Framlau Corp. v. United States

568 F.2d 687, 24 Cont. Cas. Fed. 81,906, 215 Ct. Cl. 185, 1977 U.S. Ct. Cl. LEXIS 123
CourtUnited States Court of Claims
DecidedDecember 14, 1977
DocketNo. 274-74
StatusPublished
Cited by28 cases

This text of 568 F.2d 687 (Framlau Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Framlau Corp. v. United States, 568 F.2d 687, 24 Cont. Cas. Fed. 81,906, 215 Ct. Cl. 185, 1977 U.S. Ct. Cl. LEXIS 123 (cc 1977).

Opinion

Bennett, Judge,

delivered the opinion of the court:

This case, arising under the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970), is before the court on plaintiffs appeal from a decision entered by Trial Judge Francis C. Browne, allowing defendant’s cross-motion for summary judgment. Plaintiff does not request review of seven counts of its petition disposed of by the trial judge. What remains for our attention are counts III, VIII, X, and XI of plaintiffs petition and plaintiffs motion for summary judgment as it relates to those counts.1 We reach the same result as the trial judge but by a somewhat different and shorter route.

Numerous issues were decided adversely to plaintiff by the contracting officer, by the Armed Services Board of Contract Appeals (ASBCA, or the board), and by the trial judge. Of the four remaining issues still contested by plaintiff, the first is of prime importance since it affects the outcome of each of the others. This dispute, which the parties have come to call the floor-and-girder issue, was resolved by the trial judge in favor of defendant. We agree with his able analysis, much of which has been included in the following discussion.

On June 29, 1967, plaintiff contracted with the Navy to build a Naval Reserve Training Center near Wilkes-Barre, Pennsylvania. Construction was to begin on the date of the contract and to be completed by June 26, 1968, with liquidated damages of $200 per day thereafter.2 Plaintiffs delay in posting required payment and performance bonds prevented the commencement of work until July 18, 1967. Soon thereafter, a 40-day strike retarded plaintiff s progress further. For these and other reasons, little more than half the work was completed by the onset of the severe [189]*1891967-68 winter, and construction was not completed until sometime in 1969. One factor bearing on the pace of performance was the Government’s decision concerning the method of constructing the upper floors of the building, giving rise to the dispute aforementioned as central to this case.

The contract authorized a choice by the contractor between three methods of constructing the second and third floors. The alternatives permitted were precast, cast-in-place, and combination flooring. The first two methods of construction were described in drawings which were part of the contract; the third was not. The contract’s key references to combination floor construction were in section 3C.3.1 of the specifications, which provided, inter alia:

General. A combination floor system may be provided at the option of the Contractor in lieu of the precast and cast-in-place floor construction. The combination floor system shall consist of a joist and filler system providing monolithic floor construction integral with supporting beams and columns. * * * All work and materials shall be in accordance with the applicable requirements of specification 13Y except as modified herein.-

The language most hotly debated in this case is to be found in the phrase "providing monolithic floor construction integral with supporting beams and columns,” although in the view we take of the dispute, the language incorporating specification 13Y is also critical. We begin by examining the meaning of the terms "monolithic” and "integral.”

The parties accept as authoritative the definitions of the Concrete Reinforcing Steel Institute (CRSI),3 which defines the terms relevant to this dispute as follows:

integral — Elements which act together as a unit, such as concrete joists and top slab. Concrete members may be made integral by bond, dowels, or being cast in one piece. monolithic — Strictly interpreted, is concrete cast in one operation. Monolithic concrete elements may be designed [190]*190to act integrally, or as separate elements if articulated by weakened plane contraction joints. See Integrally-cast.4

Although plaintiff initially planned to use precast panel ' floors, after award it changed plans and elected to use the combination floor system for construction of the upper floors, selecting the "Omnia” system which was commercially available from Nyce-Crete Company. In September 1967 plaintiff submitted drawings illustrating the latter as its proposed construction method. The drawings showed that plaintiff would not be casting the floors and beams (also known as girders)5 monolithically but instead would use a construction joint6 to make them integral. Under this method plaintiff would be monolithically casting the floor, permitting it to harden, and then casting the concrete for the girders. The advantage would be that plaintiff would not need hanging forms because the forms for the girders could be set upon and supported by the floor. The drawings were approved by defendant in mid-September.

In October, however, defendant revoked its earlier approval of the drawings,7 claiming the use of construction joints was impermissible under the contract and insisting that monolithic construction of the floors and girders was required. The Government insisted that the floor and girders be formed in a single pour, or two pours completed before either could cure,8 believing that only monolithic construction could provide the strength necessary to ensure the soundness of the building.

Under protest, Framlau complied and constructed the floors and girders monolithically. It then sought an [191]*191equitable adjustment for the increased cost of complying with the Government’s instructions. The contracting officer, the board, and the trial judge all concluded that the Government’s insistence on a monolithic construction method was allowed under the contract. We agree.

We have noted that section 3C.3.1 incorporated by reference specification 13Y of the Bureau of Yards and Docks specifications. We should add that section 3C.2, also applicable only to combination floor construction, also mentioned the Bureau of Yards and Docks specifications, specifically incorporating by reference specification 13Yg thereof. The parties have stipulated that the referenced specification provides that "construction joints can only be placed or used where approved or where shown.” The other important specification is in the general notes on sheet 33 of the contract documents (entitled Column Schedule & Details Structural), which provides in section 3A: "Unless otherwise indicated all construction shall be monolithic.”

Plaintiffs construction of the phrase "monolithic floor construction integral with supporting beams and columns” emphasizes the word "integral.” Plaintiff uses the definition cited earlier to support its contention that the contract permitted plaintiff to employ any method, including the use of construction joints, which would achieve integration. Framlau contends that defendant knew how to specify that the flooring and girders be monolithic but instead chose to require only that they be integral, leaving the requirement of monolithic construction to apply to the floor construction alone. Plaintiff argues that defendant was obligated to approve any construction method achieving integration (a result which the CRSI Handbook indicates could be reached with construction joints) and that defendant could not properly insist on wholly monolithic construction. Framlau invokes our rule in WPC Enterprises, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
A-Transport Northwest Co. v. United States
38 Cont. Cas. Fed. 76,440 (Federal Claims, 1992)
Big Chief Drilling Co. v. United States
38 Cont. Cas. Fed. 76,418 (Court of Claims, 1992)
Hughes Communications Galaxy, Inc. v. United States
37 Cont. Cas. Fed. 76,307 (Court of Claims, 1992)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
District of Columbia v. C.J. Langenfelder & Son, Inc.
558 A.2d 1155 (District of Columbia Court of Appeals, 1989)
Gevyn Construction Corp. v. The United States
827 F.2d 752 (Federal Circuit, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)
Nebraska Public Power District v. Austin Power, Inc.
773 F.2d 960 (Eighth Circuit, 1985)
Entwistle Co. v. United States
32 Cont. Cas. Fed. 72,807 (Court of Claims, 1984)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
L'Enfant Plaza Properties, Inc. v. United States
31 Cont. Cas. Fed. 71,681 (Court of Claims, 1983)
Landram v. United States
229 Ct. Cl. 855 (Court of Claims, 1982)
Maryland Port Administration v. C. J. Langenfelder & Son, Inc.
438 A.2d 1374 (Court of Special Appeals of Maryland, 1982)
Medtronic, Inc. v. Catalyst Research Corp.
518 F. Supp. 946 (D. Minnesota, 1981)
S.S. Silberblatt, Inc. v. United States
228 Ct. Cl. 729 (Court of Claims, 1981)
Kurz & Root Co. v. United States
652 F.2d 69 (Court of Claims, 1981)
Wheeler Bros., Inc.
650 F.2d 291 (Court of Claims, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
568 F.2d 687, 24 Cont. Cas. Fed. 81,906, 215 Ct. Cl. 185, 1977 U.S. Ct. Cl. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/framlau-corp-v-united-states-cc-1977.