S.S. Silberblatt, Inc. v. United States

228 Ct. Cl. 729, 1981 WL 21469
CourtUnited States Court of Claims
DecidedJuly 2, 1981
DocketNo. 209-76
StatusPublished
Cited by5 cases

This text of 228 Ct. Cl. 729 (S.S. Silberblatt, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.S. Silberblatt, Inc. v. United States, 228 Ct. Cl. 729, 1981 WL 21469 (cc 1981).

Opinion

This construction contract case is before the court on cross-motions for summary judgment. Plaintiff contracted with the Post Office Department to build a postal facility in Oakland, California. At the completion of the construction, the Post Office Department was to lease the facility at an agreed rental. Plaintiff seeks Wunderlich Act review of a decision of the Postal Service Board of Contract Appeals (the Board) which denied three of plaintiffs claims.

We conclude that the Board’s decision on the first claim, which involves the recovery of interest as a part of the cost of contract performance, must be remanded to the Board with instructions to make additional findings of fact and conclusions of law.

Plaintiffs second claim is for interest at 8.5 percent on the value of its funds invested in the project, amounting to $134,361.56. The third claim is for interest on an award of damages by the Board and is based on the contention that the Contract Disputes Act of 1978 is applicable. Only questions of law are involved in these claims, and we hold that the Board’s decision thereon is correct as a matter of law, and should be affirmed.

The contract provided that all costs of construction were to be borne by the plaintiff, and that its compensation was to be provided through the rental payments. The contract [730]*730also stated that the Post Office Department, through a separate contractor, would install a mechanical mail processing system, and if the mechanization work was not completed in time, the Post Office Department would have the option either to accept the building and execute the lease, or order plaintiff to suspend work. Clause 44 of the agreement (suspension of work clause) provided that if without fault or negligence of the plaintiff, the performance of any part of the work was ordered suspended, delayed or interrupted for any unreasonable period of time, the contracting officer would make an adjustment for any increase in the cost of performance (excluding profit) necessarily caused by the unreasonable period of such suspension of work, delay or interruption.

Plaintiff claimed compensation for delay and disruption costs caused by the mechanization contractor and in proceedings before the Board, the parties stipulated that the Post Office Department had ordered a suspension of work for a period of 3-% months from September 15, 1969 to December 31, 1969. They also agreed that the lease which should have begun on September 15, 1969, actually began January 1, 1970. The Board determined that the plaintiff was entitled to recover the costs it had incurred as a result of the 3-% month delay and awarded plaintiff the sum of $250,567, which the parties stipulated was the amount of plaintiffs "direct costs.”

I.

Claim for Increased Interest As a Cost of Performance

The Board found that during the 3-% month period of delay, plaintiff had two outstanding loans—one for $17 million with the New York Bank for Savings, and one with the Chemical Bank in the amount of $1 million which, during the delay period, was increased to $2 million. The parties stipulated that interest on the $17 million loan during the delay amounted to $282,625. The Board also found that the funds from the Chemical Bank loan were commingled with other funds and were not maintained in a separate account for the Oakland facility. However, the [731]*731Board concluded that these funds were also used exclusively for the construction of the Oakland facility. The Board found that the Government had not contested plaintiffs claim that the interest paid on that loan during the delay period was $29,358. The Board also found that except for the fact that the loans continued to run and that plaintiff continued to pay interest on them, plaintiff presented no evidence showing that there was a change in its borrowing as a result of the delays.

The Board discussed this court’s decision in Bell v. United States, 186 Ct. Cl. 189, 404 F.2d 975 (1968), and concluded that under that decision, extra interest paid on borrowed money during a period of delay constitutes a compensable increase in the cost of performance. The Board also summarized our decisions in Dravo Corp. v. United States 219 Ct. Cl. 416, 594 F.2d 842 (1979); Singer Co. v. United States, 215 Ct. Cl. 281, 568 F.2d 695 (1977), and Framlau Corp. v. United States, 215 Ct. Cl. 185, 568 F.2d 687 (1977). The Board then concluded, that as a result of these later decisions, it is the present position of the court "that a contractor is entitled to receive payment for interest on borrowings only when the contractor clearly demonstrates that its borrowings were incurred or increased as the direct result of a requirement for additional funds to finance a contract change or a Government-caused delay.” We hold that the Board has misconstrued our decision in the cited cases; that our decision in Bell has not been modified or limited, and that under the suspension of work clause, the contractor is entitled to recover extra interest paid or incurred on existing loans as a direct result of the Government’s delay. Therefore, if it is found that plaintiff was required to pay or that it incurred additional interest on either or both of its outstanding loans as a direct result of the 3-% month delay, plaintiff would be entitled to recover the amount of interest so paid. On the other hand, if it is found that in view of plaintiffs loan arrangements and other circumstances, plaintiff would have paid or incurred the claimed interest on either or both of the loans even if the delay had not occurred, plaintiff would not be entitled to recover.

[732]*732We have reviewed the evidence in the administrative record and find that the court cannot make the findings of fact and conclusions of law which are necessary to resolve the issue. The question must therefore be remanded to the Board in order that it may make such additional findings of fact and conclusions of law as may be required.

II

Claim for the Value of the Use of Plaintiffs Invested Capital. During the Period of Delay

The Board determined that plaintiff had "committed approximately $5 million of its own funds in connection with the contract work,” but it made no finding as to the value of the use of these funds during the period of delay. Plaintiff claimed that these funds were impounded on the project during the delay period and that it is entitled to recover the sum of $134,361.56 for the value of the use of its funds, computed at an interest rate of 8.5 percent.

Relying on Dravo, the Board held that it had no authority to allow any recovery on the claim. We hold that the Board’s decision is correct as a matter of law and should be upheld. The use of equity capital is generally regarded as an element of profit. Ingalls Shipbuilding Division, Litton Systems, Inc., ASBCA No. 17579, 78-1 BCA 13,038; Lockheed Shipbuilding and Constr. Co., ASBCA 18460, 77-1 BCA 12,458; Baifield Industries, Division of A-T-O, ASBCA Nos. 13413, 13555, 17241, 77-1 BCA 12,308. The suspension of work clause contained in the contract before us expressly excludes any allowance for profit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Hoffman Construction Co. v. United States
32 Cont. Cas. Fed. 73,279 (Court of Claims, 1985)
Entwistle Co. v. United States
32 Cont. Cas. Fed. 72,807 (Court of Claims, 1984)
S.S. Silberblatt, Inc. v. United States
31 Cont. Cas. Fed. 71,734 (Court of Claims, 1983)
L'Enfant Plaza Properties, Inc. v. United States
31 Cont. Cas. Fed. 71,681 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
228 Ct. Cl. 729, 1981 WL 21469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ss-silberblatt-inc-v-united-states-cc-1981.