Gevyn Construction Corp. v. United States

33 Cont. Cas. Fed. 74,851, 11 Cl. Ct. 203, 1986 U.S. Claims LEXIS 760
CourtUnited States Court of Claims
DecidedNovember 28, 1986
DocketNo. 158-74
StatusPublished
Cited by4 cases

This text of 33 Cont. Cas. Fed. 74,851 (Gevyn Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gevyn Construction Corp. v. United States, 33 Cont. Cas. Fed. 74,851, 11 Cl. Ct. 203, 1986 U.S. Claims LEXIS 760 (cc 1986).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This construction contract case is before the court on cross-motions for summary judgement. Plaintiff, Gevyn Construction Company, contracted with defendant for the rehabilitation of the Boston Veterans Administration Hospital and subcontracted to Potomac Metal Products, Inc. (Potomac Metal) a portion of the work. Gevyn seeks review, in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1982), of a decision of the Army Corps of Engineers Board of Contract Appeals (ENGBCA) which denied both Gevyn’s claim and the claim that Gevyn made on behalf of its subcontractor Potomac Metal.

Gevyn’s claim is for imputed interest at six percent on funds it invested in the project as a result of changes in the contract made by the government. Only questions of law are involved in Gevyn’s claim, and the court finds that the ENGBCA decision is correct as a matter of law and should be affirmed. Potomac Metal’s claim is for alleged actual interest expense incurred as a result of government caused changes in the contract. Only questions of fact are involved in Potomac Metal’s claim and the court finds that the ENGBCA’s findings are supported by substantial evidence and, therefore, are entitled to finality.

FACTS

The Gevyn contract, originally in the amount of $4,134,625.00 was made on June 28, 1963, and called for replacing a brick wall with a metal curtain wall and general rehabilitation of a Veterans Administration hospital building. On July 18, 1963, Gevyn entered into a subcontract with Potomac Metal, in the original amount of $1,035,-000.00, for a large portion of the contract work. A number of problems were encountered by both Gevyn and its subcontractors, principally Potomac Metal, during performance of the contract. However, the contract work was substantially completed December 1, 1965 and was accepted by the Government on February 26, 1967.

In November of 1967, Gevyn filed a consolidated claim with the contracting officer, under the provisions of its contract, for extra expense incurred due to government [205]*205caused changes and delays in the contract. The total amount claimed by Gevyn was $1,799,668.72, of which $1,095,583.65 was on behalf of Potomac Metal. The contracting officer denied the full claim on March 10, 1969, and Gevyn appealed to the ENGBCA, which subsequently upheld the decision of the contracting officer. Gevyn then filed a petition in the Court of Claims seeking Wunderlich Act review of the ENGBCA decision. The Court of Claims held in Gevyn’s favor on issues of changed condition, suspension, delay or interruption of the work, and acceleration. Trial Division case no. 158-74, opinion filed December 30,1977. The Court of Claims remanded the case to the contracting officer with instructions to negotiate an equitable adjustment on those claims where the court had found defendant liable. The total payment made by the Government under the resulting equitable adjustment was $1,150,-000.00, of which the government attributed $748,935.00 to Potomac Metal, and $401,-065.00 to Gevyn.

In the equitable adjustment, Gevyn reserved the right to pursue its claims for the cost of financing the extra work, labor, labor services, and equipment included in the equitable adjustment. On March 10, 1969, the contracting officer issued a final decision denying the interest expense claims. Gevyn appealed to the ENGBCA a few days thereafter. The ENGBCA again upheld the contracting officer and denied Gevyn’s interest expense claim. Gevyn, ENGBCA 3031, 83-1 BCA 1116,428. Gevyn then petitioned this court for the second time for review of the ENGBCA decision.

DISCUSSION

The present case comes before this court on Cross-Motions for Summary Judgment. Summary judgment is appropriate in this case because there are no genuine issues of material fact in dispute and judgment is appropriate as a matter of law. South Louisiana Grain Services, Inc. v. United States, 1 Cl.Ct. 281, 289 (1982).

Gevyn’s Claim

Gevyn asserts that the equity capital it used to fund changed work should be assigned a value, in the nature of imputed interest, which it seeks to recover in an equitable adjustment under the provisions of its contract. In Bell v. United States, 186 Ct.Cl. 189, 404 F.2d 975 (1968), this court held that 28 U.S.C. § 2516(a) (1982), which generally prohibits the award of interest against the government, is not a bar to the award of actual interest costs as part of an equitable adjustment under the provisions of a fixed-price government contract.

Related

Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Bromley Contracting Co. v. United States
34 Cont. Cas. Fed. 75,415 (Court of Claims, 1987)
Gevyn Construction Corp. v. The United States
827 F.2d 752 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,851, 11 Cl. Ct. 203, 1986 U.S. Claims LEXIS 760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gevyn-construction-corp-v-united-states-cc-1986.