Entwistle Co. v. United States

32 Cont. Cas. Fed. 72,807, 6 Cl. Ct. 281, 1984 U.S. Claims LEXIS 1322
CourtUnited States Court of Claims
DecidedAugust 28, 1984
DocketNo. 385-80C
StatusPublished
Cited by4 cases

This text of 32 Cont. Cas. Fed. 72,807 (Entwistle Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Entwistle Co. v. United States, 32 Cont. Cas. Fed. 72,807, 6 Cl. Ct. 281, 1984 U.S. Claims LEXIS 1322 (cc 1984).

Opinion

[282]*282OPINION

LYDON, Judge:

This government contract case involves review, under the standards of the Wun-derlich Act, 41 U.S.C. §§ 321, 322 (1976), of decisions by the Armed Services Board of Contract Appeals (Board). ASBCA Nos. 14918 and 15827, 75-2 BCA 1111,420; 76-2 BCA 1112,108. As part of these decisions in this case, the Board found the government liable for delay costs for 455 days. The Board, inter alia, awarded plaintiff $60,319.59 in interest expenses caused by the delay, but did not allow plaintiff any interest expense incurred after the filing of its appeal with the Board. Both parties have moved for summary judgment attacking selected portions of the Board decisions.

Plaintiff contends that the Board improperly disallowed its claim for post-appeal interest, and seeks to recover $864,145.49 in interest for the period during which its appeal in this case was before the Board, i.e., January 20,1970 to August 1976.1 Defendant opposes plaintiffs motion and argues that plaintiff is not entitled to recover on its post-appeal interest claim. Moreover, defendant presents a counterclaim in its cross-motion for summary judgment contending that the Board improperly awarded plaintiff $60,319.59 in pre-award interest expense because plaintiff failed to establish the required direct relationship between the interest expense and the government caused delay.

After consideration of the submissions of the parties, and oral argument thereon, the court affirms the Board’s decisions both with respect to its denial of plaintiff’s post-appeal interest claim and its award to plaintiff of $60,319.59 in pre-appeal interest expense to which defendant objected and upon which defendant’s counterclaim is based.

Facts

On November 10, 1966, plaintiff was awarded a contract (N00156-67-C-1425) by the Naval Air Engineering Center (NAEC) in Philadelphia, Pennsylvania. Under the terms of this contract, plaintiff was to manufacture, test, and deliver 6 Short Airfield Tactical System (SATS) catapults and various quantities of spare parts for these SATS catapults. This was a straight manufacturing contract which entailed no engineering development by plaintiff. The SATS catapults were part of a short airfield system which was designed to duplicate on land the process of launching and landing aircraft which was used on aircraft carriers.

The original contract price was $10,358,-810.35 with a provision for a 5 percent prompt payment discount. The contract specified that the 6 catapult systems were to be delivered during the period July 1967 to September 1967. The contract also specified that the delivery of spare parts was tó be completed by December 29, 1967. Thus, the original contract period was for 13 months and 19 days after award.

The performance of the contract was delayed by a series of 57 contract modifications, as well as by plaintiff having to make 164 Requests for Engineering Information (REIS) because of incomplete or incorrect drawings or specifications. As a result of these modifications and corrections, plaintiff’s performance of the contract was delayed. The contract completion date was rescheduled to July 25, 1969. Thus, the extended delivery date of July 25, 1969, was almost 19 months longer than the original completion date of the project, December 27, 1967. Plaintiff claimed that 16 months of the 19-month delay was attributable to the government.

On January 20, 1970, plaintiff appealed a December 23, 1969, contracting officer’s decision which denied plaintiff’s claim for an equitable adjustment of $1,398,455.12 as compensation for additional costs plaintiff [283]*283incurred on this contract. Plaintiff subsequently amended his claim on appeal to the Board and increased the claim to $2,097,084 plus $580,563 for post-appeal interest.2 This $580,563 interest claim was for interest on plaintiffs equitable adjustment claim from the date plaintiff filed its appeal before the Board, January 20, 1970, until September 30, 1973.3

The Board found that of the 481 days of delay claimed by plaintiff, defendant was responsible for 455 days of delay and plaintiff was responsible for 26 days.4 The Board allowed plaintiff a total recovery of $1,181,697.64, including $60,319.59 in pre-appeal interest expense on its claim. The Board, however, did not allow plaintiff any recovery for its post-appeal interest claim since the regulation relied on by plaintiff, ASPR § 7-104.82, was not effective at the time plaintiff entered into the contract at issue, and therefore there was no statute, regulation or contract provision authorizing the payment of post-appeal interest to plaintiff.5 In awarding plaintiff pre-appeal interest, the Board reduced plaintiffs $87,-479 interest claim to $60,319.59. The Board specifically found as a fact that this $60,319.59 amount in pre-appeal interest resulted from government-caused delay.

Plaintiff thereafter filed the present action seeking post-appeal interest of $580,-563 for the period January 20, 1970, through September 30, 1973, plus an additional amount of $283,502.49 for additional post-appeal interest for the period October 1, 1973, to August 30, 1976.6

II.

Plaintiff, in its summary judgment motion, seeks to overturn the Board’s decisions denying its post-appeal interest claim. The general rule is that interest is not recoverable against the United States absent a statute or contract provision authorizing such payment. 28 U.S.C. § 2516(a) (1982); Brookfield Constr. Co. v. United States, 228 Ct.Cl. 551, 559, 661 F.2d 159, 165 (1981); First National City Bank v. United States, 212 Ct.Cl. 357, 371, 548 F.2d 928, 937 (1977). Plaintiff, in its motion for summary judgment, does not rely on any statute, regulation or contract provision for its post-appeal interest claim. At the time, the contract at issue was entered into, there was no statute, regulation or contract provision which authorized the payment of post-appeal interest on a contractor’s claim. Therefore, plaintiff, having abandoned its ill-fated reliance on ASPR 7-104.82, now contends that post-appeal interest is includable as part of an equitable adjustment claim under the Court of Claims decision in Bell v. United States, 186 Ct.Cl. 189, 205-207, 404 F.2d 975, 984 (1968).7

[284]*284In Bell v. United States, supra, the Court of Claims held that interest expense incurred as a result of financing a government directed change under the changes clause was recoverable as part of an equitable adjustment under the changes clause. The issue in Bell involved interest expense incurred during the actual performance of the additional government-directed work. Bell v. United States, supra, 186 Ct.Cl. at 206, 404 F.2d at 984. Plaintiff contends that Bell v. United States, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ulmet v. United States
19 Cl. Ct. 527 (Court of Claims, 1990)
Jetco, Inc. v. United States
11 Cl. Ct. 837 (Court of Claims, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)
Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States
33 Cont. Cas. Fed. 74,502 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,807, 6 Cl. Ct. 281, 1984 U.S. Claims LEXIS 1322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/entwistle-co-v-united-states-cc-1984.