Opalack v. United States

32 Cont. Cas. Fed. 72,500, 5 Cl. Ct. 349, 1984 U.S. Claims LEXIS 1408
CourtUnited States Court of Claims
DecidedMay 15, 1984
DocketNo. 618-81C
StatusPublished
Cited by13 cases

This text of 32 Cont. Cas. Fed. 72,500 (Opalack v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Opalack v. United States, 32 Cont. Cas. Fed. 72,500, 5 Cl. Ct. 349, 1984 U.S. Claims LEXIS 1408 (cc 1984).

Opinion

ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

OPINION

SPECTOR, Senior Judge.

The contract dispute involved in this case has previously been the subject of two intermingled administrative decisions within the Department of Labor. The second decision was required as the result of obvious procedural irregularities in rendering the first. It is necessary at the threshold to analyze in general terms the subject matter and nature of these decisions in order to establish the jurisdiction of this court to review them and the standards to be applied in that review.

The first of these decisions is captioned:

In the Matter of Suspension and Proposed Debarment of OPALACK AND COMPANY from participation in contracting or subcontracting with the UNITED STATES DEPARTMENT OF LABOR

It is entitled “Decision and Order”, is printed on letterhead of the United States Department of Labor, Board of Contract Appeals, and bears a “BCA” docket number. The first sentence reads as follows:

This is a proceeding for debarment of a Government contractor pursuant to the Federal Procurement Regulations (41 CFR Subpart 1-1.6), joined with the contractor’s appeal from a termination for default. [Emphasis supplied.]

The “Decision and Order” is signed by a single Administrative Law Judge (AU). He states therein:

* * * On January 4, 1979, the Department issued a notice of proposed Department-wide debarment of the Contractor for a period of three years pursuant to [352]*35241 CFR Subpart 1-1.6, together with notice of immediate suspension under the provisions of 41 CFR § 1-1.605.
The Contractor thereupon requested a hearing upon the action taken under the above notice dated January 4, 1979 [debarment], and such hearing was duly held on all issues before the undersigned, to whom the Secretary of Labor duly delegated the authority to make a final decision for the Department on the said suspension and debarment. * * * [Emphasis supplied.]

The “Decision and Order” of AU Feldman further recites that it was based on a seven-day hearing and 1,200 pages of transcript plus exhibits. He concluded that the “notice of suspension did not comply with applicable Regulations” and further “that the evidence adduced at the hearing did not warrant suspension * * * ”. He issued an order terminating the suspension “and deferring determination of all other issues until after receipt and consideration of the entire record and the briefs of respective counsel.” The remainder of the “Decision and Order” recites the facts and issues which he thereafter developed together with his findings which included a determination that the debarment was justified.

However, he also concluded (and here’s the rub) that the termination for default by the contracting officer of one of the two contracts here involved was proper. The notice of hearing which preceded the decision was, as above indicated, addressed solely to the debarment issue, and AU Feldman had characterized himself as a single representative of the Secretary of Labor to address that issue under the applicable regulations. Below his signature on the “Decision and Order” appears the following:

N.B. — Decision on Appeal from Termination is endorsed on next page. [Emphasis supplied.]

On the next page it is stated:

Upon such of the foregoing findings of fact and conclusions of law as are pertinent to the appeal, the termination of Contract No. J-9-D-7-0148 for default of the Contractor is hereby in all respects affirmed. [Emphasis supplied.]
Department of Labor Board of Contract Appeals
Robert J. Feldman
Panel Chairman
Robert L. Ramsey
Panel Member

This treatment of the default termination issue was contrary to the notice of hearing and the agreement made at the outset of the hearing on suspension and debarment. Both parties and AU Feldman had agreed that the only issues to be determined at that hearing were suspension and debarment. At that time, Opalack and Co. had not even filed an appeal to the Labor Department’s Board of Contract Appeals from the contracting officer’s decision terminating one of the contracts for default. The Labor Department’s attorney and AU Feldman had agreed to permit an appeal on that issue to the BCA at a later time, and the record clearly indicates that a separate and later hearing was contemplated on the default termination issue. AU Feldman had nevertheless rendered a decision on both the debarment and termination issues, while hearing evidence directed to only one of those issues. There was an effort to rectify this problem by signing the opinion twice, once as a single representative of the Secretary of Labor on the debarment issue, and a second time as a member of a panel of the Department’s Board of Contract Appeals, which another member also signed.

The plaintiffs herein then moved that the issue of the propriety of the default termination be reopened and reconsidered. The motion was granted and additional evidence was taken, following which a very brief decision was rendered by the same two members of the BCA. It concluded:

[353]*353Appellants have not shown on the reopening that there was any error or infirmity in the original decision. The affirmance of the termination * * * for default of the Contractor is therefore confirmed.

In view of the foregoing, the issue of the propriety of the default termination is being reviewed here on the basis of both of the two administrative decisions above described and their underlying records. The case is brought under the Tucker Act1 and it is not eligible for review under the Contract Disputes Act2 because the claim was no longer pending before the contracting officer on the effective date of that Act or thereafter. It is therefore being reviewed by this court rather than by the Court of Appeals for the Federal Circuit,3 and the standards of review to be applied are those set forth in the Wunderlich Act.4 The review is on cross-motions for summary judgment, in accordance with the then applicable rules.

Statement of Facts5

This contract dispute arises out of two contracts between the Department of Labor (DOL), Office of Accounting, and Opalack and Co. (Opalack), an accounting firm. The first of these contracts was No. J-9D-6-0191 (191), dated September 14, 1976. Pursuant thereto, Opalack was to audit certain DOL grants and contracts in the States of Indiana, Iowa, Michigan, Mississippi, Missouri, North Carolina, Ohio, Oklahoma, Texas, and the Washington, D.C. metropolitan area. The second contract, No. J-9-D-7-0148(148), dated September 26, 1977, involved the audit of DOL grantees under the Comprehensive Employment & Training Act (CETA) in four geographical regions. Contract 191 was in the amount of $318,060, and the stated amount of contract 148 was $223,648.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nwogu v. United States
94 Fed. Cl. 637 (Federal Claims, 2010)
Vincent Schickler, TMD U.S.A., Inc. v. United States
54 Fed. Cl. 264 (Federal Claims, 2002)
Town Center Management Corp. v. United States
39 Cont. Cas. Fed. 76,691 (Federal Claims, 1994)
Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)
Shearson Lehman Hutton, Inc. v. United States
37 Cont. Cas. Fed. 76,245 (Court of Claims, 1991)
Martin v. United States
20 Cl. Ct. 738 (Court of Claims, 1990)
Neal & Co. v. United States
36 Cont. Cas. Fed. 75,802 (Court of Claims, 1990)
Seaboard Lumber Co. v. United States
19 Cl. Ct. 310 (Court of Claims, 1990)
International Business Investments, Inc. v. United States
35 Cont. Cas. Fed. 75,668 (Court of Claims, 1989)
Westerchil Construction Co. v. United States
35 Cont. Cas. Fed. 75,657 (Court of Claims, 1989)
Bromley Contracting Co. v. United States
34 Cont. Cas. Fed. 75,415 (Court of Claims, 1987)
Randallstown Plaza Associates v. United States
13 Cl. Ct. 703 (Court of Claims, 1987)
Saunooke v. United States
8 Cl. Ct. 327 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,500, 5 Cl. Ct. 349, 1984 U.S. Claims LEXIS 1408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/opalack-v-united-states-cc-1984.