Skip Kirchdorfer, Inc. v. United States

34 Cont. Cas. Fed. 75,481, 14 Cl. Ct. 594, 1988 U.S. Claims LEXIS 59, 1988 WL 31871
CourtUnited States Court of Claims
DecidedApril 6, 1988
DocketNo. 690-83C
StatusPublished
Cited by11 cases

This text of 34 Cont. Cas. Fed. 75,481 (Skip Kirchdorfer, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skip Kirchdorfer, Inc. v. United States, 34 Cont. Cas. Fed. 75,481, 14 Cl. Ct. 594, 1988 U.S. Claims LEXIS 59, 1988 WL 31871 (cc 1988).

Opinion

OPINION

NETTESHEIM, Judge.

This case was tried following reversal by the Federal Circuit of a decision for defendant on the parties’ cross-motions for partial summary judgment and remand for a determination of the amount of damages. Skip Kirchdorfer, Inc. v. United States, No. 85-2090 (Fed.Cir. Apr. 4, 1986) (un-publ.) 795 F.2d 1010. After the mandate issued on October 23, 1986, the parties asked that preparation for trial be deferred pending settlement negotiations.

At a status conference held on February 13, 1987, defendant advised that the possibility of settlement would be enhanced by a ruling on the measure of damages. Plaintiff sought damages for compensable excess service calls measured by the standard for breach of contract, including profit. Defendant took the position that damages should be measured by the additional costs sustained by plaintiff due to the breach. A briefing schedule was set, and defendant submitted its motion in limine as a motion for partial summary judgment as to damages, asking that plaintiff be awarded no damages since the costs incurred due to the breach did not exceed plaintiff’s estimated costs. On May 29, 1987, an order entered [597]*597denying defendant’s motion, cautioning that the total cost approach to damages is disfavored. Trial was scheduled and dates set for pretrial filings. Ultimately, the trial date was postponed twice to accommodate delays and other difficulties in completing discovery, the latter attributable to plaintiff’s slow production of documents. Only one of these postponements deserves mention.

The parties had stipulated to a methodology that plaintiff could use in proving its damages. During discovery plaintiff realized that it had not correctly followed the stipulation. In October 1987 plaintiff obtained the services of Touche Ross & Co. (“Touche Ross”) to review its damages analysis in order to verify, inter alia, the accuracy of the sample that formed the basis for its price per service call. Although the parties were hopeful that defendant could subscribe to the results of the Touche Ross verification and agree to the total number of compensable excess service calls, this did not occur, and defendant took sharp issue with the Touche Ross report. In connection with plaintiff’s expanded effort, the time for additional discovery was enlarged on November 10, 1987, thereby affording defendant the opportunity to retain an additional expert to testify on the recast. However, it was also ordered that this discovery, to which defendant agreed, should not postpone trial beyond the third trial date of January 19, 1988. Over two years had elapsed since this court’s liability decision in February 1985, and one year since issuance of the mandate by the appeals court in October 1986. Against this background defendant has no complaint that it was rushed to trial.

At trial plaintiff sought damages for breach of contract in the amount of $656,-919.56. Defendant put this claim in stark relief by taking the position that plaintiff should recover nothing.1

FACTS

Plaintiff Skip Kirchdorfer, Inc. (“plaintiff”), was awarded a fixed-price contract in the amount of $1,088,115.00 by the Department of the Air Force (the “Air Force”) to perform maintenance services on family housing units at Patrick Air Force Base, Florida. The major portion of the contract, referred to as CL1N0001 or Line Item No. 1, involved performance of service calls and other types of general maintenance.2 Line Items Nos. 2 and 3, which are not involved in this case, covered, respectively, a not-to-exceed figure for reimbursable materials and unit price quotations on painting the interior of housing units if the amount of surface to be painted exceeded 200 square feet. Against the Air Force’s estimate of $1,435,992 for Line Item No. 1, plaintiff bid $944,915.04, or $78,742.92 per month.

Plaintiff’s contract covered a 12-month period beginning on November 1, 1980, and concluding on October 30, 1981, a date subsequently changed to September 30, 1981. Despite the fact that plaintiff had notified the Air Force early on that it was experiencing service calls exceeding the number represented by the historical data, the Air Force, by a modification dated September 29, 1981, exercised its option to renew the contract for an additional one-year term from October 1, 1981, through September 30, 1982. There was no increase in the unit monthly price of $78,742.92 for the services and non-reimbursable materials during the second year.

Prior to bidding, prospective bidders were provided with historical workload data prepared by the Air Force. The Federal Circuit determined that the data represented that the total number of service calls historically required was 18,268 over a 22-month period, yielding a daily average [598]*598of 29.68 calls. Skip Kirchdorfer, Inc., No. 85-2090, slip op. at 2. The Federal Circuit also determined that plaintiff made 77.99 calls per day in contrast to the 29.68 represented. Id.3

Rejecting defendant’s contention that the manner in which the data were presented and the contractor’s acknowledgment of a discrepancy established a patent ambiguity, thereby obliging the contractor to put the Air Force on notice of the error, the Federal Circuit held that the contractor was entitled to “an accurate presentation of the historical data and to recovery for breach of contract in an amount which will compensate for its reliance on the substantial difference between the reported historical data and the correct figures. Womack v. United States, 182 Ct.Cl. 399, 389 F.2d 793 (1968).” Skip Kirchdorfer, Inc., No. 85-2090, slip op. at 3 (footnote omitted). This ruling is pivotal to the further proceedings before this court, since defendant rejects the notion that plaintiff is entitled to damages for breach. The Federal Circuit explicitly directed otherwise citing Womack, a case that characterized large variations between actual and estimated quantities as amounting to a misrepresentation and therefore a breach of contract. Womack, 182 Ct.Cl. 399, 412-13, 389 F.2d at 801. Defendant’s argument that plaintiff’s recovery should be limited to increased costs is buoyed by the last statement in the Federal Circuit’s opinion: “The government acknowledges at least $8,000 in increased labor costs....” Skip Kirchdorfer, Inc., No. 85-2090, slip op. at 6. However, at trial before this court the parties took the position that they did not know the source of the reference, and plaintiff has not pursued recovery of this amount denominated as increased labor costs. In these circumstances the court does not view the quoted language from the appellate court’s opinion as detracting from the direction that damages are to be measured by the standard for breach of contract, and the facts have been found accordingly.

Trial focused on two factual inquiries: the number of excess service calls for which plaintiff should be compensated and the price for each compensable excess service call, including labor, material, and travel time. This section of the opinion finds the facts that were not a product of expert analysis or reconstructed data.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hallwood Plaza, Inc. v. United States
84 Fed. Cl. 804 (Federal Claims, 2008)
Datalect Computer Services, Inc. v. United States
56 Fed. Cl. 178 (Federal Claims, 2003)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Bath Iron Works Corp. v. United States
40 Cont. Cas. Fed. 76,840 (Federal Claims, 1995)
Concrete Placing Co. v. United States
37 Cont. Cas. Fed. 76,267 (Court of Claims, 1992)
C. Mourer Construction, Inc. v. United States
37 Cont. Cas. Fed. 76,131 (Court of Claims, 1991)
Wilner v. United States
37 Cont. Cas. Fed. 76,101 (Court of Claims, 1991)
Maintenance Engineers, Inc. v. United States
36 Cont. Cas. Fed. 75,950 (Court of Claims, 1990)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
Neal & Co. v. United States
35 Cont. Cas. Fed. 75,683 (Court of Claims, 1989)
Skip Kirchdorfer, Inc. v. United States
35 Cont. Cas. Fed. 75,598 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,481, 14 Cl. Ct. 594, 1988 U.S. Claims LEXIS 59, 1988 WL 31871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skip-kirchdorfer-inc-v-united-states-cc-1988.