Wilner v. United States

37 Cont. Cas. Fed. 76,101, 23 Cl. Ct. 241, 1991 U.S. Claims LEXIS 195, 1991 WL 90446
CourtUnited States Court of Claims
DecidedMay 30, 1991
DocketNo. 404-89C
StatusPublished
Cited by20 cases

This text of 37 Cont. Cas. Fed. 76,101 (Wilner v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilner v. United States, 37 Cont. Cas. Fed. 76,101, 23 Cl. Ct. 241, 1991 U.S. Claims LEXIS 195, 1991 WL 90446 (cc 1991).

Opinion

OPINION

NETTESHEIM, Judge.

This construction contract case is before the court after trial on the merits. Melvin Wilner, d/b/a Wilner Construction Co. (“plaintiff”), seeks recovery for alleged government-caused delay arising in conjunction with construction of a building. At issue is whether any delays along the “critical path” leading to completion of the building were attributable to either the Government or the contractor or were unapportioned concurrent delays caused by both parties.

BACKGROUND

When the critical path is at issue, the Government may only be liable for delays that it caused if such delays occurred along that path. Broome Constr. v. United States, 203 Ct.Cl. 521, 528, 492 F.2d 829, 833 (1974). While not subject to concise definition,

[essentially, the critical path method is. an efficient way of organizing and scheduling a complex project which consists of numerous interrelated separate small projects. Each subproject is identified and classified as to the duration and precedence of the work. (E.g., one could not carpet an area until the flooring is down and the flooring cannot be completed until the underlying electrical and telephone conduits are installed.) The data is then analyzed, usually by comput[245]*245er, to determine the most efficient schedule for the entire project. Many subpro-jects may be performed at any time within a given period without any effect on the completion of the entire project. However, some items of work are given no leeway and must be performed on schedule; otherwise, the entire project will be delayed. These latter items of work are on the “critical path.” A delay, or acceleration, of work along the critical path will affect the entire project.

Haney v. United States, 230 Ct.Cl. 148, 167-169, 676 F.2d 584, 595 (1982); see also Fortec Constructors v. United States, 8 Cl.Ct. 490, 504-05 (1985) (the critical path method “breaks down the entire project into individual tasks and assigns a number of days anticipated to perform each task”), aff'd, 804 F.2d 141 (Fed.Cir.1986); G.M. Shupe, Inc. v. United States, 5 Cl.Ct. 662, 728 (1984) (“Delay involving work not on the critical path generally had no impact on the eventual completion date of the project.”). Robert Marshal Freas, a Senior Consultant with Warner Construction Consultants, Inc., who testified as defendant’s expert in the fields of critical path and delay analysis, defined the critical path as “the longest path in the schedule on which any delay or disruption ... would cause a day-for-day delay to the project itself____ Those activities must be performed as they are scheduled and timely in order for the project to finish on time____”

The critical path may continually evolve. After work commences, “items not originally on the critical path can become critical.” Fortec, 8 Cl.Ct. at 505 (citing Shupe, 5 Cl.Ct. at 728). Therefore, in order to grasp accurately the delays that a project takes on, the critical path should be updated regularly. Id. Plaintiff professes that he frequently created such updates, but only one “progress schedule,” made on October 5,1985, two months after the start of construction, is in evidence.1

Determining responsibility for delay is essential. A contractor typically may not recover if government-caused delay is concurrent with additional delay not caused by the Government, such as weather or contractor delay. E.g., Spirit Leveling Contractors v. United States, 19 Cl.Ct. 84, 96 (1989); Beauchamp Constr. v. United States, 14 Cl.Ct. 430, 437 (1988). This rule is less rigid than it may appear. As stated by the Federal Circuit:

The evidence cited ... is sufficient to uphold the ... factual finding that appellant caused the delay.
This conclusion, however, does not mean that appellant cannot prevail. The case the government relies on to support the proposition that a contractor cannot recover when there is concurrent delay, Merritt-Chapman & Scott Corp. v. United States, 528 F.2d 1392, 208 Ct.Cl. 639 (1976), did not hold that a contractor could not prove the government’s delay separate and apart from that chargeable to the contractor.
The general rule is that “[wjhere both parties contribute to the delay neither can recover damagefs], unless there is in the proof a clear apportionment of the delay and expense attributable to each party.” Blinderman [Const. Co., Inc. v. U.S.], 695 F.2d [552] at 559 [Fed.Cir. 1982], quoting Coath & Goss, Inc. v. United States, 101 Ct.Cl. 702, 714-715 (1944). Courts will deny recovery where the delays are concurrent and the contractor has not established its delay apart from that attributable to the government.

Klingensmith, Inc. v. United States, 731 F.2d 805, 809 (Fed.Cir.1984).

FACTS

On May 1, 1985, plaintiff submitted a sealed bid proposal to the United States Navy, Naval Facilities Engineering Command (“NAVFAC”), in response to Invitation for Bids N62474-83-B-2525 for construction of the approximately 8,000 [246]*246square-foot Location Exchange (the “project” or “building”) located in Margarita Area 33 of Camp Pendleton, California. The proposal also encompassed site improvements and gasoline islands. NAVFAC accepted plaintiffs bid price of $880,944.00 on July 3, 1985, and construction began on August 5, 1985.

Plaintiff, now retired, was the operator and owner of his company from 1961 to 1988. During the last ten years of plaintiffs involvement with his company, government contracts constituted approximately 90 percent of plaintiffs work. Plaintiff spent all of his time supervising construction of the Location Exchange, as well as construction of one other facility at Camp Pendleton. He had final authority over all correspondence his company made to the Officer in Charge of Construction (the “OICC”) and the Resident Officer in Charge of Construction (the “ROICC”).

Plaintiffs suit seeks equitable adjustment of the contract for delays arising in connection with this project. The original contract completion date was August 14, 1986. However, the building was not usable until March 10, 1987. As the cause of the setbacks in construction, plaintiff ascribes five broad items of government-caused delay, some of which involve the building itself and others which concern site work surrounding the building: 1) inaccurate specifications for fabrication and installation of hollow metal doors and frames, as well as for the attached finished hardware; 2) unclear dimensions of and installation requirements for precast concrete sills; 3) defective roofing plans; 4) numerous delays in receiving responses and clarifications from NAVFAC regarding site work; and 5) tardy installation of refrigerator boxes by NAVFAC. Defendant agrees that these items spawned delay, but disputes either its responsibility for and/or the relevance of these events. Each item of delay is addressed in turn. The evidence concerning these delays derived largely from the direct examination of plaintiff and from exhibits introduced during that examination.

1. Hollow metal doors and frames and finished hardware

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Mactec, Inc. v. Bechtel Jacobs Company, LLC
346 F. App'x 59 (Sixth Circuit, 2009)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
American Renovation & Construction Co. v. United States
45 Fed. Cl. 44 (Federal Claims, 1999)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
City of Miami v. Tarafa Const., Inc.
696 So. 2d 1275 (District Court of Appeal of Florida, 1997)
Al Munford, Inc. v. United States
40 Cont. Cas. Fed. 76,830 (Federal Claims, 1995)
Tyger Construction Co. v. United States
39 Cont. Cas. Fed. 76,627 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Wilner v. United States
26 Cl. Ct. 260 (Court of Claims, 1992)
C.B.C. Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,171 (Court of Claims, 1991)
Gulf Contracting, Inc. v. United States
37 Cont. Cas. Fed. 76,128 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,101, 23 Cl. Ct. 241, 1991 U.S. Claims LEXIS 195, 1991 WL 90446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilner-v-united-states-cc-1991.