Gulf Contracting, Inc. v. United States

37 Cont. Cas. Fed. 76,128, 23 Cl. Ct. 525, 1991 U.S. Claims LEXIS 272
CourtUnited States Court of Claims
DecidedJune 28, 1991
DocketNo. 90-42C
StatusPublished
Cited by11 cases

This text of 37 Cont. Cas. Fed. 76,128 (Gulf Contracting, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf Contracting, Inc. v. United States, 37 Cont. Cas. Fed. 76,128, 23 Cl. Ct. 525, 1991 U.S. Claims LEXIS 272 (cc 1991).

Opinion

OPINION

MARGOLIS, Judge.

This government contracts case is before the court on cross-motions for summary judgment. Plaintiff contractor entered into a contract to construct buildings for the defendant. The contractor and its subcontractor claim compensation for delay, return of liquidated damages, and reimbursement of interest expenses on borrowings and expert consultant fees, allegedly caused by a change to the contract. The Armed Services Board of Contract Appeals (“ASBCA”) in its first opinion agreed that there was a constructive change to the contract. In its second opinion, the ASBCA awarded direct costs resulting from the change, but denied the contractor’s other claims for relief. In its third decision, the ASBCA denied the contractor’s motion for reconsideration. The plaintiffs appeal the adverse decisions of the ASBCA under the Wunderlich Act, claiming that portions of the ASBCA’s decisions should be reversed as arbitrary and capricious, not supported by substantial evidence, and based on errors of law. The defendant asserts that the ASBCA’s decisions are supported by substantial evidence in the record and should not be disturbed. After careful review of the record, and after hearing oral argument, this court upholds the ASBCA’s decisions, and accordingly denies the plaintiffs' motion for summary judgment and grants the defendant’s motion for summary judgment.

FACTS

Plaintiff Gulf Contracting Inc. (“Gulf”) was awarded a $6,729,000 contract on May 19, 1975 for the construction of an enlisted men’s barracks complex at Fort Gordon, Georgia (“the project”). Plaintiff Hughes Masonry Company, Inc. (“Hughes”) was Gulf’s masonry subcontractor for the project. The U.S. Army Corps of Engineers, Savannah District (“Corps”) administered the project under Contract No. DACA21-75-C-0115.

The contract was scheduled to be performed between June 16, 1975 and November 7,1976. The scheduled completion date was extended 195 days through contract modifications to May 21, 1977. Gulf finished the project 147 days beyond the extended contract completion date, completing the gymnasium on October 15, 1977. The government assessed and withheld $29,106 in liquidated damages as a reuslt of this delay in completion.

Gulf submitted a critical path network that sequenced the construction work for government approval. The approved schedule was intended to be used by Gulf to plan, organize and direct the work. Progress on the schedule, as updated during the project, was used to determine Gulf’s progress payments. Gulf and the government updated the critical path schedule each month between August 1975 and May 1977. A final update was prepared on October 12, 1977, when the project was nearly complete. Major changes to the approved network during the course of the project, particularly those expected to affect contract completion dates, required written notification of the contracting officer.

Gulf’s work on the barracks complex involved construction of seven barracks buildings and seven related support buildings including a gymnasium. As its overall scheme of sequencing work on the project, Gulf planned to prosecute work on the barracks as a group. Work on the support buildings was to take place concurrently and be prosecuted as a separate group. The original critical path schedule identi[527]*527fied the support buildings as the critical path to completion of the project. The critical path remained in the support building construction throughout the project with the exception of a shift to barracks in December 1976 associated with a late start of prefabricated shower units.

In erecting the barracks, Gulf elected to lay large planks of pre-cast, pre-stressed concrete, called Quad-Ts, to form the second and third level barracks floors. To anchor the Quad-Ts, Gulf had to weld the Quad-T stems to imbeds in the exterior and interior masonry walls.

Gulf initially contemplated that it would weld the Quad-Ts to both the exterior and interior walls prior to pouring the concrete topping that served to level the floor surface. The Corps instead directed Gulf to weld the exterior ends, pour topping in the bedroom areas to load the Quad-Ts, allow the topping to cure, and then weld the remaining interior ends and pour topping on the corridor floor areas. This meant that Gulf had to weld and pour topping at two separate times, necessitating the recall of welding, masonry, and concrete work crews multiple times to the same work areas which disrupted its planned production sequence. Gulf needed to erect temporary forms to contain the concrete topping when it was poured in these separate areas, adding about 80 lineal feet of forming to the requirements for each “pod” of the barracks. Certain procedures became more difficult to perform. For example, the interior end welding had to be performed from the floor beneath rather than from above as originally contemplated.

In its first opinion in this case, the ASBCA considered the Quad-T issue and stated in its findings of fact that the government’s Quad-T directive “caused some delays with regard to [Gulf’s] work as well as the work performed by its masonry and erector subcontractors.” Gulf Contracting, Inc., ASBCA Nos. 27221 et al., 84-2 B.C.A. (CCH) II 17,472, at 87,065 (1984). The ASBCA found “that the Government’s oral directive was the equivalent of a change order, that it caused [Gulf] to perform in a manner different than it had planned, and that to the extent [Gulf] incurred greater expense as a result, it is entitled to an equitable adjustment under the contract’s ‘Changes’ clause.” Id. at 87,066.

The Board remanded the Quad-T matter to the contracting officer “for further negotiation on the question of quantum.” Id. at 87,068. Negotiations failed to resolve the question, and the parties returned to the ASBCA for resolution of the quantum issue. In its second opinion, the ASBCA acknowledged that the Quad-T directive resulted in additional direct costs and awarded $24,362 to Gulf for these costs. However, the ASBCA concluded that Gulf was not entitled to compensation for delay to the project, loss of efficiency, refund of the assessed liquidated damages, interest expense on borrowings, or expert consultant fees for a report prepared by Vinson & Associates. Gulf Contracting, Inc., ASBCA Nos. 30195 et al., 89-2 B.C.A. (CCH) 1121,812 (1989). On Gulf’s motion for reconsideration, the ASBCA affirmed its earlier decision denying Gulf compensation for items other than direct costs. Gulf Contracting, Inc., ASBCA Nos. 30195 et al., 90-1 B.C.A. (CCH) 1122,393 (1989).

STANDARD OF REVIEW

The ASBCA’s adverse decisions were appealed by Gulf and Hughes to this court, invoking jurisdiction under 28 U.S.C. § 1491(a)(1), and review under the Wunderlich Act, 41 U.S.C. §§ 321, 322. In a Wunderlich Act case, this court “may not take new evidence or redetermine the facts, and limits its review to the record developed before the agency.” Titan Pacific Construction Corp. v. United States, 17 Cl.Ct. 630, 632 (1989), aff'd mem., 899 F.2d 1227 (Fed.Cir.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2025
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
ADP Marshall, Inc. v. NORESCO, LLC
710 F. Supp. 2d 197 (D. Rhode Island, 2010)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
United Computer Supplies, Inc. v. United States
43 Fed. Cl. 351 (Federal Claims, 1999)
City of Miami v. Tarafa Const., Inc.
696 So. 2d 1275 (District Court of Appeal of Florida, 1997)
Town Center Management Corp. v. United States
39 Cont. Cas. Fed. 76,691 (Federal Claims, 1994)
Round Place, Inc. v. United States
39 Cont. Cas. Fed. 76,699 (Federal Claims, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,128, 23 Cl. Ct. 525, 1991 U.S. Claims LEXIS 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-contracting-inc-v-united-states-cc-1991.