 1984)
D & S Universal Mining Co. v. United States
31 Cont. Cas. Fed. 71,929 (Court of Claims, 1983)
S.S. Silberblatt, Inc. v. United States
31 Cont. Cas. Fed. 71,734 (Court of Claims, 1983)
R-D Mounts, Inc. v. United States
30 Cont. Cas. Fed. 71,059 (Court of Claims, 1983)
Mark A. Carroll & Son, Inc. v. United States
29 Cont. Cas. Fed. 82,684 (Court of Claims, 1982)
Ordnance Research, Inc. v. United States
609 F.2d 462 (Court of Claims, 1979)
Coley Properties Corp. v. United States
593 F.2d 380 (Court of Claims, 1979)
Jet Construction Co. v. United States
531 F.2d 538 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
389 F.2d 406, 182 Ct. Cl. 31, 1968 U.S. Ct. Cl. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sundstrand-turbo-a-division-of-sundstrand-corporation-v-the-united-states-cc-1968.