Singer Co. v. United States

568 F.2d 695, 24 Cont. Cas. Fed. 81,914, 215 Ct. Cl. 281, 1977 U.S. Ct. Cl. LEXIS 117
CourtUnited States Court of Claims
DecidedDecember 14, 1977
DocketNo. 132-75
StatusPublished
Cited by37 cases

This text of 568 F.2d 695 (Singer Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Singer Co. v. United States, 568 F.2d 695, 24 Cont. Cas. Fed. 81,914, 215 Ct. Cl. 281, 1977 U.S. Ct. Cl. LEXIS 117 (cc 1977).

Opinion

Per Curiam:

This case under the Wunderlich Act, 41

U.S.C. §§ 321, 322, comes before the court on cross-motions for summary judgment, and on the plaintiffs request for review of a report and recommended decision by Trial Judge John P. Wiese, filed by him pursuant to Rule 166(c), and affirming a decision of the Armed Services Board of Contract Appeals (ASBCA). It has been submitted on the briefs and oral argument of counsel.

Plaintiff excepted only to the trial judge’s recommended dispositions respecting Claim Items 9, 3.c, lO.d, and 11, and has offered no opposition to the recommendations of the trial judge on other items. Before us, oral argument was confined by both sides to Item 11.

Upon consideration thereof, the court agrees with the trial judge’s recommended decision respecting all claim items, and hereby affirms and adopts the same as the basis for its judgment in the case.

Item 11 demands that the equitable adjustment for changes should incorporate an allowance for the cost of [284]*284borrowing money to finance added work required by the constructive change orders on which such adjustment was allowed by the ASBCA, the amount thereof, absent interest, being $479,641. The Board denied this item as does the trial judge and as do we, but the trial judge alters the Board’s grounds somewhat. He takes the view in substance that the evidence before the Board, read most favorably to plaintiff, fails to establish a nexus or causal connection between the expenditures by plaintiff and the borrowings by plaintiffs corporate parent to provide cash for all its activities and those of its subsidiaries. He refers to a decisional trend by the ASBCA to allow interest not actually paid as such, "as an element of profit based upon the imputed value of the equity capital.” Plaintiff before us argued that the full scope of this new doctrine would make the nexus evidence found missing by the trial judge wholly irrelevant. But the case was not presented to the Board on any such theory, and the issue is not without its difficulties for us in view of the ancient doctrine disallowing interest against the Government, in the absence of express statute or contractual provision. E.g., Mescalero Apache Tribe v. United States, 207 Ct. Cl. 369, 518 F.2d 1309 (1975), cert. denied, 425 U.S. 911 (1976). Our decision here rests solely on the insufficiency of the showing before the Board as to plaintiffs and plaintiffs parent’s actual debt policy, how its debt structure was made up in the relevant period, and what connection extra work on constructive changes might have with that structure, all of which were things we could not judicially know and were essential to support Item 11 on the theory on which it was actually prosecuted. Nothing said or done in this case should be taken as intimating how interest or imputed interest should in general be dealt with in computation of equitable adjustments, where a contractor has financed additional work without contemporary reimbursement for it, nor what proof should be requisite to sustain a claim of that sort. This case stands on its own peculiar history. We note, however, that in a decision contemporaneous with this, another panel of this court grapples with the problem and establishes a precedent with respect to it. Framlau [285]*285Corp. v. United States, ante at 185.

It is, therefore, concluded that the Board decision was supported by substantial evidence, was not arbitrary or capricious, and was not contrary to law. The plaintiff is not entitled to recover, and its motion for summary judgment is denied. The defendant’s motion for summary judgment is granted and the petition is dismissed.

OPINION OF TRIAL JUDGE

Wiese, Trial Judge: In a contract with defendant dated May 3, 1962, plaintiff (also referred to herein as Librascope or the contractor) agreed to design and fabricate a Data Processing Subsystem which was to form the computer nucleus of a world-wide Air Force information gathering, recording and dispensing system — a logistics management tool to be known as the 473-L System. Plaintiff has alleged that in the performance of this contract, the Government ordered work beyond that required by the terms of the agreement, the costs of which are claimed to be compensable under the Changes clause of the contract. Following an unsuccessful presentation of its claims to the contracting officer, plaintiff appealed to the Armed Services Board of Contract Appeals,1 requesting that it be compensated in the amount of $3,918,000 on account of the alleged changes. The appeal was allowed in part and denied in part by the Board, which after reconsideration,2 awarded the contractor the sum of $479,641. Relying now on both sections of the Wunderlich Act,3 plaintiff appeals to this court certain of the claims that were denied by the Board. We affirm the Board’s denial of these claims.

I. Facts

The contract for the Data Processing Subsystem portion of the 473-L System resulted from a two-step advertised [286]*286procurement procedure. The proposal that plaintiff submitted in response to the Government’s request for technical proposals was incorporated into the contract. The original contract covered only what was termed the Interim Operational Capability (IOC) configuration of the Data Processing Subsystem, that is, one-half of a proposed paired system which, in its entirety, was to be referred to as the Complete Operational Capability (COC) configuration. The Government retained and eventually exercised its option to order the complete system.

Librascope had previously provided a computer system to the Federal Aviation Administration (FAA) which it believed to be similar to the Government’s contemplated 473-L System. Accordingly, in the instant situation, Librascope’s proposal envisioned use of this FAA computer as a baseline from which to develop the subsystem for the 473-L program. Also, that proposal relied significantly on the use of off-the-shelf components, a practice'which was encouraged by the Air Force.

The 473-L System was made up of three major hardware components: the Data Processing Subsystem (DPSS) which was to receive, process, store and dispense information received from other components of the system, the AUTODIN which was an existing world-wide Air Force communications network, and the Integrated Console Subsystem (ICSS) which was to be used to display information received from the Data Processing Subsystem. It was understood by all parties that a crucial aspect of contract performance would involve successful integration of these three major elements.

A number of other contractors were involved in the development of the 473-L System as a whole. In addition to contractors that supplied hardware elements, there were those that provided software and others who advised the Government on different technical aspects of the system. The Data Processing Subsystem was the first part of the 473-L System to be procured, although considerable work had previously been done by the Government (as well as other contractors) in preparation for the work of the Data Processing Subsystem contractor.

[287]*287Given its scope and complexity, effective administration of the procurement demanded the participation of several Government agencies and private contractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
SUFI Network Services, Inc. v. United States
105 Fed. Cl. 184 (Federal Claims, 2012)
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
Precision Pine & Timber, Inc. v. United States
81 Fed. Cl. 235 (Federal Claims, 2007)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
Jeffrey J. Tiburzi v. Department of Justice
269 F.3d 1346 (Federal Circuit, 2001)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
City of Miami v. Tarafa Const., Inc.
696 So. 2d 1275 (District Court of Appeal of Florida, 1997)
YRT Services Corp. v. United States
38 Cont. Cas. Fed. 76,512 (Federal Claims, 1993)
Municipality of Anchorage v. Frank Coluccio Construction Co.
826 P.2d 316 (Alaska Supreme Court, 1992)
Gulf Contracting, Inc. v. United States
37 Cont. Cas. Fed. 76,128 (Court of Claims, 1991)
Wilner v. United States
37 Cont. Cas. Fed. 76,101 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
568 F.2d 695, 24 Cont. Cas. Fed. 81,914, 215 Ct. Cl. 281, 1977 U.S. Ct. Cl. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/singer-co-v-united-states-cc-1977.