Bromley Contracting Co. v. United States

34 Cont. Cas. Fed. 75,415, 14 Cl. Ct. 69, 1987 U.S. Claims LEXIS 226, 1987 WL 22374
United States Court of Claims·Decided December 8, 1987·No. No. 443-84C·Published·Cited by 3 cases

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

Plaintiff, Bromley Contracting Co., Inc., motioned for summary judgment under Wunderlich Act review of two decisions of the Department of Transportation Board of Contract Appeals (Board). Defendant argued that plaintiff failed to show that the Board’s decisions were arbitrary, capricious, unsupported by substantial evidence, or otherwise not in accordance with applicable law, and moved to dismiss the complaint. Jurisdiction lies in this court pursuant to the Wunderlich Act, 41 U.S.C. §§ 321-322 (1976), because plaintiff’s cause of action was a pre-Contract Disputes Act proceeding. E.g., Opalack v. United States, 5 Cl.Ct. 349 (1984).

FACTS

On June 30, 1975, the United States Coast Guard awarded contract number DOT-CG03-6287 to plaintiff, the lowest bidder. The contract required plaintiff to repoint and waterproof various portions of the exterior masonry and to renew the windows of various buildings of the Coast Guard’s facility at Governor’s Island, New York. Disputes arose over the scope of work contemplated and performed in the contract, the appropriate categorization of work as restorative or protective, and over the payment due the contractor under each category. Plaintiff appealed an adverse decision of the contracting officer on these [72] issues to the Board. The Board issued an opinion on entitlement and remanded the matter to the parties to negotiate quantum. Bromley Contracting Co., 1981-2 B.C.A. (CCH) ¶ 15,191 (1981) (Bromley I). When settlement negotiations failed, plaintiff requested a final decision on quantum from the contracting officer. Plaintiff appealed the contracting officer’s decision on quantum to the Board. The Board ruled, Bromley Contracting Co., 1984-2 B.C.A. (CCH) ¶ 17,233 (1984) (Bromley II), and plaintiff appealed under the Wunderlich Act to the court.

DISCUSSION

The Board made exhaustive and detailed findings of fact in both decisions. Since plaintiff carries the burden of contesting the legal substantiality of the decisions, we will forego recitation of such intricacies as are irrelevant to the challenged findings. Under Wunderlich Act review, administrative findings of fact are conclusive and binding on this court unless the plaintiff can show that the finding of fact is fraudulent, capricious or arbitrary, or so grossly erroneous as to imply bad faith, or is not supported by substantial evidence. Koppers Co. v. United States, 186 Ct.Cl. 142, 147, 405 F.2d 554, 557 (1968); 41 U.S.C. § 321 (1982). The substantial evidence test is a reasonable person standard; that is, the “standard goes to the reasonableness of what the agency did on the basis of the evidence before it.” United States v. Carlo Bianchi & Co., 373 U.S. 709, 715, 83 S.Ct. 1409, 1414, 10 L.Ed. 2d 652 (1963) (emphasis in original). The reasonableness of the Board’s action, then, does not turn on whether there was no evidence in the record below to support a finding for plaintiff, but rather whether the Board’s finding against plaintiff was substantial under Wunderlich standards. Plaintiff, therefore, carries a heavy burden. In its effort to meet this burden, plaintiff may not resort to de novo reargument of the facts and evidence, Bianchi, 373 U.S. at 715, 83 S.Ct. at 1414. It must instead present the Board’s conclusions of fact, in light of the evidence used by the Board to reach that conclusion, and show how these conclusions are unsubstantiated by the evidence. On questions of law, this court is not bound by the Board’s determinations, though such determinations should be given careful consideration. Gevyn Constr. Co. v. United States, 11 Cl.Ct. 203, 205 (1986), aff'd, 827 F.2d 752 (Fed.Cir.1987) (citing Raytheon Co. v. United States, 2 Cl.Ct. 763, 767 (1983), aff'd, 730 F.2d 1470 (Fed.Cir.1984)).

Set Backs

All bidders to this contract based their bids on the work specifications included in the bid package, and on an architect’s drawing of some of the work areas. The amount of restoration work to be performed on various buildings was estimated by shaded areas on the drawings. The drawings’ companion specifications indicated square footage figures corresponding to the shaded areas. Neither the drawings nor the specifications, however, indicated that the walls contained recesses, or “set backs.” Plaintiff claimed before the Board that the “set backs” constituted 11,600 square feet1 of extra work for which plaintiff should receive additional compensation.

The Board denied the claim, stating that [plaintiff] should have known about these deviations from the drawings during performance because the work required constant referral to the drawings to determine the shaded areas. By its failure to object to patently defective drawings, [plaintiff] waived its rights to claim compensation for these defects.

Bromley I, 1981-2 B.C.A. (CCH) ¶ 15,191, p. 75,203 (citing S.O.G. of Arkansas v. United States, 212 Ct.Cl. 125, 546 F.2d 367 (1976)).

In its appeal to this court plaintiff argued that the Board erred because bidders could do nothing else than bid on the [73] square footing figures listed in the specifications and on those areas actually shown in the shaded drawings. This approach, however, fails to attack the interpretation of law upon which the Board relied in holding against plaintiff. The Board found that plaintiff was required to, and did, in fact, inspect the buildings prior to the award of the contract. Plaintiff did not dispute this finding. The Board also found, as previously noted, that the “set backs” ranged from one to twenty feet deep. Plaintiff, likewise, did not dispute this finding. The discrepancy between the areas shown and those actually observed should have been obvious to any bidder inspecting the buildings before embarking on the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Bromley Contracting Co. v. United States, 34 Cont. Cas. Fed. 75,415, 14 Cl. Ct. 69, 1987 U.S. Claims LEXIS 226, 1987 WL 22374 (cc 1987).

34 Cont. Cas. Fed. 75,415 (Bromley Contracting Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Al-Kurdi v. United States
35 Cont. Cas. Fed. 75,655 (Court of Claims, 1989)
Monarch Painting Corp. v. United States
35 Cont. Cas. Fed. 75,623 (Court of Claims, 1989)
Bromley Contracting Co., Inc. v. The United States
861 F.2d 729 (Federal Circuit, 1988)