Neal & Co. v. United States

35 Cont. Cas. Fed. 75,683, 17 Cl. Ct. 511, 1989 U.S. Claims LEXIS 127, 1989 WL 73115
CourtUnited States Court of Claims
DecidedJuly 5, 1989
DocketNo. 340-87C
StatusPublished
Cited by3 cases

This text of 35 Cont. Cas. Fed. 75,683 (Neal & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neal & Co. v. United States, 35 Cont. Cas. Fed. 75,683, 17 Cl. Ct. 511, 1989 U.S. Claims LEXIS 127, 1989 WL 73115 (cc 1989).

Opinion

OPINION

NETTESHEIM, Judge.

This case is before the court after trial on the amount of the equitable adjustment due plaintiff. Plaintiff Neal & Company, Inc. (“plaintiff”), and the Army Corps of Engineers (the “Corps”) entered into fixed-price contract DACA 85-85-C-0006 dated November 16, 1984, in the amount of $1,680,000.00 for the repair and alteration of two tramways located at the Cape New-enham, Alaska Air Force Station (“AFS”), and Tin City, AFS.

BACKGROUND

The amended complaint set forth three causes of action. First, plaintiff claims that it had a forward-priced agreement to perform a change order, referred to by the parties as Case 4, to replace the cable for the tramway at Cape Newenham. Defendant denied the existence of any binding agreement, but conceded that plaintiff was entitled to an equitable adjustment for replacement of the tram cable. Plaintiff’s second claim is for an equitable adjustment upon a change order, which the parties refer to as Case 16, for repair of a tram car damaged at Cape Newenham following an accident that was the fault of another contractor. As its third claim, known as Case 29, plaintiff seeks damages based on a delay in a progress payment.

According to an audit conducted by the Defense Contract Audit Agency (the “DCAA”) dated July 8, 1988, the claim on Case 4 spans from January 1, 1986, through October 15, 1986; the Case 16 work began on August 18, 1985, and continued through November 4, 1985. Plaintiff frames Case 4 at June through October 15, 1986, and Case 16 at October through December 1985 and May 1986. Given these disparities and the fact that defendant does not contend that any one line item should be denied as beyond a claim period, the court has identified line items to defendant’s more inclusive time periods. Moreover, because plaintiff presents its Case 4 before Case 16, which itself took place earlier, this opinion follows suit.

On December 19, 1988, defendant moved in limine for an order preventing plaintiff from introducing evidence at trial that Case 4 was negotiated on a fixed-price basis and that the only evidence admissible regarding Case 4 should be the increased ■ costs that plaintiff incurred. In a bench ruling on February 17, 1989, the court granted defendant’s motion for several reasons. The proposed forward-priced agreement dated November 14, 1985, in the amount of $296,440.00 was negotiated for plaintiff by Craig Watts, one of the two Project Managers assigned to the contract, and for the Corps by its Resident Contracting Officer Patricia S. Opheen. On its face the proposal bore the legend written by Ms. Opheen, “Agreed subject to audit and Contracting Officer approval.” It was never [513]*513approved. Defendant also had established that Ms. Opheen lacked authority to enter into a binding agreement on behalf of the Corps in excess of $50,000.00. The November 14 proposal also bore the one notation “audit” by the item covering the cost of the cable. This was consistent with plaintiffs assertion that Ms. Opheen represented that the audit was to be restricted to overhead rates and the value of the Swiss franc for the cost of the cable. In granting defendant’s motion in limine, and thereby requiring plaintiff to prove its increased costs, the court allowed plaintiff to show that any deficiencies in its proof are due to plaintiff’s acting on such a representation.

For all practical purposes, trial was confined to the amount of the equitable adjustment due on Cases 4 and 16. Plaintiff offered no evidence that its letter of December 6, 1986, with respect to Case 29 was signed, which had the effect of foreclosing, as a matter of law, recovery for any period beyond September 28, 1987, the date upon which the Corps received a certified claim, signed on behalf of plaintiff, for interest on a delayed progress payment. See J.M.T. Mach. Co. v. United States, 826 F.2d 1042, 1045-46 (Fed.Cir.1987). Therefore, on the basis of the record before the court, plaintiff has not established its entitlement to any amount beyond $82.95 that the Corps has paid on this claim.

It is plaintiff’s position in its revised cost summaries submitted after trial that it was entitled to $328,994.00 for Case 4, of which amount plaintiff asserts that it was able to document $292,999.97. With respect to Case 16, plaintiff claimed $188,-038.00 before trial; now it asserts that $119,201.88 has been documented.1 In its pretrial memorandum defendant took the position that since the Corps had paid plaintiff $250,000.00 (the amount actually was $236,399.00) on account of Case 4 and the DCAA audit determined that plaintiff could support only $187,166.00, plaintiff has been overpaid $62,834.00, for which defendant counterclaimed.2 At trial defendant stipulated to additional amounts due on this claim. However, defendant’s post-trial response to plaintiff’s corrected cost summaries retracted without explanation approximately $30,000.00 of its concession made in its prior submissions and at trial. Regarding Case 16 defendant contended at trial that the Corps has paid plaintiff $23,902.57 and that the DCAA audit revealed that plaintiff could support approximately $71,-054.00 in costs, so that plaintiff is entitled to recover approximately $47,151.43.

Counsel were advised before trial to consult the discussion on proof of damages in Skip Kirchdorfer, Inc. v. United States, 14 Cl.Ct. 594, 605-07 (1988), and they agreed that the legal standards set forth controlled. Although Skip Kirchdorfer is a breach of contract case, the law is applicable to plaintiff’s claim for an equitable adjustment. William Green Constr. Co. v. United States, 201 Ct.Cl. 616, 626, 477 F.2d 930, 936 (1973), cert. denied, 417 U.S. 909, 94 S.Ct. 2606, 41 L.Ed.2d 213 (1974); J.D. Hedin Constr. Co. v. United States, 171 Ct.Cl. 70, 86, 347 F.2d 235, 246 (1965). The contractor bears the burden of proving the amount of its damages. Roberts v. United States, 174 Ct.Cl. 940, 956, 357 F.2d 938, 949 (1966). As stated in Skip Kirchdorfer, a contractor in a claim situation is not required to segregate costs attributable to a change order; however, the claimant must present reasonably satisfactory proof of increased costs based on acceptable cost allowance principles or expert testimony, so that the determination of the amount of damages will be more than mere speculation. The hallmark of allowability of any item of increased costs is its reasonableness.

[514]*514The exchange of correspondence between plaintiff’s representatives and authorized contracting representatives of the Corps, specifically the January 5, 1987 letter to plaintiff from James R. Yolz, Resident Contracting Officer, demonstrates that both plaintiff and the Corps approached Case 4 on the basis that so-called “judgmental” items, such as equipment and labor hours, field supervision, and management expenses, were not subject to audit, but that the factual rates applied to these items were. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White Buffalo Construction, Inc. v. United States
52 Fed. Cl. 1 (Federal Claims, 2002)
C. Mourer Construction, Inc. v. United States
37 Cont. Cas. Fed. 76,131 (Court of Claims, 1991)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,683, 17 Cl. Ct. 511, 1989 U.S. Claims LEXIS 127, 1989 WL 73115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neal-co-v-united-states-cc-1989.