Round Place, Inc. v. United States

39 Cont. Cas. Fed. 76,699, 31 Fed. Cl. 749, 1994 U.S. Claims LEXIS 167, 1994 WL 460591
CourtUnited States Court of Federal Claims
DecidedAugust 18, 1994
DocketNo. 90-227C
StatusPublished
Cited by4 cases

This text of 39 Cont. Cas. Fed. 76,699 (Round Place, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Round Place, Inc. v. United States, 39 Cont. Cas. Fed. 76,699, 31 Fed. Cl. 749, 1994 U.S. Claims LEXIS 167, 1994 WL 460591 (uscfc 1994).

Opinion

OPINION

SMITH, Chief Judge.

This matter is before the court on plaintiffs motion for summary judgment and defendant’s cross-motion for summary judgment. This matter is an appeal to the court, pursuant to the Wunderlich Act, 41 U.S.C. §§ 321-322 (1988), from a decision by the Agriculture Board of Contract Appeals (AGBCA or Board) concerning a construction contract. The contract involved the construction of a floodwater retaining structure at the Lower Running Water Draw Watershed, Site 2, in Hale County, Texas, under the jurisdiction of the Soil Conservation Service, United States Department of Agriculture. Following careful consideration of the briefs and case law, and oral argument, the court must deny plaintiffs motion and grant defendant’s motion.

FACTS1

A firm fixed-price construction contract for a flood water retaining structure was awarded by the Soil Conservation Service, United States Department of Agriculture, to Round Place, Inc., on May 27, 1976. The contracting officer issued a final decision on October 26, 1977, denying four claims for additional compensation and a claim for remission of liquidated damages. This decision was then appealed to the AGBCA.

On March 12,1980, the AGBCA conducted a trial at which plaintiff acted pro se. Plaintiff presented claims for: (1) a differing site condition; (2) changes and constructive changes to its contract due to the government’s interpretation of contract specifications; (3) delay caused by adverse weather conditions justifying a time extension and remission of liquidated damages; (4) delays caused by the government due to construction operations necessitated by the government’s interpretation of contract specifications; and (5) changes due to additional quantities of work ordered by the government in connection with de-watering and water diversion at the project. Each claim pertained to work performed only by plaintiff, the sole contractor on the project.

On March 14, 1984, the AGBCA denied plaintiffs claims in their entirety. The plaintiff filed a Motion for Reconsideration in April 1984, which was denied on August 23, 1984. The plaintiff appealed to this court on March 14, 1990, under the Wunderlich Act. Plaintiff contends that the Board’s decision and findings are not supported by substantial evidence or are contrary to law. Defendant cross-moves for summary judgment.

[751]*751DISCUSSION

This action involves Round Place’s claim for expenses resulting from their five claims. This court must decide whether substantial evidence supports the AGBCA decision. Both parties agree that the Wunderlich Act principles apply to this case.

Standard of Review 2

In reviewing the Board’s decision, this court does not make independent factual findings, but examines the sufficiency of the Board’s findings. 41 U.S.C. § 321 (1988). The Wunderlich Act permits the court to determine whether the Board’s legal determinations were erroneous. Maitland Bros. Co. v. United States, 20 Cl.Ct. 53, 60 (1990), citing National Civil Ser. League v. United States, 226 Ct.Cl. 478, 643 F.2d 768 (1981). See also Koppers Co. v. United States, 186 Ct.Cl. 142, 147, 405 F.2d 554, 557 (1968). The court may also determine whether the Board’s factual findings are fraudulent, arbitrary, capricious, or unsupported by substantial evidence. Id. Plaintiff contends that the Board acted contrary to law and that their action was not supported by substantial evidence.

A plaintiff challenging the factual findings of a board faces a heavy burden of establishing that the findings are not supported by substantial evidence in the record. Gulf Contracting, Inc. v. United States, 23 Cl.Ct. 525, 528 (1991), aff'd without op., 972 F.2d 1353 (Fed.Cir.1992). Although the court is not bound by a board’s determinations of questions of law, careful consideration and great respect should be accorded to a board’s interpretation of a contract’s requirements. Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).

Nature of Plaintiff’s Challenge

In order for plaintiff to prevail, it must specifically demonstrate which finding or findings this court should reject, identifying specifically “the facts and circumstances contained in the Board’s record ... which make the Board’s decision lacking in substantial evidence.” Jefferson Constr. Co. v. United States, 177 Ct.Cl. 581, 589, 368 F.2d 247, 252 (1966). However, in the instant case plaintiff failed to address any specific findings and, therefore, the court cannot find that Board’s decision lacked substantial evidence. Thus, the court accepts as correct all the Board’s findings of fact. Milmark Serv., Inc. v. United States, 731 F.2d 855, 859 (Fed.Cir.1984).

Plaintiff also argues that there was clear error of law. However, the court finds no indicia of such, as is explained more fully below. Although plaintiff cannot prevail because specific findings of fact were not contested, this court also looks at the merits of the specific claims.

1. Differing Site Condition Claim

Plaintiff argues that the contract drawings and test soil borings represented the condition of the soil at the project whereby work for the most part involved excavation and compaction of silty clay materials. However, plaintiff maintains that the conditions were 75% sand instead of silty clay therefore requiring plaintiff to change the construction operation and haul material from other areas in order to construct the dam. Plaintiff states that it needed to stockpile materials and had irregular work activities which increased the cost of performance and time of completion.

An express representation in a contract specification or drawing furnished by the government to the contractor depicting specific conditions on a site can result in Type 1 Differing Site Conditions, if other conditions are encountered during construction. Fehlhaber Corp. v. United States, 138 Ct.Cl. 571, 584, 151 F.Supp. 817, 825, cert. den., 355 U.S. 877, 78 S.Ct. 141, 2 L.Ed.2d 108 (1957). This was held to be the case despite the fact that the government had stated that the specific data was informational only and that cavetory and exculpatory provisions were included to relieve the government of liability for such representations. [752]*752Id. 151 F.Supp. 817, 138 Ct.Cl. at 583-84. Plaintiff argues that the dispute as to what is indicated by the contract document is a question of law to be decided independently of the Board’s decision. Foster Constr. C.A. & William Bros. v. United States, 193 Ct.Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Veteran Construction, Inc. v. United States
121 Fed. Cl. 346 (Federal Claims, 2015)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,699, 31 Fed. Cl. 749, 1994 U.S. Claims LEXIS 167, 1994 WL 460591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/round-place-inc-v-united-states-uscfc-1994.